Clicky

Administrative Policies and Procedures 

1 Who is authorized to interpret the local plumbing code?
Incorrect. Please choose another answer.
Only a licensed code officer is empowered to interpret the code. (IPC 104.2; UPC 103.1). All code decisions are subject to a code officer's interpretation. An appeal can be made if the decision is questionable. Anyone can interpret the plumbing code, but the only decision which counts is the one made by a licensed code officer or an authority having jurisdiction.
2 A plumbing permit is required for the replacement of which of the following?
Incorrect. Please choose another answer.
Pipe and fixtures to be replaced require a permit. (IPC 105.2; UPC 104.2; 502.1). A water closet may be removed and reinstalled in order to clear a stoppage, replace a leaking wax seal or after a new floor has been installed but a water closet cannot be replaced without a permit.
3 Alterations to an existing plumbing system must not ___________________.
Incorrect. Please choose another answer.
Most alterations and repairs to existing plumbing systems are required to comply with current code requirements. There can be some exceptions to this that are available if a variance is applied for and received. An example of this could be when an existing fixture is not vented and current code requires an individual vent for the fixture. You may be able to obtain a variance from a code officer that will allow the installation of a mechanical vent instead of installing a vent pipe where it would be a hardship to do so. Minor alterations to existing plumbing have to comply with current code requirements, but the existing parts of the plumbing system do not have to be changed and brought into compliance with the current code. In no case can any plumbing work cause a plumbing system to become unsafe. Making changes that are detrimental to a plumbing system are never acceptable.
4 Approved plans are required to be kept on a job site and available for inspection on demand by a code officer.
Incorrect. Please choose another answer.
True- Before a plumbing permit is issued a set of plans and specifications are submitted to the code enforcement office. Once they are approved, a code officer will stamp them as approved and sign them. These become the official plans and specs for a job. This being the case, a copy of the stamped and signed plans and specifications must be kept on the job site at all times for review by a plumbing inspector. (IPC 105.5.7; UPC 104.4.6).
5 The replacement of a water heater requires a plumbing permit and a code inspection.
Incorrect. Please choose another answer.
True- A water heater is a plumbing fixture that requires a permit and an inspection even when it is replaced in the exact location of an existing water heater. (IPC 1052.; UPC 104.2). Why is this the case? Because water heaters are potential bombs. If a water heater is installed without a proper temperature-and-pressure relief valve, the pressurized vessel (the water heater) can explode due to excessive temperature or pressure.
6 Assume that you are making minor repairs to a residential plumbing system. In this case you are replacing a kitchen faucet, repairing a dripping valve in the water distribution system and replacing the lower element in an electric water heater. Based on this scenario, which of the following is true?
Incorrect. Please choose another answer.
Minor plumbing repairs do not require the issuance of a permit or an inspection. Plumbers are allowed to fix leaks, replace defective trap arms, replace faucets and similar repairs without any need for a permit. It is even permissible to replace toilets and bathing units in their exact same locations without a permit. Some states do not require a licensed plumber to make such repairs. However, if a fixture location is changed when it is replaced a permit is required.
7 Only master plumbers are allowed to obtain plumbing permits.
Incorrect. Please choose another answer.
False - Plumbing code regulations allow homeowners to obtain plumbing permits for work to be done on their own residences when the homeowners will do the work themselves. (IPC 105.3; UPC 104.3).
8 The use of previously used plumbing materials is prohibited for second use in a plumbing system.
Incorrect. Please choose another answer.
False - Used plumbing materials can be reused under certain conditions. All materials must be of an approved type. They must be in good working order. A plumbing code officer must approve the use of the specified materials. When these conditions are met it is allowable to reuse previously used plumbing parts and fixtures.
9 Who is allowed to apply for a plumbing permit?
Incorrect. Please choose another answer.
The codes allow a home owner and his or her authorized agent or contractor to apply for permits. (IPC 105.1; UPC 104.3). Journeyman plumbers are not typically allowed to apply for plumbing permits, since they have not yet become contractors. Journeyman plumbers are usually required to work under the indirect supervision of a master plumber. A master plumber can be a contractor, and obtain a plumbing permit. Homeowners who will perform their own plumbing work on their own homes are allowed to obtain permits. However, a homeowner is not allowed to obtain a plumbing permit and then allow some other person to do the plumbing work. Property owners are only allowed to be issued plumbing permits when the property where the work will be performed by the owner is the owner's personal residency. In other words, landlords are not allowed to obtain their own plumbing permits.
10 Assume that you will be involved as a plumber in the demolition of a structure. This work will require that all utilities to the building be cut off and separated from the systems within the building. When this is the case a plumber must remove any existing water meter provided by a municipality in the water distribution system and any sewer connection to a building sewer.
Incorrect. Please choose another answer.
False - Most municipalities prohibit plumbers from working on municipal plumbing parts and systems. This can apply to piping, water meters, pressure-reducing valves, piping, fittings, and other devices. Normal procedure is for a plumber's work to end within a five-foot range of the foundation of a structure. There are exceptions to this rule. Any local jurisdiction can define their own rules on who may service, repair, install or remove municipal plumbing devices.
11 For the issuance of a plumbing permit which of the following is normally required?
Incorrect. Please choose another answer.
All permit applications must be accompanied by a full description of the work to be done. Larger jobs, such as plumbing a bathroom addition, a home, or a commercial building require a set of plans to be submitted with a permit application. Specifications are also required for all plumbing permits. The specs must detail all materials to be used in a job. Permit applications require the physical address of the property to receive plumbing services. Normally, the name of the property owner is also required.
12 Once you obtain a journeyman plumbing license you are entitled to operate as a self-employed, full-service plumber.
Incorrect. Please choose another answer.
False - Journeyman plumbers are required to work under the indirect supervision of a master plumber. Therefore, journeyman plumbers are not allowed to be self-employed plumbers. However, anyone can own and operate a plumbing business if they have a master plumber employed by the company. So, a journeyman plumber could hire a master plumber and open a plumbing business. But without a master plumber, a journeyman cannot operate a full-service plumbing business. Some states do allow journeyman plumbers to work on their own in doing simple repairs and replacements that do not require the issuance of a plumbing permit.
13 Assume that a plumbing permit has been issued for the plumbing of a new home. The plumbing contractor has been waiting longer than expected for the building contractor to have the home ready for plumbing work to begin. There is a chance that the plumbing permit could become invalid if work is not started soon. At what point after a plumbing permit is issued can it become invalid if work is not begun?
Incorrect. Please choose another answer.
A code officer has latitude in deciding if a permit will be rendered invalid for a lack of work being started within six months of the issuance of a permit. (IPC 105.5.3; UPC 104.4.3). By code, the work must begin within the first six months of the issuance of a permit. This is the rule under both the IPC and UPC. However, you should check with your local jurisdiction, as they have authority to set their own time periods. There are times when weather or other uncontrollable issues prohibit the timely commencement of work. When this is the case a code officer can offer an extension of time for work to be begun.
14 Alterations made in an existing plumbing system are required to comply with current code requirements for plumbing systems.
Incorrect. Please choose another answer.
True - Any plumbing alteration is expected to comply with current code requirements. At no time can an alteration be detrimental to a plumbing system or render the system unsafe. Some plumbers think that existing plumbing systems are exempt from current code requirements. This is true if the system is in safe operating condition. But, the moment an alteration to the system is made the alteration must be within current code requirements. However, the existing plumbing that is not being altered is not required to be upgraded to current code compliance.
15 Assume that a plumbing permit was issued for a new plumbing installation. The work started about one month after the permit was issued. During the rough-in phase of plumbing the property owner ran into financial problems and was forced to put the project on hold. At what point from the time that plumbing work was stalled can the permit be rendered invalid?
Incorrect. Please choose another answer.
Occasionally work is started on a job and then grinds to a halt. For example, the underground plumbing may be put in and the concrete contractor may delay further plumbing work. Or, the framing contractor may move slowly and prevent the plumbing contractor from moving forward quickly. Through no real fault of the plumber a job can be stalled. If plumbing work is stalled for more than six months the existing plumbing permit can be determined to be invalid. (IPC 105.5.3; UPC 104.4.3). This decision is up to the local plumbing inspector.
16 It is a violation of the plumbing code to change the use of a property. As an example, if a residential home is converted to professional office space it is a violation of the plumbing code.
Incorrect. Please choose another answer.
True - Plumbing codes require different minimum standards for various types of building uses. For example, the minimum number of fixtures required for a building can vary substantially based on the use of a building. Accessibility requirements that do not apply to a residence can apply to an office building or business. There are several situations where everything from pipe sizing to the number of fixtures required can be different for various types of building uses. In order to change the use of a building within compliance to code requirements a plan and specifications must be submitted to the code enforcement office for approval.
17 Which of the following requires a journeyman plumbing license?
Incorrect. Please choose another answer.
Anyone may own a plumbing company provided a Master Plumber is employed by that company and has a current Master License. A homeowner is exempt from plumbing license law requirements but may have to obtain a plumbing permit to perform plumbing work on his homestead. Commercial plumbing jobs require at least a Journeyman license to perform work under the general supervision of a Master Plumber.
18 The provisions for licensing are determined by which of the following:
Incorrect. Please choose another answer.
The authority having jurisdiction determines the provisions for licensing. State Plumbing Boards determine requirements and provide testing of qualified applicants to become licensed. Plumbing inspectors enforce codes adopted by the AHJ.
19 An application for a building permit on a job which includes new plumbing must include all of the following, except:
Incorrect. Please choose another answer.
All items listed above, except estimated cost of materials are required on an approved plan. Some municipalities base plumbing permit fees on fixture units or estimated cost of total job, but not on material costs.
20 In situations where general provisions of the code conflict with more specific provisions of the code, which shall prevail?
Incorrect. Please choose another answer.
When there is a conflict between general provisions and more specific provisions of the plumbing code, the more specific provisions will prevail in code interpretation. (IPC 102.1; UPC 102.1).
21 A plumbing system may be ordered to be removed by the plumbing authority if the following exists:
Incorrect. Please choose another answer.
Any of these conditions can prompt the plumbing authority to order the system to be removed or placed in a safe and sanitary condition.
22 Who, or whom, has the authority to disconnect a plumbing system from utilities in the event of an immediate hazard to life or property?
Incorrect. Please choose another answer.
The plumbing authority has the power to disconnect a plumbing system from utilities in the event of an immediate hazard to life or property. The utility company can shut down the utility (i.e. natural gas), but they do not have the authority to disconnect a plumbing system. The Code states that the authority having jurisdiction shall have the authority to disconnect the plumbing system to a building, structure, or equipment regulated by the code in case of emergency, where necessary, to eliminate immediate hazard to life or property. In most scenarios, a municipality controls the water supply and the sewer to structures they supply.
23 A plumbing permit is required if the following work is to be performed:
Incorrect. Please choose another answer.
Replacing a VTR with an auto-vent under a sink would require termination and alteration of existing plumbing and, thus require a permit. (IPC 105.2; UPC 104.2; 502.1). A plumber may replace parts of a valve and remove and reset the same toilet without altering the existing plumbing system and all service calls are not subject to obtaining a permit.
24 The code enforcement office may, in writing, suspend or revoke a permit if:
Incorrect. Please choose another answer.
If an employee of the plumbing authority issues a permit erroneously or has been supplied with incorrect information it may be suspended or revoked. If the person performing the plumbing work on the permitted job is not licensed, a citation may be written by a field inspector.
25 Which of the following mediums can be used to test a water supply system using PVC?
Incorrect. Please choose another answer.
The codes do not allow air to be used to test plastic piping. (IPC 312.3; UPC 609.4). Potable water should be used and the system must prove tight under the working water pressure of the system for at least 15 minutes.
26 A water test is being utilized to test a drainage and vent system in a home. Which of the following statements are true with regards to carrying out the test?
Incorrect. Please choose another answer.
All of the openings of the drainage and vent system must be closed, except the highest opening, in a water test of a drainage and vent system. (IPC 312.2; UPC 712.2). The system to be tested must be filled with water to the point of overflow. The water pressure must be held for at least 15 minutes to complete the test.
27 The standards differ between a jurisdiction's plumbing code and building code on a plumbing issue involved in a construction project. Which code should be followed on a plumbing matter covered by the plumbing code?
Incorrect. Please choose another answer.
The IPC and UPC both give precedence to the plumbing code over other mechanical codes when there is a conflict between them on a plumbing issue covered by the plumbing code. (IPC 102.8.1; UPC 102.1).
28 The manufacturer's instructions for the installation of a faucet are more stringent than and conflict with the provisions of the more general standards of the plumbing code. Which should the plumber follow?
Incorrect. Please choose another answer.
Where the code conflicts with a manufacturer's installation instructions, the most stringent of the two will prevail and must be followed. (IPC 301.7; UPC 102.1).

General Regulations 

29 When a plumbing permit is required for work to be done, the acquisition of the permit must be done ___________________.
Incorrect. Please choose another answer.
All plumbing permits are required to be issued prior to any plumbing work being started. Beginning any portion of plumbing work before a permit is issued is a violation of the plumbing code. Some jurisdictions require that all permits be posted conspicuously so that they can be seen from the road or street that a property fronts on. In existing homes this is often done by posting the permit in a window where it can be seen easily by a code officer approaching the property. New construction sites often have the permits posted in weather-resistant coverings on poles or posts that are readily visible from vehicular routes.
30 All plumbing permit applications are required to be signed by ____________________.
Incorrect. Please choose another answer.
All plumbing permit applications must be signed by the owner or the owner's agent. (IPC 105.3; UPC 104.3).
31 Many local code jurisdictions require a site plan before any work is done on an existing sewer or water service.
Incorrect. Please choose another answer.
True - It is common for a code enforcement office to want a site plan and specifications on file prior to any work being done on an existing sewer or water service. The site plan should show the location of existing piping and the proposed location for new piping.
32 Your boss has asked you to create a schedule for maintenance on a large building. How often should backflow preventers be inspected?
Incorrect. Please choose another answer.
Backflow assemblies and air gaps are required by code to be inspected once a year. (IPC 312.11.1; UPC 603.4.2). The devices should be tested. They must be working properly and not allowing contamination to the water source of a water distribution system. They are also required to be inspected when they are installed. If any repairs are done to the devices, a test and inspection of the repaired device must be performed. Additional devices that require this same procedure include the following:

• Double check valve assemblies
• Reduced pressure detector fire protection backflow prevention assemblies
• Double check detector fire protection backflow preventers
• Spill-proof vacuum breakers
• Backflow preventers on any hose connections
• Reduced pressure principle backflow preventer assemblies
• Pressure vacuum breaker assemblies
33 Plumbing inspectors issue Stop Work Orders for which of the following reasons?
Incorrect. Please choose another answer.
A Stop Work Order is a very serious matter. Code officers issue and post these orders only when there is a serious code violation or an immediate danger pending. (IPC 115.1; UPC 106.4). Minor code violations will result in a rejection from a code officer, not a Stop Work Order. When a Stop Work Order is issued or posted it must be observed immediately. In other words, stop all work instantly. Contact the issuing code officer for instructions. The code officer's name will be affixed to the Stop Work Order. If you continue to work you and your employer could find yourselves in immense trouble.
34 Code enforcement officials are empowered to condemn the use of a building for its present use.
Incorrect. Please choose another answer.
True - If a code enforcement officer finds conditions that may prove to be an issue for health and safety, the inspector has the authority to condemn the use of the building. This action can be appealed, but it must be accepted at the time of the posting of the notice that the building is condemned and no longer available for its previous use. The owner of the property must contact the code officer or code enforcement office to remediate the situation.
35 Trusses must not be _______________.
Incorrect. Please choose another answer.
Trusses are engineered. Regardless of whether they are roof trusses or floor trusses, they must not be cut, notched, drilled, spliced or otherwise altered. (IPC 307.5; UPC 312.2). When truss integrity is disturbed, it can lose its structural ability. Normal cutting, notching and drilling procedures associated with solid wood joists and rafters do not apply to trusses. There are, however, some occasions when a truss must be altered to allow for a plumbing installation. When this is the case, an approved engineer must provide written details on how the truss can be altered to allow for a plumbing installation. Only an engineer can do this.
36 You have been left to connect a building drain to a sewer and wait for the plumbing inspector to approve the connection. Then you are to bury the pipe. What is the minimum depth of cover required over the crown of a buried pipe?
Incorrect. Please choose another answer.
Pipe protection is a major part of the plumbing trade. The code requires a minimum depth of twelve inches of compacted backfill over any buried pipe. (IPC 306.3; UPC 312.3). This is used as a means of protecting the pipe. All backfill material must be clean and free of debris. For example, you cannot use backfill material that contains broken bricks, sharp rocks or other objects that may puncture a pipe. It is also important to apply backfill material in small quantities to avoid crushing a pipe or twisting a joint at a fitting. Common practice is to apply six inches of dirt and tamp it. Then another six inches of dirt is added and tamped.
37 Consider this example. Jeff is a master plumber. He has been asked to provide plumbing for a warehouse that will be located in an area subject to flooding. The warehouse will have a concrete floor and will have only one level of service area. Most of the plumbing will be installed below the concrete floor. Given the risk of potential flooding, Jeff is required to protect against which of the following?
Incorrect. Please choose another answer.
Any plumbing installed in a potential flood area must be protected from the potential effects of flooding. (IPC 305., 309.1; UPC 301.4). These effects include the risk of the following:

• Hydrostatic load and stress
• Buoyancy
• Hydrodynamic load and stress
• Entry of flood water into the plumbing system
38 When installing underground piping in soil that may be corrosive, any piping installed must be protected from the risk of corrosion.
Incorrect. Please choose another answer.
True - Ground corrosive effects on piping must be considered before a plumbing installation is made. (IPC 305.1, 605.1; UPC 312.4) If the chemical effects of the ground will compromise certain types of piping material, such as copper, protection for the piping must be put in place. This can take the form of a sleeve or a protective, approved coating on the piping. Under no circumstances shall pipe be installed in corrosive ground conditions without suitable protective measures in place.
39 It is generally recommended that plumbing systems be installed above a designated flood hazard area. However, special provisions can be made that allows some plumbing to be installed below a design flood elevation. Which of the following is allowed to be installed below a design flood elevation?
Incorrect. Please choose another answer.
When plumbing systems are properly protected from flooding and the design and installation meets with code enforcement approval they may be installed below a design flood elevation.
40 Spencer is installing a new plumbing system. The building drain will exit the foundation below a concrete footing. Foundation walls are to be made of poured concrete. The plans and specifications call for three exterior hose bib connections. This will require three piping penetrations through the upper section of the concrete walls on each side of the building and one pipe penetration through the wall on a lower section where the walk-out basement will not be backfilled as high as it will be on the sides. There will be a total of four pipe penetrations in various locations. Each pipe is required to be protected by a sleeve as the pipe penetrates an exterior wall. What is the minimum size of the sleeve required or the minimum protection for the penetration?
Incorrect. Please choose another answer.
Any pipe that penetrates an exterior wall is required to be provided with adequate pipe protection. (UPC 305.3; 312.10). By code, adequate pipe protection is a sleeve that has a minimum diameter that is twice the diameter of the pipe it is protecting or have a water tight seal of the annular space. (IPC 305.3; UPC 312.10). The sleeve is required to prevent the plumbing pipe from being crushed if the exterior wall shifts on the foundation supporting it.
41 Plumbing installed below ground level must be protected from freezing temperatures. The frost line where freezing stops penetrating the ground varies from climate to climate. Assume you are installing a pipe where a frost line is involved. Which of the following depths below the frost line would comply with the minimum requirements of the code?
Incorrect. Please choose another answer.
The depth of frost penetration in earth varies from region to region. For example, the frost line in Maine is 4 feet. In a more southern state, the frost line could be 18 inches. Local plumbing codes define the depth of a frost line in their jurisdictions. Regardless of the depth of a frost line, plumbing pipes must be installed no less than 6 inches below the established frost line (IPC) or below 12 inches (UPC) as determined by the local plumbing code. (IPC 305.4; UPC 609.1). And, at no point is there to be less than 12 inches of ground cover over a buried pipe.
42 The direction of the flow is not relevant to the installation of valves, pipes and fittings.
Incorrect. Please choose another answer.
False - Valves, pipes and fittings must be installed in the correct relationship to the direction of the flow. (IPC 704.2 UPC 310.5). Many valves have a directional or flow arrow indicating the correct direction of the flow. The flow arrow on the valve body refers to the recommended pressure or flow direction. A stop and waste valve has a bleeder that will only work if the valve is installed with the arrow in the proper direction.
43 What is the maximum distance allowed between pipe hangers when supporting 2 inch horizontal drain-waste-and-vent (DWV) piping that is made of ABS or PVC?
Incorrect. Please choose another answer.
The maximum distance between pipe supports for 2 inch plastic DWV piping is four feet. (IPC Table 308.5; UPC Table 313.3). Spacing of pipe supports vary depending on the type of piping being supported and the direction of installation for the piping.
44 Assume that you are updating an existing plumbing system. The old plumbing contains various types of piping. There is copper DWV piping, cast iron DWV piping and galvanized steel DWV piping. Water distribution piping is installed with Type M copper tubing and brass piping. You want to use PVC pipe for your DWV work and Type L copper tubing for your water distribution piping. Which of the following connectors will the plumbing code allow you to use on the DWV piping?
Incorrect. Please choose another answer.
There are many types of adapters that can be used for various conversions and transitions from one type of pipe to another. Male and female adapters can be used on water piping and drainage and venting piping. Compression fittings can be used on water piping and drainage and venting piping. Rubber compression sleeve adapters can be used on drainage and venting piping. Rubber insert adapters can be used to convert bell-and-spigot cast iron piping to plastic piping. Depending on the state/AHJ, you may have to have PVC no hub adapters and adapters from galvanized or copper material.
45 Mechanical joints are prohibited from joining materials of different types.
Incorrect. Please choose another answer.
False - Mechanical joints are approved for joining materials of dissimilar type as well as materials of the same type. (IPC 705.16; UPC 705.10).
46 How much grade is required on the fall of a drainage line for a condensate pipe?
Incorrect. Please choose another answer.
Most plumbing pipe is associated with a grade/fall of one-quarter of an inch of fall per running foot. This is not the case with condensate piping. The amount of grade required for a condensate line is one-eighth of an inch by foot. (IPC 314.2.1.; UPC 814.1). Why is this? The line is not carrying any solid waste. Only clear water is being conveyed.
47 The liquid combustion byproducts of condensing appliances must be collected and discharged to an approved plumbing fixture or disposal area in accordance with which of the following?
Incorrect. Please choose another answer.
You must follow the manufacturer's installation instructions as they are the primary requirement to observe when installing condensate disposal systems. (IPC 314.1; UPC 814.4). The plumbing code does require certain piping requirements, such as the amount of grade that must be installed on a drainage pipe. The material used for drainage conveyance must also be of a material approved by the local code. However, the pivotal point of condensate piping requirements is determined by the manufacturer's installation requirements.
48 Equipment containing evaporators must be provided with a condensate drainage system.
Incorrect. Please choose another answer.
True - All equipment that emits condensate drainage is required to be equipped with a drainage system. This applies to evaporators, ice machines, cooling coils and any other type of equipment that needs to release liquid in the form of clean waste.
49 An auxiliary drain pan for a condensate system must be equipped with which of the following?
Incorrect. Please choose another answer.
All auxiliary drain pans for condensate systems are to be equipped with water-level detection devices that conform to UL 508. (IPC 314.2.3.1; UPC 814.2). The device must shut off any equipment served by the drain pan if an overflow of the drainage pan may occur. Consult the manufacturer's recommendations for any additional requirements that may be needed.
50 Which of the following types of materials may be used for condensate drainage?
Incorrect. Please choose another answer.
Materials approved for the construction of a condensate drainage system can include any of the following:

• Galvanized Steel
• Copper
• PEX
• Polyethylene
• ABS
• PVC
• CPVC
• Cast Iron

(IPC 314.2.2; UPC 814.3).
51 What is the minimal diameter of piping used for a condensate drainage system?
Incorrect. Please choose another answer.
Condensate drain piping must have a minimum interior diameter of .75 inch. (IPC 314.2.2; UPC Table 814.3). This is for a single drainage pipe. If multiple pipes are attached to the main condensate drain the minimum diameter of the arterial drain piping must be enlarged accordingly to accept the additional condensate flowage.
52 Condensate drain lines can develop blockages as a result of debris and biological growth in the system. The proper way to access the inside of the condensate drain line to clean it is to cut the line and clear the blockage with compressed gas, such as air or nitrogen.
Incorrect. Please choose another answer.
Condensate drain systems must be designed in such a way to allow the cleaning of the line without cutting it. (IPC 314.2.5; UPC 814.3.1). The codes permit cleanouts, capped or plugged tees and cross-fittings, unions, removable mechanical couplings and specialty devices for the attachment of compressed gas hoses.
53 Which of the following mediums may be used for testing cast iron DWV systems for leaks?
Incorrect. Please choose another answer.
Water is the test medium of choice. A 10 foot head of water is required for 15 minutes. It is common for modern DWV systems to be tested with air. The minimum test pressure is required to be 5 pounds per square inch (PSI). When there is a leak that cannot be found easily, smoke can be used to expose the leak location. Smoke is not used as a primary test method. The codes do not permit the use of air to test plastic DWV pipes. (IPC 312.2, 312.3, 312.5; UPC 712.1).
54 Which of the following statements concerning pipe, tubing or fittings is NOT accurate, according to Code?
Incorrect. Please choose another answer.
All Code books refer to pipe, tubing and fittings according to inside diameter with measurements expressed in both English and Metric units.
55 A journeyman plumber has the authority to perform all of the following plumbing work except:
Incorrect. Please choose another answer.
A journeyman plumber is not required to be under the direct supervision of a master plumber. It is a violation of the plumbing Code for a journeyman plumber to work under a homeowner's permit and to receive payment, for such would require a master plumber operating as a business and obtaining the plumbing permit.
56 An indirect connection from a floor drain or sump pump at the bottom of an elevator shaft to the plumbing system can be achieved by a ____________________________.
Incorrect. Please choose another answer.
All indirect connections require an air gap when discharging into a plumbing system. A discharge line run out to the street is not draining into a plumbing system. (IPC 301.6, 802.1.5; UPC 801.2).
57 With respect to plumbing systems, all materials used must have the approval of which of the following:
Incorrect. Please choose another answer.
Engineers specify materials that conform to standards but not all products available have been approved yet. The plumbing authority having jurisdiction may approve the use of such products and master plumbers must comply with the administrative authority's decisions. An independent source may be listed by a testing agency to verify compliance with the applicable code.
58 All pipe used in plumbing applications will have all of the following markings except:
Incorrect. Please choose another answer.
Some pipe manufacturers list measurement in one-foot increments when rolls of pipe are 100' or over, but do not list increments on joints of 21', 20' or less. Brand names, psi rating, and nominal pipe size are required. (IPC 303.1; UPC 301.2.1).
59 Pipe ends should be reamed or deburred because, if not, which of the following may result?
Incorrect. Please choose another answer.
Failure to ream or deburr pipe ends can result in all outcomes noted.
60 Which of the following fittings may be used in a vent system but not in a drainage system?
Incorrect. Please choose another answer.
A twin ell cannot be used in a drainage system. All other fittings listed can be used in both systems.
61 An example of a DWV fitting used in a drainage system in a prohibitive manner is a __________.
Incorrect. Please choose another answer.
A sanitary tee is a short pattern fitting. It can be used as a waste fitting only if it receives the waste into the bull head opening and discharges downward. When a sanitary tee is horizontal to horizontal (on its side), the sweep is also horizontal. This application would lead to blockages in the future. A long sweep fitting like a wye or combination is acceptable in the horizontal-to-horizontal application.
62 Plumbing drainage passing through concrete footings and foundation walls need to be protected by ___________.
Incorrect. Please choose another answer.
Pipe sleeves are required to be installed with pipes passing through a foundation wall. (UPC 305.3; 312.10). The other options do not allow for expansion and movement in foundation.
63 You are sent out on a commercial job to install pipe hangers for 1" PEX tubing. For this type of pipe your hangers must be spaced ___________ apart.
Incorrect. Please choose another answer.
Pipe hangers for 1" PEX tubing must be spaced 32" apart. (IPC Table 308.5; UPC Table 313.3)
64 What does ASME stand for?
Incorrect. Please choose another answer.
American Society of Mechanical Engineers. This group sets many of the codes and standards that plumbing is based on.

Fixtures 

65 Which of the following are included as part of the minimum plumbing fixtures that must be installed in a single-family residence?
Incorrect. Please choose another answer.
The minimum fixture requirements for a single-family home include a toilet, lavatory, bathing unit, kitchen sink, and washing machine connection. (IPC Table 403.1; UPC Table 422.1). Keep in mind that these are minimums. Additional fixtures, such as hose bibs, dishwashers, additional bathroom fixtures and others could be included.
66 You have been called in to install rough plumbing for a multi-family building. The structure houses four apartments. Which of the following is not required to be installed in individual rental units?
Incorrect. Please choose another answer.
Multi-family units are not required to have an individual washing machine connection. (IPC Table 403.1; UPC Table 422.1). They do require a toilet, lavatory, bathing unit and kitchen sink. A laundry connection is required when an apartment reaches a certain number of dwelling units - one laundry connection per 20 units under the IPC and per 12 units under the UPC.
67 Assuming local code requires one toilet for men and one for women, how many toilets are required for a daycare facility that houses 15 people?
Incorrect. Please choose another answer.
Daycare facilities are usually required to offer one toilet for every 15 people in a daycare. (IPC Table 403.1). Depending on how a daycare is classified, it could be one toilet for up to 50 people. (UPC Table 422.1). Some codes require that the facilities be split into two different rooms. This can result in the need for two toilets. The required minimum fixture requirements are required to be divided evenly between bathrooms for opposite sexes. This is not always the case. Check your local code to see how it interprets a need for separate facilities. The UPC requires 1 for men and 1 for women.
68 What is the maximum distance an employee of a department store in a shopping mall should have to walk to reach a suitable restroom facility?
Incorrect. Please choose another answer.
Employees in shopping malls must not have to walk more than 300 feet to reach suitable restroom facilities. (IPC 403.3.4; UPC 422.4). The 300 feet is measured from the entry of any store in the shopping mall to the toilet facility. During this walk they are not required to ascend more than one set of steps. Bathrooms under these conditions cannot be installed more than one story above the work area. There are possible exceptions for buildings that house factory workers or industrial workers. For other work locations, there is typically a 500 foot rule, but you should check your local code to confirm the local requirements.
69 All hospitals are required to have a minimum of two water services. However, the two water services are allowed to connect to a single water main.
Incorrect. Please choose another answer.
True- Hospitals are required to have a minimum of two water services in case one water service becomes unable to provide adequate water for the needs of the facility. (IPC 609.2; UPC 1303.8). While two separate water services are required, only one water main is required. This permits both water services to be tied into a common water main.
70 Which of the following structures are likely to require the installation of handicap plumbing fixtures?
Incorrect. Please choose another answer.
Accessible plumbing facilities are generally required in structures that serve the public. (See Public Accommodation, ADA, Title 42, Section 12182; ICC A117.1; UPC 403.2). They are not a requirement in residential housing. By real estate standards, a multi-family housing unit is considered to be a residential facility until they exceed five rental units. Even then, accessible plumbing is rarely required in all of the rental units. However, accessible plumbing is required in hotels, motels, commercial bathrooms and similar facilities.
71 Your job has you roughing in plumbing for a public restroom. The general contractor wants you to install two toilets, one urinal, one shower and one drinking fountain in the restroom for males. The female bathroom will not have a urinal, but it will require a bidet. Which of the following is not allowed to be installed in a public restroom?
Incorrect. Please choose another answer.
Drinking fountains are not allowed to be installed in public bathrooms. (IPC 410.5; UPC 415.4).
72 You are new to plumbing applications where handicap fixtures are required. Special requirements for these fixtures exist, but you are not sure what they are. Will you find the answers to all of your questions in the plumbing code or the building code?
Incorrect. Please choose another answer.
Plumbers working to meet accessible requirements for plumbing facilities must be aware of both the local plumbing code and the local building code. Additionally, the ADA statute may need to be referenced to determine such issues as what is a public accommodation. The point of this is that a plumber must pay attention to both the plumbing and building code when working with accessible plumbing needs. The plumbing code dictates fixtures. Requirements of the building code outline minimum spacing requirements for doors and access. In order to maximize full accessible plumbing facilities a plumber must cross over from both the plumbing and building code.
73 What is the likely height of a handicap toilet?
Incorrect. Please choose another answer.
Handicap toilets are available with heights that include 17 inches, 18 inches and 20 inches. (ICC A-117.1, 604.4). Eighteen inches is the most common height of a standard handicap toilet.
74 The accessible travel route for people going to use public plumbing facilities must not pass through a kitchen.
Incorrect. Please choose another answer.
True- Accessible routes for travel to public restroom facilities are not allowed to pass through kitchens, storage rooms, closets or similar spaces. (IPC 403.3.1; UPC 422.4.1).
75 Which of the following describes a specific type of toilet?
Incorrect. Please choose another answer.
There are many types of toilets available. The various types of acceptable toilets include the following:

• Siphon jet
• Siphon vortex
• Siphon wash
• Reverse trap
• Blowout
76 What is the minimum distance required in front of an accessible lavatory?
Incorrect. Please choose another answer.
Handicap lavatories are required by code to have a minimum of 30 inches of clearance in front of the lavatory. (ICC A 117.1, 305.3). They must be installed in a way to allow easy access by a person in a wheelchair. A rule of thumb measurement is to create a visual box that is 30 inches by 30 inches in front of a handicap lavatory. If someone can sit in this visual box and use the lavatory easily, the spacing is probably fine. This same rule applies to kitchen sinks.
77 You are sent to install and ADA accessible wall-hung lavatory on a commercial job. After mounting the wall hanger bracket, you must be sure the measurement of the rim of the lavatory does not exceed ___________________ above the floor upon installation.
Incorrect. Please choose another answer.
A handicap lavatory must be installed so that there is no more than 34 inches from the top of the lavatory to the top of a finished floor. (ICC A117.1, 606.3). When working with accessible plumbing fixtures plumbers must remember that clearance requirements and heights are not the same as they are for typical plumbing installations. The fixtures must be installed in a way to serve the people to whom they are intended to provide plumbing resources.
78 What is the maximum height allowed for a kitchen sink when it is being installed for accessible purposes?
Incorrect. Please choose another answer.
The maximum height allowed for a kitchen sink is 34 inches from the top of the sink to the top of a finished floor. (ICC A117.1, 606.3).
79 Toilet facilities must be installed along accessible routes in an office building. The distance to be traveled to reach the facilities must not exceed 300 feet.
Incorrect. Please choose another answer.
False - The maximum length of a travel route to a toilet facility in a building with employees and customers, other than a shopping mall or center, is 500 feet. (IPC 403.3.3; UPC 422.4).
80 What is the maximum distance that a lavatory faucet for accessible use can be placed from the front edge of a lavatory?
Incorrect. Please choose another answer.
Lavatory faucets must be located no farther than 25 inches from the front edge of the lavatory being served by the faucet when the fixture is intended for handicap use. (ICC A117.1, 308.2.2).
81 What is the maximum pressure allowed as the force needed to operate a handle on a handicap faucet?
Incorrect. Please choose another answer.
The maximum operational force required to activate a handicap faucet is five pounds. (ICC A117.1, 309.4). Faucets must be easy to operate when used for accessible purposes. The type of handles allowed on handicap faucets may include any of the following:

• Blade handles
• Wing handles
• Single handles
• Senior-units
• Push-button handles
82 Which of the following is required to be installed with a bathtub that is used for a handicap installation?
Incorrect. Please choose another answer.
Bathtubs installed for handicap use are required to have seats and grab bars. (ICC A117.1, 607.4). The grab bars are to have a minimum diameter of 1.25 inches and not more than 2 inches. These bars must be at least 24 inches in length. Bars are to be installed horizontally. There should be grab bars in the area of the seat provided for the bathing unit. Design and strength requirements for grab bars are provided in the local building code. A seat for a handicap bathtub may be of an integral type or a removable type.
83 What is the minimum length requirement for a hose that serves a personal shower unit in a handicap bathing unit?
Incorrect. Please choose another answer.
Hoses installed for the operation of personal shower units in handicap bathing units are required to have a minimum length of five feet. (ICC A117.1, 607.6).
84 Assume that you are installing a sink in a public bathroom. The sink is to be installed in a custom-made base cabinet that contains two doors that open outward. Plumbing code requirements dictate certain requirements for fixtures than can involve the cabinet design of the cabinet housing the fixture. In this case a plumber should check the toe clearance of the kitchen cabinet. There must be a minimum of nine inches high and seventeen inches deep that will allow for toe space.
Incorrect. Please choose another answer.
True - To meet regulations on accessible fixtures, a sink installation requires a minimum toe space that is at least nine inches high and seventeen inches deep. (ICC A117.1, 306.2). This can be a common element of an installation for a plumber to overlook, especially when the base cabinet is made as a custom cabinet. Production cabinets should meet minimum standards for both the building and plumbing code. But, this may not be the case with a handcrafted cabinet. It is wise to check all potential code violations prior to making a plumbing installation.
85 What is the maximum width of a seat in a shower that is installed for handicap use?
Incorrect. Please choose another answer.
A handicap shower is to have a seat that is no wider than 16 inches. (ICC A117.1, 610.3.1). The seat is to be mounted along a sidewall of the shower and it should run the full length of the shower. A height requirement for the seat requires that the seat be installed at a height of not less than 17 inches and not more than 19 inches. This height is to be measured from the finished floor.
86 Where water dispensers or bottle filling stations are permitted as an alternative to a drinking fountain, up to how many drinking fountains may be substituted?
Incorrect. Please choose another answer.
The codes permit water dispensers or bottle filling stations as drinking fountain alternatives for up to 50 percent of the drinking water requirements. (IPC 410.4; UPC 415.2). Under the IPC, there must be at least three drinking fountains required before alternatives are permitted.
87 Assume that you are installing a standard bidet. This is not meant to be a handicap installation. You will also be installing a toilet beside the bidet. There is a wall to the right of the proposed bidet location. Additionally, there is a bathtub already in place to the left of the proposed toilet location. You have to determine the minimum spacing requirements between fixtures to be code compliant. How much space is required from the center of the drain for the bidet from the nearest fixture or wall?
Incorrect. Please choose another answer.
Both toilets and bidets require a minimum open floor space of 30 inches to be installed. (IPC 405.3.1; UPC 402.5). This is to allow a minimum of 15 inches of clear space from the center of the fixture drain to the nearest fixture, wall or obstruction. Essentially, a plumber can measure from one obstruction to another and determine if there is 30 inches between them. If there is, the center of the drain for either a toilet or bidet can be installed in the center of the space. It is not required that the fixture be centered in open space, but there must be at least 15 inches from the center of the drain to the nearest obstruction.
88 When plumbing inspectors are inspecting the installation of plumbing fixtures, they may consider which of the following in their decisions to approve or reject an installation?
Incorrect. Please choose another answer.
Plumbing inspectors can consider several factors when inspecting the installation of plumbing fixtures. Fixtures are to be installed level. They are not to be installed in a manner that makes them crooked. As an example, the tank of a toilet should have the same distance measured from the edge of the tank to the back wall on the left side that it does on the right side. Good workmanship is always a consideration in any plumbing installation. Even adequate space for proper cleaning can be considered. In the end, all fixtures must be installed in a code-compliant manner.
89 Assume that you are working on a job that is new construction. The time has come to install toilets. You have heard of reverse traps on toilets. Since you want to show your knowledge, you ask the supervising plumber what type of toilets will be installed. He tells you that siphon jet toilets are going to be used. Toilets that are equipped with reverse traps are no longer approved by current plumbing codes.
Incorrect. Please choose another answer.
False - Toilets can have reverse traps. A blowout toilet bowl is also acceptable. Siphon jet bowls are common and a wash down toilet is fine.
90 The bolts used to secure a toilet to a closet flange should be made of which of the following materials?
Incorrect. Please choose another answer.
Closet bolts are normally made of brass. They must be made of some type of material that is resistant to corrosive action. (IPC 405.4; UPC 402.6). Otherwise, the bolts will deteriorate over time and the toilet will no longer be secured to the closest flange. When a closet flange, which is recommended, is not used, the lag bolts used to secure a toilet are required to be brass or some other non-corrosive material.
91 What is the minimum unobstructed opening of egress when a shower door is installed for a typical shower?
Incorrect. Please choose another answer.
The minimum unobstructed opening of egress for a shower door installed on a typical shower is 22 inches. (IPC 421.4.2; UPC 408.6).
92 Assume that you have been hired to install a shower valve. The customer wants a shower valve that will reduce the risk of a scalding risk. Which of the following should you install?
Incorrect. Please choose another answer.
In this scenario you will not install any of the options offered in the question. Temperature actuated flow reduction valves are not a suitable replacement for a balanced pressure valve, a thermostatic valve or a combination shower and tub valve. The simple solution is to install an anti-scald mixing valve.
93 Your job calls for you to install plumbing for a handicap tub-shower combination. Part of your job involves the installation of grab bars. You will, of course, be installing a valve/faucet for the bathing unit. The lowest grab bar is intended to be mounted 9 inches above the flood-level rim of the fixture. The shower valve should be installed at least 6 inches above the grab bar in that section of the bathing unit.
Incorrect. Please choose another answer.
False - Grab bars are not allowed to be installed below faucets in bathing units. For safety reasons the code requires the bars to be installed above faucets. One reason is to discourage people from grabbing the faucet as a support device. (ICC A117.1 607.5).
94 Which of the following types of devices are approved to block the waste outlet of a bathtub?
Incorrect. Please choose another answer.
Bathtubs are required to have a waste outlet with a stopper. (IPC 407.2; UPC 409.2). The device used to block the drainage opening of a bathtub can be one of any of the following:

• Plunger stoppers
• Rubber stoppers
• Lift-and-turn stoppers
• Push-pull stoppers
• Snap-down-pop-up stoppers
95 Which of the following is required with the installation of a whirlpool bathtub?
Incorrect. Please choose another answer.
Access to the circulation pump is required and should be done in accordance with manufacturer's instructions. (IPC 426.5; UPC 409.6). If the manufacturer's instructions do not provide guidance on access, the codes provide guidance.
96 Dishwasher installations require the use of which of the following?
Incorrect. Please choose another answer.
All dishwashers are required to discharge their waste through an air gap or a backflow prevention device. (IPC 409.2; UPC 414.3). This is to prevent back siphonage. Without the use of an air gap there is a risk that dirty drain waste water could be sucked back into a dishwasher. This could introduce bad bacteria into the fixture. One alternative to the use of an air gap is the installation of a backflow preventer on the drainage line. However, the common installation calls for an air gap to be mounted on the deck of a kitchen sink or countertop. The dishwasher drain hose connects to one end of the air gap. A separate hose attaches to the other end of the device and conveys the waste water to the general drainage system. Since the waste passes through open air at the air gap, the risk of back siphonage is eliminated.
97 You and your plumber have just finished installing seven drinking units in a commercial building. The plumber tells you to go to each fixture and check to see that the water being delivered for drinking is high enough. You must ensure that the water delivery is at the front of the fixture and that the water flows upwards for a minimum distance of four inches.
Incorrect. Please choose another answer.
True - Water coolers are required to have the drinking delivery device located at the front of the drinking unit. (ICC A117.1, 602.2.5). When water is called for it is to flow upward for a minimum distance of four inches. Levers and buttons that are used to control the flow of water may be mounted on either the front or the side of a drinking fountain.
98 The drainage hose from a clothes washing machine should discharge into which of the following:
Incorrect. Please choose another answer.
Wastewater from a washing machine should discharge into an indirect waste receptor. (IPC 406.2; UPC 804.1, 1001.2). What does this mean? It is not complicated. A typical installation has the discharge hose for the washing machine discharging into the open end of a two-inch drainage pipe that is trapped. Another acceptable means of discharge is for the washing machine hose to hang over the rim of a laundry sink and discharge wastewater into the trapped sink drain. This type of piping arrangement is known as an air break and it prevents back siphonage.
99 What is the minimum diameter of a drain pipe allowed to be for a residential garbage disposal?
Incorrect. Please choose another answer.
The minimum size of a drain pipe accepting the discharge from a garbage disposer is 1.5 inches. (IPC 416.2; UPC Table 702.1). The connection must be a solid connection that does not use an air break or an air gap. The drainage pipe is to be trapped. Garbage disposers can be discharged into a continuous waste drain under a kitchen sink. Or, it may be trapped and discharged directly into the sanitary drainage system. Garbage disposers do require a water source, which is usually a kitchen faucet. Most garbage disposers are mounted to one of the drainage holes in a kitchen sink.
100 What is the minimum diameter of a drain that will receive the waste from a floor drain?
Incorrect. Please choose another answer.
Floor drains are required to discharge into a drain pipe that has a minimum diameter of two inches. (IPC 413.3; UPC Table 702.1). This should go without saying since the minimum diameter of a drain pipe installed below concrete is two inches. Every floor drain must be trapped and they are typically required to be provided with a vent. Removable strainers for the floor drains are also a code requirement. All removable strainers are required to be readily accessible.
101 Bidets must be equipped with an approved device on the incoming water pipe to prevent back siphonage.
Incorrect. Please choose another answer.
True - All bidets are required to be protected from back siphonage. (IPC 408.2; UPC 410.2, 603.3). A vacuum breaker is normally used for this purpose. If a backflow preventer is not an integral part of a bidet being installed you must provide protection for the fixture in the supply piping from the water distribution system.
102 Which of the following drain pipe sizes meets code for a shower drain?
Incorrect. Please choose another answer.
A 2" waste outlet for a shower meets the minimum requirements of the IPC (1.5") and the UPC (2"). (IPC 421.3; UPC 408.5).
103 The minimum waste outlet size for a bathtub with a shower is:
Incorrect. Please choose another answer.
Bathtubs with showers are allowed to have waste outlets with 1.5-inch diameter drains. (IPC 407.2; UPC 409.2). The minimum waste outlet size for a bathtub and shower is the same under the IPC, 1.5 inches. (IPC 407.2 and 421.3). Under the UPC, the minimum requirement for a waste outlet on a shower is 2" while the minimum for a bathtub is 1.5 inches. (UPC 408.5 and 409.2).
104 What is the minimum height requirement for a shower wall above the shower drain?
Incorrect. Please choose another answer.
When measured from the surface of a shower drain the shower walls must extend 70 inches above the drain. (IPC 421. 4; UPC 408.7).
105 When sheet lead is used to line a shower pan that will have a poured concrete base and tile finish, the lead must not weigh less than _______ pounds per square foot.
Incorrect. Please choose another answer.
Sheet lead used for a shower pan lining must have a minimum weight of no less than four pounds per square foot. (IPC 421.5.3; UPC 408.8.3). The lead is to be coated with an asphalt paint or other approved coating. The sheeting must be insulated from any conducting substances, except the drain connection. Fifteen-pound asphalt felt, or an equivalent thereof, is the normal means of insulating the sheet lead. Any sheet lead that must be joined is to be joined by burning.
106 When a drinking fountain is installed in a public restroom the fixture must have a minimum distance of 15 inches from the side of the fountain to the center of a toilet.
Incorrect. Please choose another answer.
False - Drinking fountains and water coolers must not be installed in rooms where toilet facilities exist. (IPC 410.5; UPC 415.4).
107 Ballcock assemblies for residential toilet must be which of the following?
Incorrect. Please choose another answer.
Ballcock assemblies for toilets are required by code to be of an anti-siphon design. (IPC 415.3.1; UPC 413.3). It remains possible to buy ballcocks that do not meet this criterion, but they are not approved by the plumbing code standards.
108 Sheet copper can be used as a liner for a built-up shower. This is a suitable alternative to sheet lead. What is the minimum weight requirement for sheet copper used for this purpose based on a one square foot section of the material?
Incorrect. Please choose another answer.
Sheet copper that is used as a liner for a shower must have a minimum weight of 12 ounces per square foot. (IPC 421.5.2.4; UPC 408.8.4). Some suitable form of insulation is required to be applied between the sheet copper and the subflooring that exists for a shower installation. This is most often done with 15-pound asphalt felt, but the insulation can be of some other equivalent material.
109 A plumber is installing a commercial garbage disposer. Which of the following drain sizes will meet code?
Incorrect. Please choose another answer.
Commercial garbage disposers are big beasts. They usually sit on a tripod set of legs to support their weight. By the code, a minimum diameter of a drain pipe for these machines is 1.5 inches for the IPC and 2 inches for the UPC. (IPC 416.3; UPC Table 702.1). Many plumbers will use no smaller than 2 inches. They require their own drainage piping and trap. Do not confuse the code regulations for residential garbage disposers with the requirement for commercial garbage disposers. A cold water source must be available to the disposer. The water source can be of an automatic type. Commercial garbage disposals are not allowed to be connected to grease interceptors.
110 The removal of a strainer on a water pressure regulator can involve the disconnecting of the supply piping and must be accessible.
Incorrect. Please choose another answer.
False - A strainer on a water pressure regulator must be readily accessible. (IPC 604.8.2; UPC 608.2). Its removal must not involve the removal of the valves, the regulator or supply piping. Remember that readily accessible means that you can see and touch the piping without removing anything. Accessible plumbing can be concealed by a removable access panel.
111 Garbage can washers are required to be fitted with which of the following?
Incorrect. Please choose another answer.
Garbage can washers are common commercial plumbing fixtures. They must be supplied with a water source and must be equipped with a backflow preventer or an air gap. (IPC 417; UPC 603.5.19). Every garbage can washer is required to have an individual trap. Discharge from the fixture must pass through an approved, removable strainer to prevent large particles from entering a sanitary drainage system.
112 How many urinals may one flush valve serve?
Incorrect. Please choose another answer.
Urinals must be equipped with individual flush valves. A single flush valve is not allowed to operate more than one urinal. (IPC 415.1.1; UPC 413.2).
113 Which of the following water closet designs are not allowed for commercial use?
Incorrect. Please choose another answer.
Commercial water closets are required to have elongated bowls and elongated seats. (IPC 425.2, 425.3; UPC 411.3). Round-front bowls are allowed for residential use, but they are not allowed for commercial applications. Commercial toilet seats are required to be hinged and they are required to have split fronts.
114 Another name for a clinical sink in a health-care installation is which for the following?
Incorrect. Please choose another answer.
Clinical sinks are also known as bedpan washers.
115 Assume that you are sent to a job where you are to install a medical sterilizer in a healthcare facility. There are a number of code requirements related to medical sterilizers. Which of the following is required for the installation of a sterilizer?
Incorrect. Please choose another answer.
The drain connection must be protected by an air gap. (IPC 608.3.1; UPC 1303.4.1). This type of unit is considered a special fixture.
116 The plumbing codes use terms "accessible" and "readily accessible" and they are considerably different. In order to comply with the code, you must understand the difference. What does readily accessible mean? Choose from the following options.
Incorrect. Please choose another answer.
For a plumbing system to be readily accessible, the plumbing should be able to be seen and touched without having to move, or remove, anything.
117 Which of the following locations is suitable for the installation of vacuum fluid-suction systems?
Incorrect. Please choose another answer.
Vacuum fluid-suction systems are intended to be installed in cabinets or cavities, but they must be visible and readily accessible. When central systems are installed in hospitals they must be connected to emergency power facilities. Venting for a vacuum fluid-suction system requires that the vent extend to outside air through a pipe that penetrates the roof of a building. Any central fluid-suction system must be intended for continuous use. The cleaning and maintenance of a central fluid-suction system must not interfere with the operation of the system even when cleaning and maintenance is being provided.
118 A clinical sink that depends on trap siphonage to discharge its wastes contents is required to have:
Incorrect. Please choose another answer.
A clinical sink that depends on trap siphonage to discharge its waste contents needs to have a flushometer valve, flushometer tank or a flush tank to supply water in sufficient quantity and flow rate to flush the contents of the fixture, to cleanse the fixture and to refill the trap without excessive water use. (IPC 415.1; UPC 413.1).
119 What is the minimum height above a flood-level rim of a fixture that a vacuum breaker is allowed to be installed?
Incorrect. Please choose another answer.
Backflow prevention devices must be installed at least six inches above the flood-level rim of the fixture being served. (IPC 608.16.4; UPC 603.5.1). When such a device is used for a handheld shower unit the backflow preventer must be installed a minimum of six inches above the highest point that the shower can be held to.
120 Which of the following is the most common type of backflow prevention device installed in hospitals?
Incorrect. Please choose another answer.
Vacuum breakers are the most common form of backflow prevention devices used in hospital settings. Vacuum-suction systems require the installation of air gap or a vacuum breaker. Boiling-type sterilizers are required to be protected by air gaps. But in general, vacuum breakers remain the most common form of backflow prevention in hospitals.
121 Which of the following is not true regarding compliance with ADA Accessibility toilet requirements for adults?
Incorrect. Please choose another answer.
Sensor valves are not required. The other items are required. (ICC A117.1, 604.2, 604.3.1 and 604.6).
122 Toilets installed in public restrooms should be rated at no more than ___________ gallons per flush?
Incorrect. Please choose another answer.
1.6 gallons per flush is the present industry standard. (IPC Table 604.4; UPC 411.2).
123 You are installing the rough-in for an ADA compliant urinal. What is the maximum rim height above the floor you need to consider for the urinal upon final installation when roughing-in the drain outlet?
Incorrect. Please choose another answer.
The maximum distance above the floor for the rim of an ADA urinal is 17". (ICC A117.1, 605.2).
124 Which of the following water temperatures meet code for a public lavatory?
Incorrect. Please choose another answer.
The IPC requires tempered water for public lavatories, which is a range of 85° to 110°. (IPC Definitions, 419.5). The UPC sets the maximum temperature at 120° for a public lavatory. (UPC 407.3).
125 To control the maximum water temperature on a public lavatory, which of the following is not permissible by Code?
Incorrect. Please choose another answer.
The main water heater thermostat is not considered a control for meeting the provision of the Code.
126 The minimum clearance for a public lavatory, or water closet, from the side wall or partition to its center is _______________________.
Incorrect. Please choose another answer.
The minimum clearance for a public lavatory, or water closet, from the side wall or partition to its center is 16". (ICC A117.1 604.2). The maximum distance is 18".
127 The minimum clearance for a lavatory, or water closet, from the side wall or partition to its center is _______________________.
Incorrect. Please choose another answer.
The minimum clearance for a lavatory, or water closet, from the side wall or partition to its center is 15". (IPC 405.3.1; UPC 402.5).
128 Approved toilet bolts should be made of _____________________.
Incorrect. Please choose another answer.
Despite the availability of brass-coated steel, nylon and plastic commode bolts on the market, corrosive resistant bolts are specified by the code because of their strength and corrosion resistance. (IPC 405.4.2; UPC 402.3).
129 The minimum distance between adjacent fixtures (center to center) in a public restroom, other than accessible fixtures, is _____________________.
Incorrect. Please choose another answer.
The minimum distance between adjacent fixtures (center to center) in a public restroom, other than accessible fixtures, is 30". (IPC 405.3.1; UPC 402.5).
130 Which of the following types of plumbing connections in concealed spaces would require installation of an access panel?
Incorrect. Please choose another answer.
Slip joints are connected using an elastomeric gasket and nut and may need to be replaced or repaired due to movement or expansion/contraction therefore needing accessibility. (IPC 405.9; UPC 402.10).
131 In order to eliminate trap siphonage or sudsing in other fixtures downstream from a domestic clothes washing machine, a(n) _________________________ should be installed.
Incorrect. Please choose another answer.
A 2" diameter trap and stand pipe is required on domestic washer drain connections but branch drain pipe size must be 3" or larger to accommodate additional fixture drains on branch. (IPC 406.2; Table 709.1; UPC Table 702.1).
132 The discharge hose from a domestic washing machine must connect to the drain standpipe in the following manner:
Incorrect. Please choose another answer.
An air break allows the hose to discharge without possible spillage (as with an air gap) but protects against backflow and siphonage. (IPC 406.2; UPC 801.2).
133 Domestic clothes washer manufacturers were once required by code to have a(n) _____________________ on their product.
Incorrect. Please choose another answer.
This code requirement was removed to prevent compliance issues during inspections as some manufacturers ceased to comply by not indicating the washer conformed to ASSE 1007.
134 Because domestic clothes washer manufacturers are no longer required to comply with ASSE 1007, many plumbing inspectors require a(n) _______________________ on the water connections to the washer.
Incorrect. Please choose another answer.
ASSE 1007 required domestic clothes washers to contain an internal air gap on the machine but manufacturers quit complying with ASSE 1007 when the requirement was dropped in 2012. It was virtually unenforceable since inspectors were unable to visually inspect the appliance without disassembly. This leads code officials to require the machine water connections to have backflow preventors to comply with the code. (IPC 406.1; UPC 402.7).
135 All bath tubs must have a minimum drain size of what diameter pipe?
Incorrect. Please choose another answer.
1.5" inside diameter pipe size is the minimum for bath tub drains. (IPC 407.1; UPC 409.2).
136 As a means of draining, bath tubs may have a ________ in addition to the waste connection on the drain.
Incorrect. Please choose another answer.
Bath tub drains may have overflow piping that is connected upstream of the fixture trap. (IPC 407.2; UPC 404.2.1, 409.3). The overflow is to function whether or not the waste outlet is closed or open.
137 Code requires which of the following between the tub filler spout and flood rim of the tub?
Incorrect. Please choose another answer.
An air gap at least twice the diameter of the pipe size is required to prevent back siphonage. (IPC 405.1; UPC 409.5).
138 The hot water temperature serving a bidet should not exceed _____________________ degrees.
Incorrect. Please choose another answer.
Code requires a water temperature limiting device conforming to ASSE 1070 or CSA B 125.3. (IPC 408.3; 410.3).
139 To prevent possible back siphonage on a bidet, a/an ____________________ should be installed.
Incorrect. Please choose another answer.
An air gap or a backflow preventer must be present on a bidet. (IPC 408.2; UPC 410.2).
140 The water supply to a commercial dishwashing machine must have which two of the following backflow protection devices or methods?
Incorrect. Please choose another answer.
Since Code officials cannot always determine if the appliance has an internal air gap, many will require a backflow preventer to be installed. (IPC 409.2; UPC 414.2).
141 The flushing fluid temperature of an emergency eye wash is specified by Code to be __________.
Incorrect. Please choose another answer.
The codes' sections on emergency eye washes refer to ASSE 1071 and ASSE 1085, for tepid water supplies. (IPC 411.3; UPC 416.2).
142 Which of the following is not required of emergency eye wash and shower stations?
Incorrect. Please choose another answer.
Depending on what hazardous waste or contaminants may be introduced into the building sewer, the building owner may have to contain and dispose of these wastes under a different regulatory authority. (IPC 411.2; UPC 416.5).
143 The water supply to a commercial food waste grinder should be protected against backflow by a backflow preventer or a/an _____________________________________.
Incorrect. Please choose another answer.
An air gap is the most common and effective means to prevent backflow. (IPC 416.4; UPC 419.3).
144 Most grinder manufacturers recommend _________________ water to effectively flush grease and food contents through grinder.
Incorrect. Please choose another answer.
Cold water keeps greases more solid for better grinding results. The codes require cold water. (IPC 416.4; UPC 419.3)
145 You are determining the minimum number of fixtures needed in a building renovation based on the occupant load. How should the occupant load be divided to account for men and women?
Incorrect. Please choose another answer.
In a determination of the minimum amount of fixtures needed based on the occupant load, the occupant load is to be is to be divided in half to account for men and women. (IPC 403.1.1; UPC 422.1.1).
146 What is the minimum diameter of a P-trap allowed for a public lavatory?
Incorrect. Please choose another answer.
The minimum diameter of a P-trap allowed for a public lavatory is 1.25". (IPC 709.1; UPC 407.5).
147 Which of the following fixtures is required by Code to have an approved water temperature device installed?
Incorrect. Please choose another answer.
Public restrooms seldom have water heaters dedicated for their use, so a tempering device is required. (IPC 419.5; UPC 407.3).
148 Which of the following types of urinals is no longer Code approved?
Incorrect. Please choose another answer.
Due to privacy standards and unsanitary conditions resulting from their use, trough urinals are no longer allowed to be installed in public restrooms. (IPC 402.1; UPC 405.2)
149 Shower and tub faucets must _______________________.
Incorrect. Please choose another answer.
120 degree water is the point at which skin may be scalded. Showers/tubs have scald guard setting built in to deliver water no hotter than 120 degrees. (IPC 412.3; UPC 408.4.2).

Indirect and Special Wastes 

150 Which of the following types of fixtures may have requirements for an indirect waste connection?
Incorrect. Please choose another answer.
Drains from washing machines are required to discharge into an indirect-waste receptor. (IPC 406.2 and 802.4.3.1; UPC 804.10. This is required to prevent contaminated water from entering a potable water source. This is accomplished by a trapped and vented indirect-waste receptor. The discharge hose from the clothes washer is inserted into the standpipe of the receptor and does not come into contact with drainage water in the trap.
151 You are working with an indirect waste receptor. It is up to you to determine if a trap is needed and where it should be placed. Which of the following lengths of indirect waste piping should be trapped?
Incorrect. Please choose another answer.
Standard practice is to trap the drain of an indirect waste if the drainage pipe will extend more than five feet in length. (UPC 803.3). The IPC requires a trap on indirect waste piping that exceeds 30 inches of developed length or 54 inches of total developed length. (IPC 802.3). No vent is usually required for the indirect drain. Check your local rules and regulations to be certain on this point. In other cases, a simple floor drain can serve as a receptor, but the drain must be trapped and a vent is normally required for this trap.
152 Buildings that require a system for the handling of special waste are required to have two drainage systems. One system is for used with special wastes, like chemical waste. The second system is to be used for normal sanitary drainage needs.
Incorrect. Please choose another answer.
True - A building cannot have a combined system. Two separate systems are required. (IPC 803.2; UPC 811.1). Special wastes cannot be allowed to enter a sanitary drainage system until it has been treated and confirmed to offer no risk to a typical sanitary drainage system.
153 Which of the following is considered to be the best method for connecting an indirect waste to a sanitary drainage system?
Incorrect. Please choose another answer.
The codes permit indirect waste piping to discharge to a waste receptor through an air gap or air break. (IPC 802.3; UPC 801.2). An air gap is believed to be superior to an air break for the protection of an indirect wastepipe from back siphonage. Due to the nature of installation, there is more risk of a backflow occurring with an air break. Since air breaks have discharge piping entering a receptor it is feasible to have the sanitary drain become clogged and back up, which could result in contaminated waste traveling back to the indirect waste fixture. This is not possible when an air gap is used.
154 Which of the following types of drainage tubing do not require a trap?
Incorrect. Please choose another answer.
Traps are not allowed to be installed on the discharge piping from relief valves that serve water heaters, boilers or expansion tanks installed in conjunction with boilers. (IPC 504.6). These types of discharges are clear water and do not contain waste or fecal material. Sewer gas is not transported through these discharge outlets. In all of the cases above, the wastes are to terminate above a floor or over an indirect waste receptor, such as a floor drain. Therefore, they cannot be trapped.
155 When an air break is being created, the discharge hose from a fixture being served by the drain receptor is required to penetrate the receptor to a point where at least two inches of the discharge tube are below the trap seal.
Incorrect. Please choose another answer.
False - The discharge tubing, hose or piping being conveyed to an indirect waste receptor is never to enter the trap seal. (IPC 802.3.2). This defeats the entire purpose of the air break. Once the tubing, hose or pipe is in the drainage, water held in the trap there is high risk of potential backflow to the fixture that the indirect waste is serving.
156 You are plumbing a new house. Part of the plumbing system includes the installation of DWV piping for a clothes washer. The fixture is going to discharge its wastewater into an indirect waste that will be trapped and vented. The minimum required height of the receptor standpipe is _______ inches.
Incorrect. Please choose another answer.
The standpipe receptor that will receive the discharge from a clothes washer must be at least 18 inches tall and not more than 42 inches tall by the IPC and 30 inches by UPC. (IPC 802.4.3; UPC 804.1). The measurement is made from the trap seal, not the top of the trap. The receptor must also be accessible. In other words, it cannot be concealed in a finished wall that does not allow for access.
157 Standpipes for automatic clothes washing machines must have a minimum diameter of two inches. The drains for these standpipes are required to travel their developed length in their full diameter and enter into a drainage branch or stack that has a minimum diameter of ______. The vent for a washing machine standpipe can be as small as 1.5 inches in diameter.
Incorrect. Please choose another answer.
A drain that collects the waste from an independent drain for a clothes washing machine must have a minimum diameter of three inches. (IPC 406.2). Pipe with a 2-inch diameter can convey the waste from the trapped receptor at the washing machine to the branch drain or drain stack where it terminates.
158 A wye-branch fitting is approved to accept the waste from an air gap for a domestic dishwasher when the wye-branch fitting is connected to an end-outlet waste for a kitchen sink.
Incorrect. Please choose another answer.
True - Wye-branch tailpieces can be installed between a kitchen sink basket strainer and the trap serving the sink when a discharge port is required for the hose that extends from an air gap that is serving a dishwasher drain. (IPC 409.4; UPC 414.3).
159 During a rough-in installation you notice that an indirect waste receptor is called for in the room where you are installing a DWV system. At the same time, you see a requirement for what is normally a prohibited fixture when it is installed in the same room as an indirect waste. What type of fixture is it that you are questioning?
Incorrect. Please choose another answer.
Indirect wastes are generally not approved for use in rooms that contain toilets. (UPC 804.1). There can be special exceptions when licensed code enforcement officers authorize such a change. One such exception is most commonly the approval for the installation of an indirect waste receptor for an automatic clothes washer. But most installations do not use an indirect waste receptor in any room that houses a toilet.
160 Which of the following locations is not an acceptable location for an indirect waste receptor?
Incorrect. Please choose another answer.
Indirect waste receptors are not to be installed in closets or unvented areas. (IPC 802.4; UPC 804.1). All indirect waste receptors are required to be accessible.
161 Assume that you are installing plumbing for floor drains in a walk-in refrigerator or freezer. The building where this is occurring is a food service establishment. You are working under the normal plumbing code guidelines. In this case, no exceptions have been made. Is it true that the floor drains must connect to the sanitary drainage system through an air gap?
Incorrect. Please choose another answer.
True - In this scenario, it is required that the floor drains connect to the drainage system through an air gap. (IPC 802.1.1; UPC 418, 801.2). However, there could be an exception. When a system is protected from backflow by a backwater valve it may be permissible to make connections between a floor drain and a sanitary drainage system with an air break. Keep in mind that we are talking about a situation when the floor drain is in a walk-in refrigerator or freezer. Waste receptors can sometimes be the hub of a pipe that extends one inch above a water-impervious floor. When this is the case, a strainer is not required on the pipe. Due to potential tripping hazards, most plumbers would opt to make their connections through air gaps.
162 You have just installed a commercial dishwashing machine and have been asked by the property owner to set the temperature for the water at 140 degrees F. What is the maximum allowable temperature for hot water used in commercial dishwashing machines?
Incorrect. Please choose another answer.
Commercial dishwashing machines are allowed to use high-temperature hot water. This is water that is in excess of 140 degrees F. (IPC 702.5; UPC 810.1). When the temperature of hot water will exceed 140 degrees the discharge from the dishwasher must discharge through either an air gap or an air break. Then it must be received by a standpipe made of approved materials for the high-temperature water. In the case of steam pipes, they are not allowed to be connected to a sanitary drainage system. Check your local code requirements to confirm what types of materials must be used to accommodate high-temperature water. You may find that you will have to install special piping, a sump or a condenser.
163 Which of the following types of building usage are most likely to create a need for special wastes?
Incorrect. Please choose another answer.
All of the above locations can require the installation of special waste piping and systems. A special waste is one that may have a harmful effect on a plumbing or waste disposal system. The use of strong chemicals is one reason why special waste piping systems are required. Bio-hazardous waste is another reason for the need to provide a system for special waste. Special waste must be neutralized, diluted or otherwise treated before it can be allowed to enter a sanitary drainage system. Small, personal photography laboratories are rarely required to be equipped with piping for special waste.
164 Clear water waste from a potable source, such as a relief valve on a water heater, must be piped to an indirect waste through an air gap.
Incorrect. Please choose another answer.
True - Clear water waste from a potable water system is to be piped to an indirect waste and must discharge through an air gap. (IPC 802.1, 802.3; UPC 801.2, 812.1). This is as simple as having the discharge pipe terminate six inches above the strainer of a floor drain.
165 You are installing the drain for an ice-making machine in a restaurant. This drain line will terminate to a/an _______________________________.
Incorrect. Please choose another answer.
Indirect waste piping terminates to a floor sink or floor drain and requires an air gap. (IPC 802.1.2; UPC 801.3.3).
166 Indirect waste piping requires a/an _________________________ to protect its discharge contents from backflow.
Incorrect. Please choose another answer.
Before termination to an indirect waste receptor, an air gap must be maintained between the piping and the flood rim of the receptor. (IPC 802.3; UPC 801.2).
167 An indirect waste line that has a diameter of 3/4" is draining into a floor sink. What size air gap should be used between the end of the indirect drain line to the floor sink's flood rim?
Incorrect. Please choose another answer.
The air gap between indirect waste piping and the flood level rim of a waste receptor should be at least twice the effective opening of the indirect waste pipe. (IPC 802.3.1). The size of an air gap on indirect waste piping should not go below 1". (UPC 802.1).
168 Which of the following is the minimum size in indirect waste line piping of an ice-maker machine?
Incorrect. Please choose another answer.
The indirect drain line on an ice-maker machine should be no less than ¾" or the size of the outlet. (UPC 801.3.1).
169 A multiple-compartment sink composed of three wells in a restaurant needs how many indirect waste pipes?
Incorrect. Please choose another answer.
Each well of a multiple-compartment sink needs to discharge independently to a waste receptor. (IPC 802.1.1; UPC 801.3.3). If there are three wells, each well needs an indirect waste pipe to discharge into a floor drain.
170 The drain piping from food prep sinks, bins or other equipment used in direct contact with ready to eat food shall be which of the following?
Incorrect. Please choose another answer.
Drain piping from food prep sinks, bins or other equipment used in direct contact with ready to eat food shall be indirectly connected to a drainage system. (IPC 802.1.1; UPC 801.3.3).
171 You are installing indirect piping to kitchen equipment in a restaurant. A unit has a 1 inch drain. Which of the following sizes of indirect piping can you use?
Incorrect. Please choose another answer.
The minimum size pipe for indirect piping should not be less than the drain size on the unit and, in no case, under a 1/2". (IPC 704.2; UPC 803.3).
172 You are installing a bar sink in a restaurant in a location where the trays cannot be vented. There is, however, a floor sink nearby. What is the maximum length you may run the sink drain line to the floor sink?
Incorrect. Please choose another answer.
60" or 5' is the maximum distance allowed. (UPC 801.4).
173 When installing a dishwasher, the only Code approved method of connecting the drain hose is:
Incorrect. Please choose another answer.
All other connections result in the connection being below the flood rim of the fixture. An air gap is mounted above its flood rim to prevent backflow. (IPC 802.1 and 802.3; UPC 801.2, 807.1).
174 Sterilizers that require waste connections may be indirectly piped to drain receptors. The maximum length of the indirect piping is _____________________.
Incorrect. Please choose another answer.
15' is the maximum distance allowed. (UPC 801.6).
175 Installation of plumbing fixtures receiving discharge from indirect waste pipes require approval by ____________________________.
Incorrect. Please choose another answer.
The plumbing authority having jurisdiction can approve or disapprove the types of plumbing fixtures used. (IPC 105.1; UPC 802.1).
176 Which of the following is true about vents and indirect waste piping?
Incorrect. Please choose another answer.
Indirect piping is typically limited in length and is not trapped, so they do not need to be vented. (UPC 803.3). Waste receptors may need to be trapped and vented. (IPC 802.3).
177 The diameter of indirect waste piping should be _________________ the diameter of the tailpiece or outlet of equipment being served.
Incorrect. Please choose another answer.
The size of the indirect piping can be equal to but not less than the tailpiece or equipment outlet. (IPC 704.2; UPC 803.3).
178 You are roughing-in a P-trap for a washing machine drain in a residential house. The trap must be at least ___________________ AFF.
Incorrect. Please choose another answer.
6" is the minimum distance above the finished floor. (UPC 804.1).
179 The maximum distance of a washing machine trap from the floor is:
Incorrect. Please choose another answer.
18" is the maximum distance above the finished floor for a washing machine trap. (UPC 804.1).
180 Which of the following lengths of a standpipe receptor for a washing machine is permissible measured from above the trap weir?
Incorrect. Please choose another answer.
The standpipe receptor for a washing machine must be at least 18 inches above the trap weir. (IPC 802.4.3; UPC 804.1). The maximum length under the UPC is 30 inches and it's 42 inches under the IPC.
 
181 Indirect waste receptors are allowed to be installed in ____________________________.
Incorrect. Please choose another answer.
Indirect waste receptors can be installed where washing machines are being used. (IPC 802.4.3.1; UPC 804.1).
182 Indirect waste connections are provided for all but which of the following?
Incorrect. Please choose another answer.
Discharges under pressure shall not be connected to a part of the drainage system. This does not apply to sump pumps and sewage wasting fixtures. (UPC 805.1).
183 Condensate drains piping may be connected to all but which of the following:
Incorrect. Please choose another answer.
A tapped waste line is not approved by Code. (IPC 314.2.1.1; UPC 814.1).
184 No water having a temperature above _____________________ degrees shall be discharged under pressure directly into a drainage system.
Incorrect. Please choose another answer.
No water having a temperature above 140° shall be discharged under pressure directly into a drainage system.
185 Undiluted condensate waste from a fuel burning condensing appliance may be discharged into a drainage system made from this material:
Incorrect. Please choose another answer.
Any of the above materials is permitted by Code. (IPC 314.2.2; UPC 1208.5).
186 Sumps and condensers constructed of concrete should have a bottom and well thickness not less than _______________________________.
Incorrect. Please choose another answer.
Sumps and condensers constructed of concrete should have a bottom and well thickness not less than 4". (UPC 810.2).
187 Overflow of condensate from equipment would cause structural damage to a building. Which of the following is a protective measure required by the code?
Incorrect. Please choose another answer.
Where damage to a building or its contents may result from an overflow of condensate from equipment, the codes provide ways to address the matter: (1) use of an auxiliary drain pan; (2) use of an additional separate drain line; (3) use of a water level detection device that will shut off the equipment in the event of a blockage. (IPC 314.2.3; UPC 814.2).
188 A furnace is subject to damage due to condensate overflow of an auxiliary drain pan. What step is required to prevent damage to the furnace?
Incorrect. Please choose another answer.
If a condensate overflow condition occurs, equipment, such as furnaces will be exposed to condensate water. Made of sheet metal, most appliance are not suitable for wet environments due the potential for rust. Insulation is not enough, as it can be degraded by water providing conditions for the growth of mold. To address this situation, the codes require that the equipment be elevated above the flood level rim of the drain pan. (IPC 314.2.3.2; UPC 814.2.1).
189 Are detailed plans of facilities for the treatment of chemical waste required to be submitted to the plumbing authority for approval?
Incorrect. Please choose another answer.
Detailed plans of facilities for the treatment of chemical waste are required by the plumbing authority having jurisdiction for approval. (IPC 803.1; UPC 811.1).
190 Which of the following materials is not Code approved for drainage of chemical waste?
Incorrect. Please choose another answer.
Copper tubing of any grade (M, L, or K) is not approved. (IPC Table 702.6; UPC 811.1).
191 Vent pipes which connect to waste pipes containing chemical waste shall not be made of ______________.
Incorrect. Please choose another answer.
Neither copper nor PVC cell core pipe is approved for chemical waste or vent. (IPC Table 702.6; UPC 811.2).
192 Of the following, who is required to keep a permanent record of the location of chemical waste and vent piping?
Incorrect. Please choose another answer.
The owner is required to keep a permanent record of the location of chemical waste and vent piping. (UPC 811.5).
193 Pump discharge of wastewater from a swimming pool shall be discharged _________________.
Incorrect. Please choose another answer.
Wastewater discharge from a pool must be discharged as an indirect waste. (IPC 802.1.4; UPC 813.1).
194 Condensate piping from condensing fuel burning appliances should drain into all of the following except:
Incorrect. Please choose another answer.
Condensate should not drain into a street, alley or other public places that would cause a nuisance. (IPC 314.2.1; UPC 814.1). All other choices are examples of indirect drains.
195 The minimum slope of condensate piping into the drainage system is:
Incorrect. Please choose another answer.
1/8" per foot, or 1% slope, is the minimum approved slope. (IPC 314.2.1; UPC 814.1).

Vents and Venting 

196 Which of the following is accomplished by the installation of plumbing vents?
Incorrect. Please choose another answer.
Plumbing vents serve multiple purposes. Their primary purpose is to keep sewer gas from entering a building's enclosed air. This is done in two ways. The first is that sewer gas is vented out of a plumbing system by a vent and the gas is emitted into open air outside of the building where the plumbing is installed. By preventing plumbing traps from being siphoned dry vents prevent sewer gas from entering buildings through unprotected traps. A side benefit of vent installation is that the drains being served by the vent will drain faster as a result of air admittance into the drain.
197 Which of the following types of fixtures can be served by a combination-waste-and-vent system?
Incorrect. Please choose another answer.
Combination-waste-and vent (CWV) systems do not require independent vents on all fixtures. Instead of a vertical vent the fixtures approved for a CWV installation are installed with oversized drains. Due to the larger drain diameter the fixture obtains the needed air for drainage in the top section of the oversized piping. Urinals, toilets and bidets are not allowed to be installed on CWV systems. (IPC 915.1; UPC 910.7).
198 Assume that you are installing a CWV system for part of the plumbing fixtures in a building. You will install a DWV system for toilets. This building contains floor drains, lavatories, sinks, toilets, bathtubs, showers, drinking fountains, bidets, garbage disposers and slop sinks. Which of the following fixtures should you not install on the CWV system?
Incorrect. Please choose another answer.
You are not allowed to install bathtubs on CWV systems. (IPC 915.1). Floor drains, drinking fountains and lavatories are allowed to be installed with a CWV system. So are sinks. Toilets are not allowed on a CWV system. Neither are bidets or garbage disposers.
199 As an apprentice plumber you are working on the installation of a DWV system with a journeyman plumber. You were studying about the use of relief vents the night before. Your journeyman plumber is taking a break and you ask about using relief vents with circuit vents. The answer you get is that relief vents are not allowed to be used in conjunction with circuit vents. Is this true or false?
Incorrect. Please choose another answer.
False - It is fine to use relief vents in conjunction with circuit vents. (IPC 914.4; UPC 911.3). It is common for a relief vent to be installed near a soil stack that is accepting the waste from multiple fixtures that are being served by a circuit vent and a vent stack.
200 Traps must be set _______ with respect to the trap seal.
Incorrect. Please choose another answer.
The trap seal contains water or liquid and must be set level to maintain the trap seal. (IPC 1002.7; UPC 1005.1). If not set level, the trap seal water or liquid will drain out and sewer gasses will enter the building. Where necessary, the trap seal must be protected from freezing.
201 Individual vents serve only one fixture. These vents are _________.
Incorrect. Please choose another answer.
Individual vents are allowed to be combined with other vents in a venting system when the arterial vent of the system will terminate outside of the building into open air. (IPC Definitions, 904.3, 910.1; UPC Definitions, 906.1). It is never acceptable for a vent to terminate in the attic of a building.
202 Relief vents are installed with trap arms that extend beyond the allowable distance between a trap and its vent. Assume that you are installing piping of various sizes that will require relief vents. Pipe diameters for the drains include 1.5 inches, 2 inches and 3 inches. Which of the following describes the minimum diameter of a relief vent for each of the drain sizes.
Incorrect. Please choose another answer.
A relief vent can be one-half the diameter of the drain pipe being served by the vent. (IPC 906.2; UPC 904.1). In this scenario each drain can be vented with a 1.5 relief vent. If one of the drains had been piped with a 4-inch diameter it would require a relief vent with a minimum diameter of two inches.
203 You are installing a drain that will be vented with a circuit vent. You check your code book to find out what the allowable grade on the vent will be so that you can drill holes in the framing studs that will allow an approved installation. That is when you find that a horizontal drain that is being vented by a circuit vent is required to have a maximum grade of one inch per foot.
Incorrect. Please choose another answer.
True - A maximum allowable grade for a horizontal drain that is circuit vented is one inch per foot (an 8.3 percent slope). (IPC 914.3; UPC 911.4).
204 Circuit vents can do which of the following?
Incorrect. Please choose another answer.
Circuit vents are used when venting a battery of fixtures. The vents may be tied into other vents that extend to outside air. This includes vent stacks and stack vents. The diameter of a circuit vent must be at least one-half the size of the drain that it is serving.
205 Which of the following describes a branch vent?
Incorrect. Please choose another answer.
Branch vents are vents that are installed horizontally. They act as an arterial vent that other vents can be connected to. When a branch vent is piped with piping that has the same diameter of the drain being served by the vent the branch vent may have an unlimited developed length.
206 Which of the following types of vents are used only for the purpose of venting?
Incorrect. Please choose another answer.
Vent stacks are used only as vent pipes. They extend upward from a drainage system to open air. Other vents may be connected to vent stacks. Any vent stack is determined to be a primary vent.
207 Vents are exempt from the need for protection from freezing since they transport only air.
Incorrect. Please choose another answer.
False - Vents are required to be protected against freezing when the region of a vent installation is subject to freezing conditions. (IPC 903.6; UPC 906.7). To be more specific, the ruling is usually that vents do not require freeze protection except in areas when temperatures may reach a low of zero degrees F. One way of fighting freezing conditions is to expand the pipe sizing for a vent. As an example, a 3-inch vent is considered unlikely to freeze as a result of condensation and freezing temperatures that reach a level of zero degrees F. If this over sizing method is used, the increased vent sizing must apply to all exterior vents and at least one foot inside of the building housing the vent. Vent terminals must not terminate under the overhang of a structure with soffit vents.
208 Which of the following types of vents are allowed to be used as both a vent and as a conduit for waste disposal in a sanitary drainage system?
Incorrect. Please choose another answer.
Vents stacks are allowed only to be used as a vent. Stack vents and wet vents are allowed to be used as both drains and vents. Offsets installed in stack vents must not be made until the stack vent rises to a level that is at least six inches above the flood-level rim of the highest fixture being served. (IPC 913.3; UPC 905.3).
209 You are installing a DWV system. In this system you want to use common vents to reduce the cost of plumbing materials and labor. You know that a common vent is an individual vent that is allowed to vent multiple traps. There are certain regulations on when common vents can be used. Identify the correct answer below that shows a situation where common vents are allowed to be installed.
Incorrect. Please choose another answer.
Common vents are restricted to use only for fixtures that are located on the same floor level and elevation. (IPC 911.1; UPC 905.6). When fixtures are at different floor levels a single common vent cannot be used. An additional common requirement is that a common vent shall not serve more than two traps. However, some local codes may allow up to three traps for lavatories to be vented by a common vent.
210 Island vents are only allowed to be installed for which of the following fixtures?
Incorrect. Please choose another answer.
The only fixtures allowed to be vented with island vents are sinks and lavatories. (IPC 916.1; UPC 909.1). When an island vent is installed, it must rise to the highest point possible in a cabinet. Even though the plumbing is called an island vent it is treated as a drain since it does not rise above the flood-level rim of the fixture being served. The vent portion of the piping is required to contain a cleanout. Connecting an island vent to a general venting system is allowed once the island vent rises a minimum of six inches above the flood-level rim of the fixture being served by the vent. The vents are rarely used. Their most common use is in kitchens where sinks are installed in island cabinets.
211 When offsets exist in a stack vent, they must not be installed prior to the stack vent reaching a height that is at least eight inches above the flood-level rim of the highest fixture being served.
Incorrect. Please choose another answer.
False - Stack vents must rise a minimum of six inches above the flood-level rim of the highest fixture being served before it can be offset with fittings. (IPC 905.5; UPC 905.3).
212 Wet vents are allowed for use with fixtures in a single bathroom group. A wet vent is _______.
Incorrect. Please choose another answer.
Wet vents serve as a vent for one fixture and a drain for a different fixture when the two fixtures exist in the same bathroom group if the wet vent is providing a horizontal branch drain. Fixtures must discharge downstream of the wet vent. A benefit to using wet vents is reduced cost in both the labor and material required to provide a plumbing installation. When a wet vent is used a vertical vent for a fixture is eliminated. Vertical wet vents can be used to vent any combination of fixtures within two bathroom groups located on the same floor level.
213 Crown vents can be installed on which of the following?
Incorrect. Please choose another answer.
Crown-vented traps are not allowed in modern plumbing systems. (IPC 1002.3; UPC 1004.1).
214 Sumps used to hold sewage or house sewage pumps are required to be ________.
Incorrect. Please choose another answer.
Sumps for sewage pumps that remove sanitary waste are required to be vented to outside air. (IPC 712.1, 712.3.2; UPC 710.10). The vent cannot be tied into a general venting system if a pneumatic sewer ejector pump is to be installed. When a typical sewer pump is to be used the vent can tie back into a general venting system. Generally, the minimum diameter of a vent for a sewage sump will be required to be two inches in diameter. In addition to proper venting, sewage sumps must be equipped with gas-tight covers.
215 Soil stacks that have up to ten branch intervals are required to be equipped with relief vents.
Incorrect. Please choose another answer.
True - Soil and waste stacks in buildings having more than 10 branch intervals must be equipped with a relief vent. (IPC 908.1; UPC 907.1).
216 The size of a main vent pipe is based on:
Incorrect. Please choose another answer.
The IPC and UPC determine the size of vent piping based on the drainage fixture units being served and the developed length of the vent piping. The codes provide tables to use to determine the vent pipe size. (IPC Table 906.1; UPC Table 703.2).
217 Using the tables in the IPC and the UPC for sizing vent piping, what size vent pipe should be used if a building uses a 4 inch waste pipe, with 250 total drainage fixture units, and vent piping with a developed length of 300 feet?
Incorrect. Please choose another answer.
Using the Table 906.1 in the IPC and Table 703.2 in the UPC, a 4" vent pipe should be used.
218 What is the minimum size vent piping diameter that can be used under the codes?
Incorrect. Please choose another answer.
The codes set the minimum size at 1 ¼". (IPC 906.1; UPC 904.1). However, this size is rarely used in modern plumbing and venting. The smallest size typically used is 1 ½" piping.
219 Assume that you are installing a DWV system in a two-story home. The house has several roof lines. For example, the kitchen is counter levered off of the main foundation and equipped with a shed roof design. This roof is below the double-hung windows of the bedrooms on the second floor. The kitchen sink must be vented. However, the outlet location of the vent pipe could be affected by window placement above if the windows are able to be opened. For this scenario assume that the second-story windows do open. Which of the following gives the proper code requirement for the placement of the kitchen vent?
Incorrect. Please choose another answer.
It is not acceptable to risk having sewer gas enter open windows. With this in mind, vents that are within 10 feet of windows must extend a minimum of three feet above the window. The two options are to keep vents at least 10 feet away from windows or extend them to two feet above the windows. (IPC 903.5; UPC 906.2)
220 Some codes require buildings that have soil stacks with more than _____ branch intervals to be equipped with vent stacks.
Incorrect. Please choose another answer.
Some codes require buildings that have soil stacks with more than five branch intervals to be equipped with vent stacks. These vent stacks are usually installed close to a soil stack. You may find that the vent stack must be installed within 10 times its pipe size on the downward side of a soil stack. Given this factor, a 3-inch vent stack would have to be within 30 inches of a soil stack. (IPC 904.2; UPC C 401.2)
221 You are running the waste and vent system in a 3-story building. The vent stacks must terminate through the roof. You have been told the roof will be used for social activities. How far above the roof, at a minimum, must the vent terminate above the roof?
Incorrect. Please choose another answer.
When a roof is to be used for any other purpose other than weather protection the vent extension must terminate at least 7 feet above the roof. (IPC 903.1.2; UPC 906.3)
222 You have just completed the waste system for two sinks. You want to connect the vent into the vent stack. At a minimum, how far above flood level of the fixture should the vent be connected into the vent stack?
Incorrect. Please choose another answer.
Every dry vent must rise vertically to a minimum of 6 inches above the flood level rim of the highest trap or trapped fixture being vented. (IPC 905.4; UPC 905.3)
223 You are connecting two back-to-back lavatories, two urinals and two water closets to one horizontal branch. What are the maximum number fixtures that can be connected to a horizontal branch?
Incorrect. Please choose another answer.
The plumbing code allows a maximum of eight fixtures connections to a horizontal branch drain. This is also called a circuit vent. (IPC 914.1; UPC 911.4.1)
224 You have connected all the vertical vents to one common vent stack. How far above the roof should the vent terminate?
Incorrect. Please choose another answer.
Vent stacks typically terminate at least 6 inches above the roof if it is not covered. (IPC 903.1.1; UPC 906.1). The UPC sets the minimum at 10 inches if snow or frost closure is likely. (UPC 906.7). This allows fresh air to the vent stack and prevents moisture from freezing over the vent terminal and closing over in cold weather.
225 What is an air admittance valve and where is it installed?
Incorrect. Please choose another answer.
An air admittance valve is a device that when connected to a drainage system will allow air to be admitted to the drainage system. This valve can be used in lieu of a vent through the roof. (IPC 918).
226 Where does the soil stack end and the vent stack begin?
Incorrect. Please choose another answer.
The soil stack is the lowest part of the plumbing system that carries away waste and above the waste entry, at that point, the pipe becomes the vent stack. The vent stack receives no waste, only air to vent the plumbing drainage system. The vent stack connects above all vent branches and then terminates 12 inches above the roof.
227 How close can a fixture vent be installed in relation to a trap weir?
Incorrect. Please choose another answer.
A fixture vent cannot be installed within 2 pipe diameters of the trap weir. (IPC 909.3)
228 You have been asked to install a waste and vent system. When digging the trenches, you reveal that the soil has coal ash mixed with acid waste. What type of waste and vent piping would be best suited for this soil condition?
Incorrect. Please choose another answer.
All vent piping that consists of metal or cast iron will not resist the chemicals or coal ash that exists in the soil. This would deteriorate the pipe and cause the pipe to leak as the acids eats through the metal or cast iron. The PVC pipe is a nonmetallic pipe and is not affected by acid waste in the soil.
229 You are installing a bar sink. The counter area does not allow for a vent stack to be installed. How can ventilation be provided when normal venting is not possible?
Incorrect. Please choose another answer.
A loop vent will provide sufficient air to prevent a trap seal from being lost. The system is designed for â..." waste and â..." make up air within the piping system.
230 How can a trap primer protect the venting system?
Incorrect. Please choose another answer.
The trap primer will admit small amounts of water into the trap that will prevent negative pressure in the vent system. By installing a trap primer, it will allow water to replenish the trap which will allow the sewer gas to be removed within the vent system.
231 You are installing a tub, shower and lavatory in a residential home. You must select a vent system using a pipe for the waste and vent. What type of system would you select?
Incorrect. Please choose another answer.
A wet vent will serve both the waste and vent using one pipe. The smaller fixtures will drain to the larger waste and vent pipe and the vent will run through the roof.
232 You are installing a two inch kitchen sink stack. Why is it good plumbing practice to install a 45 degree offset before exiting the roof?
Incorrect. Please choose another answer.
PVC expands and contracts when heated and cooled; the offset will prevent damage to the roof flashing and prevent noise within the piping system by means of movement in the wall.
233 You are installing a trap stand mop sink. The size of the trap stand is 3 inches and the trap stand is supported by a brace connected to the floor. The waste pipe is connected with a sanitary tee behind the wall. What would be the minimum size vent pipe that could be used?
Incorrect. Please choose another answer.
The plumbing code allows the vent piping to be installed ½ the size of the drain system to the fixture that is located above the ground, and is individually vented. (IPC 906.1; UPC 904.1).
234 How do you determine the size of the vent piping to be installed on a waste system?
Incorrect. Please choose another answer.
You determine the size of the vent piping to be installed on a waste system by the number of DFU's that are assigned to the fixture. You must add the total number of fixtures of the waste piping system and refer to the plumbing code to calculate the size of the pipe that is required. (IPC 906.1; UPC 904.1)
235 In a vent system, in what direction are the fittings pitched?
Incorrect. Please choose another answer.
The vent system rising will allow sewer gas to travel up the pipe and out the vent stack; it will also allow any condensation that is in the piping system to travel down the waste system and be removed through the entire system.
236 If an individual vent has two traps it is a _________.
Incorrect. Please choose another answer.
A common vent is an individual vent that is to vent two traps or trapped fixtures. It can serve two separate fixtures, but each fixture must have a separate trap. The common vent can serve as the vent for both fixtures. (IPC 911.1; UPC 905.6).
237 When can a combination waste and vent system receive the discharge from a urinal or water closet?
Incorrect. Please choose another answer.
A combination waste and vent system is not permitted to connect to urinals or water closets. (IPC 915.1; UPC 910.7). The fixtures that can connect to a combination waste and vent system is floor drains, sinks, lavatories and drinking fountains.
238 A _______ is any part of the piping system except a riser, main or stack.
Incorrect. Please choose another answer.
Any part of the piping system except a riser, main or stack is a branch. Risers, stacks and mains are the principal arteries of water and waste plumbing systems. Pipes that connect to these arteries are called branches.
239 When using an air admittance valve, it should have at least ___ stack(s) through the roof.
Incorrect. Please choose another answer.
For vent systems utilizing air admittance valves, not less than one stack vent or vent stack within each plumbing system shall extend outdoors to the open air. This will prevent any type of gases from the drainage system to remain in the pipe. (IPC 918.7)

Traps and Cleanouts 

240 You are installing a sewer for a home and connecting the sewer to a building drain. Cleanouts are required to be installed within the sewer piping. For which of the following intervals would a cleanout be required for horizontal drainage piping?
Incorrect. Please choose another answer.
Cleanouts are required during the installation of a sewer when the sewer connects to a building drain. The normal spacing of cleanouts in straight runs of a sewer pipe is 100 feet. (IPC 708.1.2; UPC 707.4; 719.1). There are exceptions to these rules, but the information here is the typical installation requirement for cleanouts associated with sewer piping. Additionally, any change in direction in excess of a 45-degree bend (IPC) or 135-degrees in the aggregate (UPC) requires the installation of a cleanout in sewer piping.
241 Cleanouts are required where building drains intersect with sewers. Which of the following locations is acceptable for a typical cleanout installation under these conditions?
Incorrect. Please choose another answer.
The cleanouts used at the junction of a building drain and sewer can usually be installed on either side of the foundation between the two pipes. Most plumbers, real estate developers and builders prefer the cleanout to be installed outside of the foundation wall. In the case of a serious sewage backup this keeps the cleanout opening outside of the structure being served. In the event that a cleanout for a sewer connecting to a building drain is to be made inside the foundation, a plumber may be required to extend the riser of the cleanout pipe to a point above the flood-level rim of fixtures being served by a horizontal drain. (IPC 708.1.3; UPC 707.4).
242 If three 45-degree bends are used to make an offset, a cleanout is required at the top of the horizontal drain within 24 inches of where it connects with the last 45-degree bend.
Incorrect. Please choose another answer.
False - Cleanouts are not required when a drain pipe makes a turn of no more than 45 degrees (IPC 708.1.4) or less than 135 degrees (UPC 707.4). The fact that three 45-degree fittings are used to make an offset is not reason to require the installation of a cleanout.
243 You are responsible for installing a sewer with an 8-inch diameter. Which of the following distances between cleanouts would meet the code for sewers that have 8-inch diameters?
Incorrect. Please choose another answer.
Due to the large diameters of these sewers the cleanouts may be spaced up to 400 feet (IPC) or 300 feet (UPC) apart. They are still required at points of changes in direction. When manholes are used for access to large sewers the manholes and their covers must be of approved types. All sewer cleanouts are required to be accessible. This is accomplished by installing a riser from the sewer to approximately ground level for the finished grade. The cleanout fitting is then installed on the riser pipe. (IPC 708.1.2; UPC 719.6).
244 Horizontal drainage branches must be fitted with cleanouts. Assume that you are installing a horizontal branch that has a total length of 60 feet. This is a 3-inch branch. The pipe takes one 45 degree change of direction. How many cleanouts are required for this installation?
Incorrect. Please choose another answer.
This scenario requires 1 cleanout under both the IPC and the UPC.
Under the IPC, a cleanout is needed for every 100 feet of horizontal drain piping and one for every change of direction exceeding 45 degrees. No change of direction exceeds 45 degrees in this scenario, so the focus is on the length. The length of the run is under 100 feet, so only one cleanout is needed. (IPC 708).
Under the UPC, a cleanout is needed for every 100 feet of developed length of pipe or a fraction thereof. Furthermore, a cleanout is needed for every aggregate change of direction that exceeds 135 degrees. The aggregate change of direction is less than 135 degrees, so no cleanouts are needed for the change in direction. Using these standards, we need 1 cleanout based on the distance of 65 feet. (UPC 707.4).
245 Normally a cleanout is required at the junction of a building drain and a sewer. Can you think of a situation where this might not be the case? Let's say that the building drain has a 3-inch diameter. This limits the number of water closets installed in the structure to a total of two, but it is an acceptable size for a building drain. How will you install the piping of the building drain to avoid the need for a junction cleanout where the building drain connects to a sewer? Is it true or false that you can install a cleanout 8 feet from the junction point and be exempt from a junction cleanout?
Incorrect. Please choose another answer.
True - A cleanout installed in a building drain within 10 feet of the developed length of piping upstream of the junction can eliminate the need for a junction cleanout. (IPC 708.1.3; UPC 719.1 - cleanout required near the connection between the building drain and the sewer).
246 What size cleanout must be used with a 2 ½ inch horizontal drain pipe?
Incorrect. Please choose another answer.
Under the IPC, the cleanout must be the same size as the piping served, provided the pipe being served is 4" or under. If over 4", only a 4" cleanout need be used. (IPC 708.1.5). Under the UPC, a 2 ½" pipe needs a 2 ½" cleanout. (UPC 707.1 table).
247 When can a cleanout be used for the installation of a new fixture? In other words, what makes it acceptable to remove a cleanout plug, replace it with a male adapter and then extend piping from that point to a new fixture?
Incorrect. Please choose another answer.
Fittings housing cleanout plugs are not allowed to be used as a connection point for a drainage pipe that will serve a new fixture, unless the connection is approved by a code officer and a new cleanout is provided to replace the cleanout being changed over to a connection point for drainage piping. (IPC 708.1.12).
248 Approved two-way cleanouts are allowed in locations where building drains connect with sewers.
Incorrect. Please choose another answer.
True - Approved two-way cleanouts are allowed at the junction of building drains and sewers. (IPC 708.1.9; UPC 707.4). Any type of approved cleanout can be used. These types could be any of the following:
• Rubber caps that are installed with stainless steel clamps
• Female adapters fitting with cleanout plugs
• Test tees are suitable cleanouts
• Special cleanouts that allow the cleaning of a drain in the direction of drainage flow.
249 You are plumbing a multi-family dwelling. This structure will house four apartments. As you are installing the DWV piping you must know when and where to install required cleanouts in the drainage piping. Which of the following describes a situation where a cleanout is not required?
Incorrect. Please choose another answer.
Water closets are considered viable cleanouts. Removable P traps are as well. (IPC 708.1.6)
250 When installing cleanouts which of the following is required?
Incorrect. Please choose another answer.
Cleanouts are required to be accessible. Adequate space in front of the cleanout is required for effective drain cleaning. Fittings installed to accept a cleanout must be installed with the same direction of flow that is being used for the drain that the cleanout serves. The size or required cleanouts is determined by the diameter of the pipe being served. Pipes under the diameter of four inches require cleanouts equal to the diameter of the pipe being served. Larger drains can usually be served by cleanouts with 4-inch diameters.
251 Cleanouts installed for under-floor piping are required to be installed at least 12 inches above the finished floor level.
Incorrect. Please choose another answer.
False - When practical, cleanouts for under-floor piping should be installed at a height that is 18-48 inches above the finished floor level. This is not always practical. An example could be a grocery store where the building is large and requires cleanouts throughout travel paths. When this is the case, the cleanout can be installed flush with the finished floor. It must not be equipped with a raised-head cleanout plug. A sunken-head cap must be used to remove tripping hazards. (IPC 708.1.11; UPC 707.9).
252 Under the code, cleanouts cannot be installed at intervals exceeding:
Incorrect. Please choose another answer.
Cleanout spacing is not to exceed 100' under the codes. (IPC 708.1.1; UPC 707.4).
253 Which of the following materials is acceptable for cleanout fittings, plugs and caps?
Incorrect. Please choose another answer.
The codes provide tables with acceptable materials for cleanout fittings, plugs and caps. (IPC Table 702.4; UPC Table 707.2). Only approved materials may be used for the construction of cleanout plugs. The plugs must be durable and strong enough to be removed throughout the life of the plumbing system.
254 To allow for adequate drain cleaning, the minimum clearance in front of a cleanout that has a diameter of 2 inches is 16 inches.
Incorrect. Please choose another answer.
False - The minimum required distance in front of a 2-inch cleanout is 18 inches. (IPC 708.1.10; UPC 707.9). This space is needed to allow for successful drain cleaning methods. Never point a cleanout towards a floor or wall without adequate space being provided. With a 3-inch pipe, the clearance under the IPC is still 18 inches, but under the UPC it goes to 24 inches.
255 Manholes are typically required at maximum intervals of ______.
Incorrect. Please choose another answer.
When a sewer has a diameter that exceeds 8 to 10 inches a manhole is normally used as a cleanout. When this is the case most jurisdictions require the manholes to be located at maximum intervals of no more than 300-400 feet. (IPC 708.1.2; UPC 719.6). The manholes must be protected from flooding. Covers used on manholes must allow gases from the sewer to escape to open air. Flexible compression connections are normally used to install manholes. The connections must not be closer than one foot to a manhole and not more than three feet away from a manhole.
256 Traps for plumbing fixtures are sealed with a liquid level in the trap. Water is the liquid most commonly used. What are the minimum and maximum depths of a trap seal?
Incorrect. Please choose another answer.
Trap seals are required to have a minimum depth of two inches and a maximum depth of four inches. (IPC 1002.4; UPC 1005.1). Special circumstances can alter these figures, but they must be approved by a code officer. If a trap seal is subject to going dry as a result of evaporation a trap primer must be installed to ensure a continuous liquid trap seal.
257 Cover plates, trim covers and access doors may be used with cleanouts. These access points may not be covered with mortar, plaster or other permanent material.
Incorrect. Please choose another answer.
True - Cleanout plugs must be accessible. (IPC 708.1.11.1; UPC 707.8). Cover plates, trim covers and access doors for clean out plugs must not be covered by mortar, plaster or other permanent material.
258 The installation of a P trap is required to be vented properly. If such a vent is not installed the trap may _______.
Incorrect. Please choose another answer.
P traps are required to be vented properly to avoid the risk of the trap seal being removed by backpressure. If the trap seal is removed harmful sewer gas can infiltrate interior air space in a structure. This can result in both annoying smells and potential health hazards. Since P traps are self-cleaning traps the trap seal can be siphoned out of the traps if a vent is not installed to protect the trap seal.
259 Which of the following types of traps are not allowed in new plumbing installations?
Incorrect. Please choose another answer.
P traps are the modern plumbing trap of preference. S traps are still in use in older buildings, as are many other types of traps, but they are not approved for new installations. Other types of traps that are no longer allowed in new plumbing installations include the following:
• Crown-vented traps
• House traps
• Running traps
• Bell traps
• Drum traps, except when they are used as solid interceptors or in chemical waste systems.
• Traps that depend on moving parts or interior partitions
(IPC 1002.3; UPC 1004.1).
260 Laundry tubs and service sinks must be double-trapped due to the nature of their use.
Incorrect. Please choose another answer.
False - No plumbing fixture is allowed to be double trapped. (IPC 1002.1; UPC 1004.1).
261 The tailpiece between a fixture drain and the fixture's trap must not be longer than ______.
Incorrect. Please choose another answer.
The maximum allowable length for a tailpiece between a fixture and its trap is 24 inches. (IPC 1002.1); UPC 1001.2). Why is this important? The first reason is that it is a code requirement. When a tailpiece is too long it allows a straight drop from a fixture to its trap that may result in splash back. When this happens, solids in the drain waste can hit the bottom of a trap and bounce back up the tailpiece. In some cases, the result can be solid waste clinging to the tailpiece. In some cases, such as a toilet installation, the waste may collect under the water closet and contribute to an eventual stoppage that will require drain cleaning. Therefore, the vertical drop is limited to 24 inches.
262 Which of the following types of traps are required to be equipped with a device that controls the water flow through the trap in a manner that prevents the water flow from exceeding the rated flow of the trap?
Incorrect. Please choose another answer.
Grease traps are required to be fitted with devices that control water flow. (IPC 1003.3.5.2; UPC 1017.4). The maximum water flow must not exceed the rating given for the grease trap being protected. If water flow exceeds the maximum flow rate, the performance of a grease trap can suffer and result in an inadequate trapping of grease materials.
263 Dishwashers and clothes washers may discharge into a kitchen sink as an indirect waste.
Incorrect. Please choose another answer.
False - Dishwashers are allowed to discharge through kitchen sinks. Clothes washers are not. (IPC 409.4; 1003.6; UPC 1001.2). A clothes washer can discharge into a laundry sink or a service sink or a dedicated indirect waste, but it must not discharge into a kitchen sink. (IPC 406.2; UPC 1001.2)
264 Which of the following types of traps are allowed to be installed below a concrete floor when access is not available without removal of the floor material?
Incorrect. Please choose another answer.
P traps that use solvent-weld joints, or other suitable permanent joints, may be used below grade for concrete slabs. No easy access is required for these traps. Situations when such traps will be used include floor drains and shower drains. It is not acceptable to use traps that rely on slip nuts and washers for a trap connection to drainage piping. Since bathtub traps cannot be connected until after a concrete floor is poured, cured and present, a tub box (also known as a trap box) must be provided. This box makes the under-floor piping accessible for an above-grade connection, which can be made with slip nuts and washers. However, solvent-weld P traps are most commonly used for this purpose. The tub box must be protected from water, insect and rodent infiltration.
265 Which of the following is a grease trap?
Incorrect. Please choose another answer.
Grease traps are actually not traps at all. Yes, they are called grease traps. But, they are actually grease interceptors. They are typically installed in building uses other than residential dwellings. The purpose of the device is to retain grease that would otherwise clog drains, sewers and waste-treatment facilities. They can be small or large. Grease traps must be accessible for cleaning.
266 Plumbing interceptors are installed to control which of the following?
Incorrect. Please choose another answer.
Interceptors in a plumbing system are designed to control grease, sand, oil and other materials. Sand interceptors are required to be readily accessible. A sand interceptor requires a water seal that is at least six inches deep. Not all interceptors are the same. For example, and interceptor used for a commercial laundry facility is not required to have a liquid trap seal. These devices can use wire to limit the introduction of lint, string and other objects into a drainage system. This is not to say that the indirect waste receptor for automatic clothes washing machines is not required to be trapped with P traps that are vented and that retain a liquid trap seal.
267 You are on a job and are doing the final plumbing and the setting of fixtures. Most of the work is done. There is still a laundry sink to trap and set the faucet on. After installing the faucet and connecting the water supplies you are ready to trap the sink. This sink has the minimum-size drain arm allowed for the fixture. In this situation, it would be a code violation to connect the fixture with a 2-inch P trap.
Incorrect. Please choose another answer.
True - It would be a code violation to install a 2-inch trap on a laundry sink that is piped with a minimum-diameter trap arm. The trap arm size would be 1.5 inches. You cannot install a trap that has a larger diameter than the drain that is serving a fixture. (IPC 1002.5; UPC 1003.3). It would be fine to install a 1.5 inch trap on a lavatory that has a 1.25 tailpiece and a 1.5 drain. If the laundry sink had a 2-inch drain, you could use a 2-inch trap. But, you cannot install a 2-inch trap on a 1.5 inch drain.
268 What is the grease retention capacity, measured in pounds of grease, of a grease trap/interceptor that has a total flow-through rating of 12 gallons per minute (GPM)?
Incorrect. Please choose another answer.
In essence, you can take the total flow-through rating based on GPM and determine grease retention capacity, in pounds, buy doubling the flow-throw rating. In this case the rating for flow-through is 12 GPM. (IPC Table 1003.3.5.1). That allows for 24 pounds of grease. If the flow-through was 15 GPM, the grease trap would be allowed to hold up to 30 pounds of grease. You can find a sizing chart in your local code book that will show this factor clearly.
 
Total Flow-Through Rating in GPMGrease Retention Capacity in Pounds
714
1020
1530
1836
2550
50100
100200

 
269 Which of the following is a common type of establishment that would be required to be equipped with an oil separator?
Incorrect. Please choose another answer.
Oil separators are required equipment at several types of establishments. (IPC 1003.4; UPC 1017.1). The type of use of the facility dictates the need for an oil separator. Examples of the types of building uses that require oil separators include the following:

• Auto repair garages
• Gasoline stations equipped with grease racks
• Grease pits
• Work racks for automotive repair
• Car-washing facilities
• Factories where oil-bearing, grease-bearing, and flammable wastes may enter the building's drainage system
270 Which of the following locations are likely to contain a backwater valve?
Incorrect. Please choose another answer.
Backwater valves are installed on drains and sewers. They act as something of a check valve to keep downstream waste from entering the drainage system that the backwater valve is protecting. These devices prohibit sewers from backing up into building drains. A backwater valve must be installed in such a way to make it readily accessible. (IPC 714.3; UPC 710.6).
271 Interceptors are installed to prevent the discharge of oil, grease, sand and other substances into which of the following?
Incorrect. Please choose another answer.
The interceptors take substances such as oil, grease and sand out of wastewater before they are discharged to sewer systems. The codes specifically state their purpose as protecting the public and private sewer systems, include sewage treatment plants. (IPC 1003.1; UPC 1009.1).
272 You are working in a commercial facility. The facility is known to discharge chemicals, enzymes and emulsifiers. Which of the following devices will you not connect to a drainage source for these wastes?
Incorrect. Please choose another answer.
The plumbing code prohibits food waste grinders from accepting the following types of waste:

• Emulsifiers
• Chemicals
• Enzymes
• Bacteria
273 The minimum standpipe height for an indirect waste to accept the drainage from an automatic clothes washing machine is 18 inches.
Incorrect. Please choose another answer.
True - Standpipes installed to collect the waste from clothes washers are required to have a minimum height of 18 inches. (IPC 802.4.3; UPC 804.1). The maximum height under the UPC is 30 inches and 42 inches under the IPC. Some local code requirements may have exceptions to this rule, but the information here is the normal code requirement.
274 How many traps are required to be installed for a three-bowl kitchen sink?
Incorrect. Please choose another answer.
A three-bowl kitchen sink can be plumbed with a continuous waste that collects discharge from all three sink bowls and dumps the waste into a single trap. (IPC 1002.1; UPC 1001.2). The trap must be vented. When a single trap is used for a three-bowl kitchen sink, the trap must be in a location that is central to all three of the sink bowls.
275 Traps must not be ______.
Incorrect. Please choose another answer.
Trap installations must not be crooked. If the trap seal is not level, it can be at risk of siphonage which would result in the loss of the trap seal. (IPC 1002.7; UPC 1005.1). A trap that is extremely crooked may not have the minimum 2-inch trap seal of liquid that is required. Workmanship is always a factor in a plumbing installation.
276 Which of the following fittings are approved for changes in piping direction from vertical to horizontal?
Incorrect. Please choose another answer.
Both of the listed fittings are allowed for changes in piping from a vertical to horizontal position. (IPC Table 706.3; UPC 706.2). Additionally, any fitting allowed for changes in horizontal-to-horizontal direction are also approved for use when turning to a horizontal position.
277 Which of the following is an allowable distance for a 1.5" drain arm to a fixture trap?
Incorrect. Please choose another answer.
The maximum allowable horizontal distance is 30" under the IPC and 42" for the UPC. (IPC 1002.1; UPC Table 1002.2).
278 What may result if a drain arm exceeds its maximum length from trap to vent?
Incorrect. Please choose another answer.
If back siphonage occurs, the trap will lose its liquid trap seal resulting in sewer gas escaping from the drain. A cross connection occurs when non-potable water siphons back into the potable water supply.
279 One trap arm may serve a total of how many P-traps?
Incorrect. Please choose another answer.
Not more than one trap is permitted on a trap arm. (IPC 1002.1; UPC 1002.1)
280 Which of the following fixture traps is permitted to receive waste from another fixture?
Incorrect. Please choose another answer.
A laundry tub may accept the discharge from an adjacent domestic washing machine. (IPC 406.2; UPC 1001.2)
281 The maximum vertical distance between the weir of the trap and the fixture outlet should not exceed _________________.
Incorrect. Please choose another answer.
24" is the maximum allowable distance for the riser on the fixture. (IPC 1002.1; UPC 1001.2).
282 You are roughing-in a drain arm to a future lavatory fixture. In order to comply with the Code, you should measure from the _______________________ to make sure you do not exceed the maximum distance.
Incorrect. Please choose another answer.
Measurements are determined from the trap weir to the inner edge of the vent serving that fixture.
283 How many traps are permitted to accept the waste water from a 3-compartment sink?
Incorrect. Please choose another answer.
One trap shall be permitted to serve a set of no more than three single-compartment sinks. (IPC 1002.1; UPC 1001.2).
284 The minimum distance between a vent and trap 1.5" in diameter is _________________.
Incorrect. Please choose another answer.
The minimum distance between any size trap and inner edge of the vent shall be 2 times the diameter of the trap arm. (IPC 909.3; UPC Table 1002.2)
285 Which of the following measurements is permitted for a 2" trap arm from a vent?
Incorrect. Please choose another answer.
5' or 60" is the maximum allowable distance for a 2" diameter pipe under the IPC. (IPC Table 1002.2). Under the IPC, up to 8' is permissible for a 2" dimeter pipe. (IPC Table 909.1).
286 Generally, a fixture trap cannot be below its weir. What fixture is the exception?
Incorrect. Please choose another answer.
A water closet has an integral trap. The vent is below it.
287 Which of the following directional changes of a trap arm will not need a cleanout?
Incorrect. Please choose another answer.
Under the IPC, a directional change of 45 degrees or less in horizontal drain piping does not need a cleanout. (IPC 708.1.4). Under the UPC, changes of direction under 90 degrees do not need a cleanout. (UPC 1002.3).
288 A plumber has to install a cleanout with a 3" trap arm on horizontal drain piping that exceeds a 135 degree change of direction.
Incorrect. Please choose another answer.
Under the IPC, a directional change of greater than 45 degrees requires the installation of a cleanout. (IPC 708.1.4). Under the UPC, with a 3" trap arm, a change of direction that exceeds 135 degrees requires a cleanout. (UPC 1002.3).
289 Which of the following fixtures does not require the weir of the trap to be below the vent opening?
Incorrect. Please choose another answer.
The trap of a floor mounted toilet is above the opening of the drain inlet of the sanitary tee which also serves as the vent origination.
290 Traps must be designed in such a way that they ________.
Incorrect. Please choose another answer.
Fixture traps must be made of materials that are resistant to corrosion and degradation. They have to be self-scouring and have a smooth and uniform interior. They are not to have movable parts or interior partitions, except where they are integral with the fixture. Traps must have a flow pattern that offers minimal resistance, so a uniform flow velocity can carry solids through the U-shaped area and into the fixture drain. (IPC 1002.2; UPC 1004.1 and 2).
291 Which of the following fixtures can discharge into a grease interceptor?
Incorrect. Please choose another answer.
A hand sink used in a kitchen can discharge into a grease waste line. (IPC 1003.3.1; UPC 1014.1).
292 Traps may have ______________________ approved slip joint fittings on the outlet side of the trap.
Incorrect. Please choose another answer.
Only one slip joint fitted is allowed on the outlet side of the trap. (IPC 1002.2; UPC 1003.2).
293 The size of a P-trap should be what diameter with respect to its trap arm?
Incorrect. Please choose another answer.
The P-trap should have the same diameter with respect to its trap arm. This is true of any size trap. (IPC 1002.5; UPC 1003.3).
294 Which of the following types of traps is permitted?
Incorrect. Please choose another answer.
Tubular traps are the only types permitted. All other traps are prohibited. (IPC 1002.3; UPC 1004.1).
295 The liquid seal of a fixture trap shall be at least _________________________.
Incorrect. Please choose another answer.
The minimum liquid trap seal is 2" and not more than 4" unless the plumbing authority determines a deeper seal is needed. (IPC 1002.4; UPC 1005.1).
296 Trap primers prevent traps from _________________________________.
Incorrect. Please choose another answer.
Trap primers may be engineered type or gravity fed off fixture drains but are intended to protect the trap seal by supplying the trap with water.
297 Floor drains subject to a reverse flow of sewage should be equipped with an approved _______.
Incorrect. Please choose another answer.
The backwater valve will prevent reverse flow of sewage by releasing back up through the riser of the cleanout.
298 Every building trap shall have each of the following, except:
Incorrect. Please choose another answer.
Not all building traps require the need for a trap primer.
299 The relief vent for a building trap need not be larger than ____________ of the connecting drain.
Incorrect. Please choose another answer.
The relief vent for a building trap only has to be as large as one-half of the diameter of the drain it connects. (IPC 906.2; UPC 1002.2).
300 Harmful or hazardous liquid wastes or grease should be drained into which of the following:
Incorrect. Please choose another answer.
Liquid wastes containing chemicals, grease, sand, etc. must go through interceptors or clarifiers before entering the sanitary sewer. (IPC 1003.3.1; UPC 1009.1)
301 All grease interceptors are required to have _________________.
Incorrect. Please choose another answer.
Not all grease interceptors are in traffic rate areas so do not require traffic rated lids, but do require a clean-out and relief vent. (IPC 1003.9; UPC 1009.4).
302 A ______________________________ may be required to be installed downstream of an interceptor/clarifier.
Incorrect. Please choose another answer.
Most municipalities take samples periodically to ensure the interceptor/clarifier is removing unwanted wastewater from entering the public sewer system.
303 Grease interceptors receive waste water from all of the following except:
Incorrect. Please choose another answer.
Fixtures that convey human wastes such as toilets, bidets and urinals are routed directly into the sewer system.

Water Supply and Distribution 

304 Which type of water is acceptable for uses such as drinking water, water for cooking and water for bathing?
Incorrect. Please choose another answer.
Only potable water is allowed to be used for drinking, cooking and bathing. Gray water and non-potable water can be used for flushing toilets and urinals. (IPC 602.2).
305 Which of the following is the proper term for piping that delivers potable water from a water source to a water-distribution system?
Incorrect. Please choose another answer.
The primary piping that delivers potable water to a water-distribution system is called either a water main or a water supply. This is the case whether the water is coming from a water well or a municipal water system. The minimum diameter for a water supply pipe is .75 inch. (IPC 603.1; UPC Table 610.4).
306 Assume that you are making both water and sewer connections to a building. In this process you will be installing both pipes from a location that is a terminal of a municipal system. The city has placed both a sewer lateral and a water service pipe on the private property where the building will be erected. You will be installing about 75 feet of piping for both the sewer and the water supply. The site contractor has provided one ditch that is to accommodate both pipes. Knowing what you do, which of the following is correct?
Incorrect. Please choose another answer.
Water services and sewers can share a common trench. (IPC 603.2; UPC 609.2; 720.1). They must be separated. This is normally done with a stable shelf, usually made of dirt, that provides a solid platform for the installation of the water service. When this is done the water service must be at least 12 inches above the sewer. If this is not practical, the two pipes can be installed on the same level as long as the two pipes are spaced a minimum of five feet apart and separated by undisturbed or compacted earth between the two. An exception is that a water service can be installed across a sewer if the water service piping is sleeved for at least five feet horizontally from the sewer pipe centerline on both sides of the crossing.
307 Assume that you are installing a reverse osmosis system. This system is located in a basement. The basement has a concrete floor and no plumbing fixtures in it. Is it true that the discharge from a reverse osmosis system is required to pass through an air gap or an air gap device before it is allowed to enter a sanitary drainage system?
Incorrect. Please choose another answer.
True - Any waste from a reverse osmosis system entering a sanitary drainage system must pass through an air gap or an air-gap device. (IPC 608.4; UPC 611.2). The function of a reverse osmosis system is converting non-potable water to potable water. Therefore, the waste is required to pass an air gap or air-gap device as it enters a sanitary drainage system.
308 A water service pipe should never run _______ a waste disposal system, such as a septic field.
Incorrect. Please choose another answer.
Water service piping is not allowed to be installed above, through or under a septic system or other waste disposal system. (IPC 603.2.1). This regulation is in place to prevent the potable water supply from being contaminated by waste should piping be compromised.
309 A water service is required to be protected from which of the following?
Incorrect. Please choose another answer.
A water service pipe must be protected from freezing by being buried below the local frost line. (IPC 305.4; UPC 609.1). The pipe is also required to be protected from flooding to prevent floating. When backfilling a ditch that contains a water service the backfill must be clean and free of sharp objects to protect the piping from damage that may be caused under the weight of backfill material and settlement movement.
310 At what point after entering a building is a water service pipe that is not third-party rated for water service piping, such as polyethylene piping, required to terminate and be changed to a piping that is suited for water distribution?
Incorrect. Please choose another answer.
Water service piping that is not rated for water distribution use must be changed over to water distribution pipe at, or before, the full-open valve that is required at the entrance of the water service pipe into the building. (IPC 605.3; UPC 606.2). A rule of thumb is that the water service pipe should never proceed more than five feet within a building before it is converted to water distribution piping.
311 All water heaters are required to be insulated with an energy-conserving, after-market blanket.
Incorrect. Please choose another answer.
False - Insulating blankets that can be bought and installed on water heaters to increase efficiency are not required by the plumbing code. However, all water heaters are required to be insulated. The amount of insulation required is determined based on heat loss from the unit within a one-hour period of time. Manufacturers insulate water heaters and the amount of insulation must be approved for use before the water heaters are installed. For a common-sense approach, it is safe to assume that water heaters available commercially for sale in a state are approved for installation in the state where they are being sold.
312 Flexible water connections are required to be _________.
Incorrect. Please choose another answer.
All flexible water connections are required to be accessible. (IPC 605.6; UPC 604.5). This means that they can be concealed in a cabinet or behind an access panel, but they must be accessible.
313 What is likely to cause banging in water pipes?
Incorrect. Please choose another answer.
Water hammer is the action known to cause piping to bang. One cause of a water hammer is long, straight runs of water piping. This can be avoided by installing offsets in long runs of water piping or by installing a water hammer arrester above water outlets. Added protection can be provided with air chambers that are installed above water outlets. Quick-closing valves, such as those used in washing machines and ballcocks, are known to cause water hammer. Air chambers or water hammer arresters are the best defense against a water hammer which is usually annoying and can be harmful to piping. When pipes are vibrating their joints can be weakened.
314 When water pressure being supplied to a single-family residence is in excess of ______ psi a pressure reducing valve is required to be installed to reduce the pressure to a level below the maximum allowable pressure.
Incorrect. Please choose another answer.
When the water pressure being supplied to a residence exceeds 80 psi a pressure reducing valve is required to reduce the pressure to a point at or below 80 psi. (IPC 604.8; UPC 1505.5; 1506.5). The valve must be installed near the point of entry for the water service pipe.
315 Assume that you are installing a potable water system. During this installation you plan to install a few double-check valves. In one instance, there is a need for backflow protection on a pipe where you will be installing a double-check valve. You could install a separate means of backflow protection. But, you can also use the double-check valve to serve a dual purpose which will include backflow protection if you equip it with an approved vent.
Incorrect. Please choose another answer.
True - The local water supplier determines the type of water backflow protection needed. Check with local code officials before choosing backflow protection. Double-check valves can be used to control backflow when they are equipped with an approved vent. You do not have to vent double-check valves in every installation. However, if the valve is being used as a form of backflow prevention the check valve is required to be vented.
316 Which of the following devices can be used to increase water pressure when the pressure from a water source is not adequate for the needs of a plumbing system?
Incorrect. Please choose another answer.
Booster pumps can be installed to increase water pressure as needed. (IPC 606.5; UPC 609.9). These pumps are installed as a part of the water distribution system. These pumps are capable of reducing volume to increase pressure without negative effects on the performance of plumbing fixtures.
317 Water storage tanks are a potential solution to plumbing systems that suffer from low water pressure. If these tanks are used, they must not be installed below __________.
Incorrect. Please choose another answer.
Water storage tanks are not allowed to be installed beneath soil or waste pipes. (IPC 606.5.8). The tanks must be protected from contamination. If the tank is of a gravity type it must be equipped with overflow provisions. Any water supply to a water storage tank is required to be automatically controlled. Inlet water is to enter through an air gap that is at least four inches above the overflow for the tank. Every tank must be capable of being drained and equipped with a drain valve to prevent unwanted draining.
318 You are installing a well system for a rural home. The pump for this house is a submersible pump. The pressure tank is located in the basement of the home. You have chosen a diaphragm-type pressure tank. By doing so, you have eliminated the need for installing a vacuum relief valve on the top of the tank. But there is still an important valve that must be installed on the supply pipe that feeds the tank or on the tank itself. This valve is a ________valve.
Incorrect. Please choose another answer.
A diaphragm-type pressure tank is required to be equipped with a relief valve that is rated for the requirements of the manufacturer's rating of the tank. (IPC 606.5.9; UPC 607.6). The valve is to be installed on either the incoming water supply or on the tank itself. Normally, this valve is installed on a tank tee that accepts the incoming water, connects to the tank and distributes water to the water distribution system. Discharge from a relief valve is not allowed to be piped into a sanitary drainage system. Normally there is no discharge tube required for a relief valve that is installed in conjunction with a pressure tank for potable water. However, the valve must be installed in such a way to discharge safely by gravity to a suitable disposal location, which could be a basement floor.
319 Irrigation systems are required to be protected from backflow. The most often installed device for backflow protection on irrigation systems, like lawn sprinklers, is vacuum breakers.
Incorrect. Please choose another answer.
True - Lawn sprinklers and irrigation systems must be installed with a form of backflow protection. (IPC 608.17.5; UPC 603.5.6). Vacuum breakers are normally used. Other types of approved backflow protection can be used, but it is recommended that vacuum breakers be installed on the systems.
320 Pipe hangers used for water distribution piping must be compatible with the type of pipe that is being supported. The supports are not allowed to __________.
Incorrect. Please choose another answer.
Pipe hangers cannot be used if they will create corrosive reactions. (IPC 308.3; UPC 313.2). As an example, you should use plastic, copper or some other type of hanger that is properly coated to prevent corrosion when supporting copper tubing and piping.
321 Galvanized steel pipe straps may be used to support copper pipes.
Incorrect. Please choose another answer.
False - Galvanized steel pipe straps are not an acceptable means of support for copper tubing or piping. The contact between the two dissimilar types of metal could result in corrosion.
322 What is the maximum span allowed for pipe supports on 3/4" copper tubing or piping that is used for water distribution and piped in a horizontal direction?
Incorrect. Please choose another answer.
Copper water tubing and piping (with diameters 1 ¼ " IPC or 1 ½" UPC or smaller) used for water distribution that is installed horizontally must be supported at intervals not to exceed six feet. (IPC Table 308.5; UPC Table 313.3). See the list below for all of the requirements for maximum support spacing for different types of water distribution piping in most jurisdictions:

• CPVC                       3 feet
• Copper                     6 feet
• PEX                         32 inches
• Brass                       10 feet
• Galvanized steel      12 feet
323 You are installing plumbing valves for showers in the gang showers of a locker room. These shower valves will mix hot and cold water to provide a flow from a shower head. What type of valve is required for this type of installation?
Incorrect. Please choose another answer.
Shower valves installed for use in gang showers are required to either be controlled by thermostatic means or a pressure-balance valve. (IPC 412.4; UPC 408.4). This requirement is in place to prevent the scalding of people using the showers. The requirement for this type of valve is being extended to other uses and some local jurisdictions require them even in residential dwellings. Even when the valves are not required, they are a good idea. The very young and the elderly are at high risk of being scalded when water temperature changes quickly. They simply cannot react quickly enough to turn off the water or to get out of the flow.
324 When barometric loops are used to prevent back siphonage they are required to extend to a point that is at least 35 feet high.
Incorrect. Please choose another answer.
True - Barometric loops are required to extend to a minimum height of 35 feet. (IPC 608.14.4). They can only be used as a vacuum breaker. How do they work? The loop works because it rises to a height that is high enough to prevent a vacuum suction.
325 The installation of every sill cock requires the use of ___________.
Incorrect. Please choose another answer.
All sill cocks installed are required to be equipped with cutoff valves. (IPC 606.2). They are also required to be fitted with a backflow preventer. These fixtures must be securely attached.
326 Gate valves and ball valves are rated as __________.
Incorrect. Please choose another answer.
Both gate valves and ball valves are known as full-open valves. (See UPC 606.4). When they are open, the pipe that they are installed on has a full flow since the valve does not restrict the flow diameter of a pipe when it is completely open. Stop and waste valves are an example of a valve that restricts flow.
327 Gate and ball valves depend on rubber washers to create a positive seal.
Incorrect. Please choose another answer.
False - Gate and ball valves do not depend on rubber washers to create a positive seal.
328 Which of the following locations do not require the installation of a full-open valve?
Incorrect. Please choose another answer.
Full-open valves are not required to be installed for every plumbing fixture. However, every fixture is required to have some type of cutoff valve. Ball valves and gate valves are required on all water heaters, between water services and water distribution piping, on the discharge piping of water supply tanks and similar locations.
329 A water well that is 60 feet from a building sewer violates the code due to the probability of contamination.
Incorrect. Please choose another answer.
False - The codes regulate how far a water well must be from a sewer to prevent contamination. Under the IPC, it's 10 feet and under the UPC, it's 50 feet. (IPC Table 608.18; UPC 721.1).
330 Which of the following types of valves can be used to meet the requirements of installing a cutoff valve on every fixture?
Incorrect. Please choose another answer.
All plumbing fixtures must be equipped with an approved cutoff valve. These valves can include the following:

• Supply stops
• Stop valves
• Gate valves
• Ball valves
331 Backflow preventers installed on potable water systems are required to be _________.
Incorrect. Please choose another answer.
Backflow preventers installed on potable water systems are required to be inspected periodically and the devices must be accessible. (IPC 312.11 and 608.15; UPC 603.4). Any relief port on a backflow preventer is required to have a discharge tube that is not trapped, does not enter the sanitary drainage system and that is piped to a safe and suitable disposal location.
 
A gentleman farm has a water line for irrigation from an alternate water source using nonpotable water.
332 What color, if any, should be the piping?
Incorrect. Please choose another answer.
A nonpotable water line must be in purple under the UPC and if the nonpotable water line is from an alternate water source under the UPC. (IPC 608.9.2; UPC 601.3.3).
333 Does the nonpotable water piping need to be stamped with any warning?
Incorrect. Please choose another answer.
Nonpotable distribution piping needs to be embossed, stamped or marked "CAUTION: NONPOTABLE WATER, DO NOT DRINK." (IPC 608.9.2; UPC 601.3.3).
334 Water heaters, hose bibs and sill cocks are normally protected from backflow with ________.
Incorrect. Please choose another answer.
Vacuum breakers are normally used to protect water heaters, sill cocks and hose bibs from backflow dangers.
335 Which of the following types of fixtures are required to have their water sources protected by an air gap?
Incorrect. Please choose another answer.
Potable water delivery systems for lavatories, bathtubs, drinking fountains, sinks, showers and laundry tubs are required to be protected from backflow with an air gap. (IPC Table 608.16.1; UPC 409.5 and Table 603.3.1). This is why the flood-level rim of these fixtures is well below the outlet of the faucet or valve delivering potable water to the fixture. Many plumbers don't think of this as an air gap protection, but it is.
336 Which of the following types of backflow prevention is the most dependable?
Incorrect. Please choose another answer.
An air gap is the most effective form of backflow protection. This is because when an air gap is used, water never comes into contact with a potable water system. Therefore, it is a positive means of backflow protection.
337 Let's assume that you are installing plumbing in a food-service area. One of the fixtures that you will be installing is a carbonator. This is for a carbonated beverage dispenser. You must install a potable water supply pipe for the fixture. What type of backflow prevention are you likely to use if the carbonator does not have an internal backflow preventer?
Incorrect. Please choose another answer.
If the carbonator is not equipped with an approved internal backflow preventer you must install a vented backflow preventer with two independent check valves that is not affected by carbon dioxide gas to protect the carbonator. Most carbonators will come equipped with an approved, manufacturer-installed backflow prevention device. If they do not, many water suppliers dictate the backflow protection needed.
338 Connections between potable water supply systems and automatic fire sprinkling systems are to be made with a check valve. If the potable water supply is connected to a non-potable water connection, the connection should be protected by _________.
Incorrect. Please choose another answer.
Reduced-pressure-principal backflow preventers are required for connections between potable and non-potable water sources. (IPC 608.16.2; 608.17.4; UPC 602.3; 603.5.14.2; 603.3.7). This is often the case when potable water is used in conjunction with automatic fire-suppression systems, such as sprinkler systems. Other types of backflow protection are available for use when fire-control systems are pressurized.
339 You are installing piping for the hot water side of a water distribution system. The desired temperature of the hot water must be maintained for a certain amount of distance. How far from the fixture being served must the hot water temperature be maintained?
Incorrect. Please choose another answer.
Pipe that delivers hot water is required to maintain the desired water temperature for a minimum point of at least 50 feet from the fixture being served. (IPC 607.2). If this is not feasible with a typical installation there should be a recirculation pump installed. This pump will keep the hot water moving to maintain the desired temperature at the prescribed distance required.
340 You are to install a private water system. Is it true that you can connect it without any approval?
Incorrect. Please choose another answer.
False - The agency having jurisdiction must approve the final connection. (IPC 602.3.3; UPC 602.4).
341 Hot water supplied to plumbing fixtures that utilize two handles to be operated must be installed _______.
Incorrect. Please choose another answer.
Hot water is to be supplied to the left-hand side of plumbing faucets and mixing valves. (IPC 607.4; UPC 417.5). One exception is the use of single-handle valves. When a single-handled faucet is used, the hot water should be piped to the left side and may rely on distinct markings on the face of the faucet to define the proper position to receive hot water.
342 Which of the following residential uses do not require hot water to be available to the fixture?
Incorrect. Please choose another answer.
Hot water is required to be provided to fixtures that are used for cooking, bathing, washing, cleaning, laundry and building maintenance. It is not required for other fixtures.
343 Systems that are under continuous pressure and that contain chemical additives or antifreeze are required to be equipped with approved devices to prevent contamination in potable water systems.
Incorrect. Please choose another answer.
True - Potable water systems must be protected from contamination. (IPC 608.17.4.1; UPC 603.5.14.2). This includes fitting systems that are under continuous pressure and that contain chemical additives or antifreeze with adequate backflow protection.
344 Assuming that you are working with a common water heater. What is the maximum working pressure for the fixture?
Incorrect. Please choose another answer.
The pressure setting for a common water heater is not to exceed the tank and water heater manufacturer's rated working pressure. (IPC 504.5; UPC 504.4). Under some codes, like the IPC, the pressure setting cannot exceed 150 degrees in any case. Normally the maximum working pressure for a water heater is 125 psi. You can determine the maximum working pressure by checking an identification marking on the water heater. The maximum working pressure is to be indelibly stamped onto the metal of the fixture or otherwise permanently attached.
345 Some plumbing systems do not have municipal water supplies. When this is the case, private water sources are used, which is generally some form of water well. Which of the following types of water wells are allowed to provide a private water supply?
Incorrect. Please choose another answer.
Private water sources can take the form of any of the following:

• Dug wells
• Driven wells
• Bored wells
• Drilled wells
• Cisterns
• Springs
• Streams
• Reservoirs
When any of these sources are used for a private water supply, the water supplied must meet minimum standards for the water supply to be potable water. This may require treatment or disinfection prior to being provided to a water distribution system.
346 Which of the following distances is acceptable when locating a well in relation to an underground sewage disposal field?
Incorrect. Please choose another answer.
Private water sources, such as a well, must be separated 50 feet from an underground sewage disposal field to provide water for potable-water usage. (IPC Table 608.18.1; UPC Appendix H Table H101.8). All private water sources should be located above and upstream from any possible contaminating source, which could include a septic field.
347 PEX tubing cannot be installed within ________ inches of a piping connection to a water heater.
Incorrect. Please choose another answer.
Pex tubing used to make connections with water heaters must not be installed closer than 18 inches to the connection point. (UPC 604.13). This means that some other type of piping, such as copper tubing, should be installed from the connection points on the water heater and extend a minimum of 18 inches before they are converted to PEX tubing.
348 Pipe used to conduct the blow-off from relief valves on water heaters must be able to sustain temperatures of up to 210 degrees F.
Incorrect. Please choose another answer.
True - All piping used as a conduit for the blow-off from relief valves on water heaters are required to sustain temperatures of up to 210 degrees F. (IPC 504.5; UPC 608.5).
349 Vacuum breakers for hose connections in healthcare and laboratory areas are required to be installed at least ______ feet above the finished floor level.
Incorrect. Please choose another answer.
All vacuum breakers for hose connections in healthcare and laboratory areas are required to be installed a minimum of six feet above the finished floor. (IPC 608.3.1; UPC 603.5.15).
350 When installing a double check valve should a drain be provided?
Incorrect. Please choose another answer.
Double check valves consist of two check valves and do not have a relief valve, so no drain is required.
351 Hot water supplied to plumbing fixtures that utilize two handles to be operated must be installed _______.
Incorrect. Please choose another answer.
Hot water is to be supplied to the left-hand side of plumbing faucets and mixing valves. (IPC 607.4; UPC 417.5). One exception is the use of single-handle valves. When a single-handled faucet is used, the hot water should be piped to the left side and may rely on distinct markings on the face of the faucet to define the proper position to receive hot water.
352 Which of the following residential uses do not require hot water to be available to the fixture?
Incorrect. Please choose another answer.
Hot water is required to be provided to fixtures that are used for cooking, bathing, washing, cleaning, laundry and building maintenance. It is not required for other fixtures.
353 Why should you not install joint compound on the inside threads of a pipe?
Incorrect. Please choose another answer.
All threads shall confirm to ASME standards and approved threads lubricant or tape shall be applied on the male threads only.  (IPC 705.2.3; UPC 705.4.2). When installing pipe joint compound to the female threads of a fitting it would allow contamination of the liquid inside the piping. The pipe joint compound when placed on the inside or the female threads will cause a shoulder buildup of pipe compound on the inside of the female threads.
354 Assuming that you are working with a common water heater. What is the maximum working pressure for the fixture?
Incorrect. Please choose another answer.
The pressure setting for a common water heater is not to exceed the tank and water heater manufacturer's rated working pressure. (IPC 504.5; UPC 504.4). Under some codes, like the IPC, the pressure setting cannot exceed 150 degrees in any case. Normally the maximum working pressure for a water heater is 125 psi. You can determine the maximum working pressure by checking an identification marking on the water heater. The maximum working pressure is to be indelibly stamped onto the metal of the fixture or otherwise permanently attached.
355 Some plumbing systems do not have municipal water supplies. When this is the case, private water sources are used, which is generally some form of water well. Which of the following types of water wells are allowed to provide a private water supply?
Incorrect. Please choose another answer.
Private water sources can take the form of any of the following:
• Dug wells
• Driven wells
• Bored wells
• Drilled wells
• Cisterns
• Springs
• Streams
• Reservoirs
When any of these sources are used for a private water supply, the water supplied must meet minimum standards for the water supply to be potable water. This may require treatment or disinfection prior to being provided to a water distribution system.
356 Which of the following distances is acceptable when locating a well in relation to an underground sewage disposal field?
Incorrect. Please choose another answer.
Private water sources, such as a well, must be separated 50 feet from an underground sewage disposal field to provide water for potable-water usage. (IPC Table 608.18.1; UPC Table 721.1). All private water sources should be located above and upstream from any possible contaminating source, which could include a septic field.
357 PEX tubing cannot be installed within ________ inches of a piping connection to a water heater.
Incorrect. Please choose another answer.
Pex tubing used to make connections with water heaters must not be installed closer than 18 inches to the connection point. (UPC 604.13). This means that some other type of piping, such as copper tubing, should be installed from the connection points on the water heater and extend a minimum of 18 inches before they are converted to PEX tubing.
358 Pipe used to conduct the blow-off from relief valves on water heaters must be able to sustain temperatures of up to 210 degrees F.
Incorrect. Please choose another answer.
True - All piping used as a conduit for the blow-off from relief valves on water heaters are required to sustain temperatures of up to 210 degrees F. (IPC 504.5; UPC 608.5).
359 Vacuum breakers for hose connections in healthcare and laboratory areas are required to be installed at least ______ feet above the finished floor level.
Incorrect. Please choose another answer.
All vacuum breakers for hose connections in healthcare and laboratory areas are required to be installed a minimum of six feet above the finished floor. (IPC 608.3.1; UPC 603.5.15).
360 When installing a double check valve should a drain be provided?
Incorrect. Please choose another answer.
Double check valves consist of two check valves and do not have a relief valve, so no drain is required.
361 Which of the following is water that is safe for human consumption under public health standards?
Incorrect. Please choose another answer.
Potable water is water free from impurities present in amounts sufficient to cause disease or harmful conditions.
362 A bathtub mixing valve is required to flow at the rate of _____ gallons per minute.
Incorrect. Please choose another answer.
The required water design capacity of bathtub mixing valves is 4 gallons per minute. (IPC Table 604.3; UPC Table 610.3).
363 The maximum flow rate for a water closet is _______ gallons per flushing cycle.
Incorrect. Please choose another answer.
The maximum flow rate for a water closet is 1.6 gallons per flushing cycle, as required by federal standards. (IPC 604.4; UPC 411.2.2).
364 When installing a flush-o-meter on a water closet, what must be provided to prevent cross connection from occurring?
Incorrect. Please choose another answer.
Atmospheric vacuum breakers are connected as part of the flush-o-meter assembly to provide an air gap from the drainage pipe to the water supply. (IPC 415.2; UPC 603.5.1). This connection is in the lowest part of the flush-o-meter assembly.
365 Backflow preventers must not be located in areas subject to _________.
Incorrect. Please choose another answer.
All backflow prevention devices must be protected from freezing, flooding and electrical grounding. They should never be installed in an electrical panel room or at any source that could lead to electrical grounding. Underground installation is not permitted, because the operation or leakage cannot be detected.
366 What is required to be installed on all water supply fixtures, except residential bathtubs and showers?
Incorrect. Please choose another answer.
The code requires shutoffs on all fixtures; however, bathtubs and showers have concealed piping that may be difficult to access. (IPC 606.2). In the cause of an emergency, the water supply can be turned off at each individual fixture while the remainder of the water piping to the house can remain on.
367 What type of water does a bidet use?
Incorrect. Please choose another answer.
A bidet uses both hot and cold water.
368 A vacuum breaker is suitable backflow protection for:
Incorrect. Please choose another answer.
A vacuum break will allow air to be admitted into the plumbing system if siphonage occurs, breaking the siphon.
 

Sanitary Drainage Systems 

369 What is the typical amount of grade required per liner foot on a household drainage pipe?
Incorrect. Please choose another answer.
The amount of grade, also referred to as pitch or fall, for a drain pipe is determined by the size of the drain pipe. Master plumbers and other design professional establish these elements of a plumbing system based on the minimum standards required by local code requirements. As a general rule-of thumb, the proper amount of grade for a drain up to 4-inches in diameter is .25 inch per liner foot. (IPC 704.1; UPC 708.1).
370 How many fixture-units will a fixture that requires a 1 1/4-inch trap be rated for?
Incorrect. Please choose another answer.
A fixture that requires a 1 1/4-inch trap will have a fixture-unit rating of one fixture unit. Tables in the plumbing code allow plumbers in the field to quickly determine this type of conversion and evaluation. (IPC Table 709.1; UPC Table 702.1(1)).
371 Horizontal branch drains may ________.
Incorrect. Please choose another answer.
Horizontal branches are drain pipes that branch off of a plumbing stack. They normally run in a horizontal position. However, they can turn to a vertical rise and still be considered horizontal branches.
372 Drains with a diameter of 4 or 5 inches can be installed with a minimum grade of ________.
Incorrect. Please choose another answer.
Pipes with diameters of between three and six inches (IPC) or 4 inches or larger (UPC) are allowed to be installed with .125 inch of grade. Even though this grade is allowable, most plumbers install pipes up to four inches in diameter with a grade of .25. When space is at a premium the smaller amount of grade can be used. (IPC Table 704.1; UPC 708.1)
373 PVC Schedule 40 may be used for underground drain waste piping and fittings.
Incorrect. Please choose another answer.
True - PVC Schedule 40 may be used for underground sanitary drainage. (IPC Table 702.2; UPC Table 701.2).
374 Assume that you are installing drain pipes below grade. It is your job to make joints to connect sections of piping. Which of the following types of connections are you allowed to use?
Incorrect. Please choose another answer.
Underground piping can be joined in a number of ways, depending on the type of pipe being installed. When mechanical joints are used, they are required to have elastomeric seals. Plastic piping is normally connected with solvent-weld joints, but they can be joined by other means, such as rubber couplings that are held in place with stainless-steel clamps. Cast-iron pipe that is of the bell-and-spigot type can be caulked with okum and lead. In reality, caulked joints are rarely used in modern plumbing installations. Rubber insert connectors are far more common for bell-and-spigot cast-iron pipe. The key is to match a suitable connector to the type of pipe being installed. (IPC 705; UPC 705).
375 You are roughing in drainage piping for a future fixture in a part of a building that is partially occupied. Which of the following is required in a stub-out for a future fixture?
Incorrect. Please choose another answer.
A stub-out for drainage piping for future fixtures must terminate with a cap or plug when it will be located in a partially occupied building. (IPC 704.4; UPC 402.11). The requirement prevents foul odors from coming into the building.
376 During the course of your plumbing rough-in you are installing several horizontal branches. These drains are connected to stacks. The connections must be made downstream of the stack. But, how far downstream from the stack is the closest location that a connection can be made?
Incorrect. Please choose another answer.
Backwash into horizontal connections within a zone where hydraulic jump can occur could cause the pipe connections to be closed up. It is required then to construct the fittings in such a way that discharge from one inlet does not enter another. (UPC 706.2). In furtherance of this, the IPC requires that horizontal branches that connect to the bases of stacks be no closer than 10 pipe diameters from the stack. All connections are required to be made on the downstream side of a stack. (IPC 704.3)
377 Vents for vertical offsets are not required where the stack and its offset are _____ as a building drain.
Incorrect. Please choose another answer.
Vents for vertical offsets are not required where a stack and its offset is sized as a building drain. (IPC 710.1.2). It is normal for vent pipes to have a diameter that is smaller than the drain that they serve. However, if the vent has the same diameter of the drain, it is serving it is exempt from certain vent regulations. In this case, that means that vents with diameters equal to the drains being served are exempt from the venting of vertical offsets.
378 Lead bends are required to have a minimum wall thickness of .5 inch.
Incorrect. Please choose another answer.
False - A lead bend is required to have a minimum wall thickness of 1/8". (IPC 702.7; UPC 701.5). This minimum thickness requirement also applies to the wall thickness of lead traps. Neither of these items are common in modern plumbing, but the code does still regulate the devices and you may be tested on it.
379 A vent is required for a stack that has a horizontal offset that is located more than ______ branch intervals below the top of the stack.
Incorrect. Please choose another answer.
A vent is required for a stack that has a horizontal offset that is located more than four branch intervals below the top of the stack. (IPC 711.2).
380 Assume that you are installing drainage piping for a restaurant. Much of the piping will be in and around the food service area, and this is the area that you are planning an installation for. The routing of the drainage piping is important. As a journeyman plumber you must know where you can and cannot install the piping. In this scenario we will assume that the drainage piping is to be installed as exposed piping. There are regulations pertaining to such an installation. Which of the following locations are not allowed to have exposed piping installed above them in this type of situation?
Incorrect. Please choose another answer.
When drainage piping is installed exposed in a food service area it must not be installed above any working areas, storage areas or eating surfaces. Since the piping is exposed, it could leak onto these areas and contaminate them. The rule applies only to exposed piping. (UPC 317.1).
381 Assume that you are required to join dissimilar types of pipe in a plumbing system. When this is done, what type of joint is acceptable?
Incorrect. Please choose another answer.
It is common to use mechanical joints to connect pipes of different types of materials. (IPC 705.16; UPC 705.10). Both compression joints and mechanical-sealing devices are approved for use. Mechanical joints are sometimes restricted on drain pipes installed above grade. However, if the piping is accessible, mechanical joints for above-ground drains are normally acceptable. All mechanical joints are required to have approved elastomeric seals.
382 Drainage systems sometimes incorporate the use of a waste pump. When this is the case certain requirements must be met to remain in compliance with the plumbing code. Choose from the list below which device, or devices, are required to be installed on a waste pump?
Incorrect. Please choose another answer.
Drainage pumps are required to be equipped with both check valves and full-open valves. (IPC 712.2; UPC 710.3). Both devices must be accessible. The full-open valve shall be installed on the discharge side of the check valve. This allows the pump and check valve to be removed without the waste in the drain pipe running back to the point of connection. Full-open valves should be installed above the cover of a sewage sump that contains a pump. When this is not possible, the valve is to be installed outside of the sewage sump in an access pit. There can be limited exceptions to this ruling. For example, a one- or two-family dwelling application may not require a full-open valve. Even if it is not required, it should be installed for servicing purposes.
383 You are installing some underground piping. You must make sure that as you are installing the pipe sections that will be joined that all of the drainage piping will be protected from effects of flooding.
Incorrect. Please choose another answer.
True - Drainage piping is to be installed with the risk of flooding in mind. (IPC 309; UPC 312.4). If an installation is being made in an area that is prone to flooding the piping must be protected. Flooding must not be allowed to float drainage piping. It is also necessary for drainage system installations to be installed so that flood water will not enter the sanitary drainage system.
384 Understanding which fittings are approved for changes in direction is critical to making a proper plumbing installation. Envision a situation where you are installing horizontal drain piping above ground. Which of the following fittings are suitable for a change of direction from a horizontal position to another horizontal position?
Incorrect. Please choose another answer.
The fittings allowed to change direction with horizontal piping include the following:

• Sixteenth bend
• Wye
• Eighth bend
• Sixth bend
• Long-sweep fittings
• Combination fittings
• Wye with eighth bend
The reason these fittings are allowed is that they have a subtle change in direction. An abrupt change in direction could result in drain blockage. (IPC Table 706.3; UPC 706.3).
385 Which of the following fittings are approved for changes in piping direction from horizontal-to-vertical?
Incorrect. Please choose another answer.
All of the listed fittings are allowed for changes in piping from a horizontal to vertical position. (IPC Table 706.3; UPC 706.2). Additionally, any fitting allowed for changes in horizontal-to-horizontal direction are also approved for use when turning to a vertical position.
386 If you are changing direction from a vertical pipe to a horizontal pipe there are several fittings which are acceptable. Some short-sweep fittings are allowed for this purpose. The determining factor on which short-sweep fittings may be used is based on the pipe-diameter of the piping being installed. Which of the following pipe sizes are allowed to use short-sweep fittings to turn a drain from a vertical position to a horizontal position?
Incorrect. Please choose another answer.
In order for short-sweep fittings to be used in changing direction from a vertical drain to a horizontal drain the minimum diameter of the drain must be no less than three inches. Piping with a smaller diameter is not allowed to be turned from vertical to horizontal with short-sweep fittings. (IPC Table 706.3; UPC 706.1).
387 Assume that you are installing two blowback water closets. The fixtures are to be installed back-to-back on a common wall. Which of the following fittings is allowed for this type of installation?
Incorrect. Please choose another answer.
Double tee-wye or combination fittings are approved for use to collect the waste from two blowback toilets that are installed back-to-back on common walls. (IPC 706.3; UPC 704.2). Sanitary tees are not allowed for this type of connection. Why? The long sweep of a tee-wye directs waste down, into the drainage piping. Since sanitary tees do not have the long sweep there is risk that the waste from one fixture will transfer to the base of the other fixture.
388 Assume that you are installing a 3" DWV system that is going to consist mostly of plastic drain piping. However, there is one area of the job that has been specified to receive DWV copper piping. When these two types of piping are installed horizontally what is the maximum allowable distance between the hangers that support the piping? The plastic piping must be supported at intervals not to exceed ______ feet and the DWV copper piping is required to have support at intervals not to exceed ________.
Incorrect. Please choose another answer.
The maximum allowable distances for support hangers is determined by the type and size of piping being installed. When 2" or 3" piping is being installed horizontally the maximum allowable distances between support hangers for different types of piping are generally as follows:
 
Type of Piping MaterialMaximum Span Between Pipe Supports
ABS4 feet
PVC4 feet
Cast Iron5 feet
Galvanized Steel12 feet
DWV Copper10-12 feet

(IPC Table 308.5; UPC Table 313.3)
389 A drainage pipe has a diameter of six inches and uses flexible couplings at changes in direction. The piping must be supported at the point of the flexible connection.
Incorrect. Please choose another answer.
True - Flexible couplings on pipes with a diameter in excess of 4-inches that create a change in direction are required to be supported to prevent any loosening pertaining to the coupling. (IPC 308.7.1; UPC 313.4).
390 What is the minimum allowable diameter for a drain pipe that is installed underground?
Incorrect. Please choose another answer.
It is common for plumbing codes to require any pipe installed below grade to have a minimum diameter of two inches. However, under the IPC and UPC, the drain pipe size is based on fixture units. (IPC Table 710.1; UPC 717.1).
391 You are installing cast iron pipe. What is the maximum support distance allowed by code for cast iron piping that is installed vertically?
Incorrect. Please choose another answer.
The maximum distance allowable between supports for vertical piping are different from some of those for horizontal piping. You can see the allowable distances between supports below:
 
Type of PipeIPCUPC
ABS10 feetevery floor and mid story
PVC10 feetevery floor and mid story
Cast Iron15 feet15 feet
DMV Copper10 feet10 feet
Galvanized Steel15 feetDetermined by local authority

(IPC Table 308.5; UPC Table 313.3)
392 Which of the following is the correct answer for a drainage pipe that is being installed to empty into a waste-disposal site?
Incorrect. Please choose another answer.
Drainage pipes installed to empty into a waste-disposal site are not allowed to be reduced in size. (IPC 704.2; UPC 717.1).
393 A drainage pipe that is being installed to empty into a waste-disposal site may be increased in size.
Incorrect. Please choose another answer.
True - Drainage pipes installed to empty into a waste-disposal site are allowed to be increased in size.
394 Which of the following plastic pipes can be threaded and remain in compliance with the plumbing code?
Incorrect. Please choose another answer.
Plastic piping must be rated as Schedule 80 or greater. (IPC 705.2.3; UPC 705.1.3). Normal DWV plastic piping is Schedule 40. Threading of Schedule 40 pipe is not allowed. When plastic pipe is threaded, the threading must be done with dies designed for threading plastic pipe. An approved thread lubricant or tape is required to be applied to male threads only when connected threaded joints of plastic piping.
395 Caulked lead joints used to connect cast iron pipe are required to be painted either red or orange to provide a visual warning of the pipe's presence.
Incorrect. Please choose another answer.
False - Caulked lead joints are not allowed to be painted, varnished or otherwise coated until a joint is tested and approved by a code officer. (IPC 705.3.1; UPC 705.2.1). There is no code requirement that calls for caulked joints to be painted.
396 Your boss has dispatched you to a fast-food restaurant to repair a hand sink in the kitchen area. You have detected the waste pipe over the food preparation table. What modifications, if any, will be needed to satisfy the plumbing code?
Incorrect. Please choose another answer.
Never should waste piping be located above any working, storage, food prep or eating surfaces in food service establishments. (UPC 317.1). Piping will need to be relocated away from any food service areas.
397 An offset is defined as____________________.
Incorrect. Please choose another answer.
An offset is a combination of approved fittings that make two changes in direction bringing one section of the pipe out of line but into a line parallel with the other section to keep the piping headed in the same direction.
398 You are installing a 6 inch storm line under a concrete floor of a nursing home. You will need to provide cleanouts of sufficient size and the proper distance apart from each cleanout. How will you install this system?
Incorrect. Please choose another answer.
A 4 inch floor cleanout is considered as a full-size cleanout and can be used on a 6 inch drain pipe. (IPC 708.15 - 4 inch and larger pipes need at least 4 inch cleanout; UPC Table 707.1 - 4 inch and larger pipes needing at least a 3 ½ inch cleanout). Cleanouts must be provided every 100 feet to allow for proper cleaning. (IPC 708.1.1; UPC 707.4).
399 You have installed a sanitary sewer in the floor of a warehouse; a floor cleanout is required at the end of a run. The waste piping size is 6 inches. Which of the following clearances meet the code for proper cleaning?
Incorrect. Please choose another answer.
Under the IPC, 6 inch drain pipe or less need at least 18 inches in clearance. (IPC 708.1.10). Under the UPC, 6 inch drain pipe needs at least 24 inches of clearance. (UPC 707.9). This will give you sufficient clearance to operate an electric sewer cleaning machine.
400 If you install a pipe with more than a ¼ of an inch per foot fall, what affect will this have on the waste system?
Incorrect. Please choose another answer.
If the piping system has too much pitch or fall, water will travel faster than the waste causing the waste to stop flowing and potentially block the sewer line.
401 You have been sent to inspect the plumbing system in a single-family home. All the plumbing appears to be to code standards, but on further inspection you notice a 3 inch test tee cleanout on a 2 1/2 inch stack. Does this installation meet code requirements?
Incorrect. Please choose another answer.
On a 2 1/2 inch stack a 2 1/2 inch cleanout is required. (IPC 708.1.5; UPC Table 707.1).
402 What will result when a 4 inch pipe is reduced in size in the direction of the flow?
Incorrect. Please choose another answer.
At the reduction point, because of the direction of flow, waste can build up which will result in ping system blockage.
403 The plumbing code allows for a cleanout equivalent for the sanitary sewer system. Which of the following is a cleanout equivalent?
Incorrect. Please choose another answer.
Any fixture that has an integral trap is a cleanout equivalent. (IPC 708.1.6). An example is a water closet. A water closet can be removed to allow for proper cleaning of the sanitary sewer line.
404 You have instructed a laborer to dig a pit hole for a residential sump pump. Which of the following size holes are acceptable for the dimensions (height and diameter) of a sump pit?
Incorrect. Please choose another answer.
A residential sump pit must be at least 24" height x 18" diameter (IPC) and 18" height x 15" diameter (UPC). (IPC 712.3.2; UPC 1101.6.2). The hole to install the sump pit will need to be dug deeper and wider than the measurements of the sump pump.
405 Can steam pipes connect to a plumbing drainage system with PVC pipes to carry steam water at 180 degrees?
Incorrect. Please choose another answer.
Steam pipes cannot connect to a plumbing system with a water temperature above 140 degrees. (IPC 702.5; UPC 810.1). The IPC allows a plumbing system to handle wastewater with temperatures above 140 degrees if special piping is used that is rated for the temperature of the water to be handled.
406 A drainage system into a sewer should have a _________ for purposes of cleaning.
Incorrect. Please choose another answer.
A drainage system should have an access opening point for the purpose of removing a clog or other obstruction in the drain line. A test tee cleanout has a screw cap that can be removed to gain access into the drain pipe. A removable on hub clamp or removal fitting can be disassembled and also used as an access point for the cleaning of the line.
407 A journeyman plumber has encountered different diameter pipe joints. He calls his master plumber for instructions. He wants to know if he can use rolling o-rings. The master plumber should inform him that:
Incorrect. Please choose another answer.
In a sanitary drainage system, joints between diameter pipes made with elastomeric rolling o-rings are prohibited. (IPC 707.1). Elastomeric o-rings may be used on stainless steel drainage systems, press-connect fittings and push fit fittings of copper or copper alloy pipe. (IPC 705.20; UPC 605.1.3.2 and 605.1.3.3).
408 The lowest part of the drainage system inside a building that receives the discharge from soil, waste and other drains is called the ________.
Incorrect. Please choose another answer.
The building drain is the lowest part of the plumbing system that is inside the building. The building sewer is located outside the building. Although part of the drainage system, the building drain and building sewer are two different parts of the drainage system.
409 What is the smallest size p-trap that can be used on any unlisted fixture?
Incorrect. Please choose another answer.
The minimum trap size for unlisted fixtures is the size of the drainage outlet but not less than 1 ¼ inches. (IPC 709.2; UPC 702.1; UPC Table 702.1).
410 What part of the plumbing system is installed just prior to the installation of fixtures?
Incorrect. Please choose another answer.
This includes drainage, water supply, vent piping and the necessary fixture supports and any fixtures that are built into the structure. When we speak of underground piping or wall rough piping by itself it does not constitute the plumbing rough in system.
411 What will result when a 4 inch pipe is reduced in size in the direction of the flow?
Incorrect. Please choose another answer.
At the reduction point, because of the direction of flow, waste can build up which will result in ping system blockage.
412 ________ always involve at least two changes in direction to keep the piping heading in the same direction.
Incorrect. Please choose another answer.
A combination of approved bends that make two changes in direction bring one section of the pipe out of line but into a line parallel with the other section.
413 You are sizing gravity drainage piping. A 2'' pipe needs to slope a minimum of ______ an inch per foot fall.
Incorrect. Please choose another answer.
A ¼ of an inch per foot fall is the requirement for sizing 2" gravity drainage piping. (IPC Table 704.1; UPC 718.1).
414 Which of the following is prohibited from installation in compacted areas such as driveways and parking lots?
Incorrect. Please choose another answer.
Private sewage disposal systems must not be installed in compacted areas. (IPSDC 406.1; UPC Appendix H 601.9). Such areas include driveways and parking lots. It is not wise to install water pipes under compacted areas when it can be avoided, but this action is not prohibited.
415 Before a seepage trench or bed is constructed the intended location for the system is required to be subject to soil testing by an approved authority.
Incorrect. Please choose another answer.
True - Soil tests are required to establish perk rates for soils that will be used to house seepage trenches and beds. (IPSDC 404; UPC 1504.3, Appendix H 401). The testing is usually done by an engineer or an authorized public official. Local regulations vary on what designation is required for an approved perk test. Check with your local code officer to determine what agency or professional is required to conduct the testing.
416 What is the minimum width required for a seepage trench for a septic system drain field?
Incorrect. Please choose another answer.
The minimum width of a seepage trench is one foot. (IPSDC 201; UPC Appendix H 301). Seepage trenches are not allowed to have a length in excess of 100 feet. You should also know that the maximum width of a seepage trench is five feet. All trenches must be spaced a minimum of two feet apart.
417 Which of the following comply with the code on the diameter of a seepage pit?
Incorrect. Please choose another answer.
The minimum diameter for a seepage pit is 4 feet under the UPC and 5 feet under the IPSDC. (IPSDC 605.3; UPC Appendix H 701.3).
418 The bottom of a seepage trench or bed excavation for a septic system drain field shall:
Incorrect. Please choose another answer.
The bottom of seepage trenches or beds shall be level. (IPSDC 1403.1.4; UPC Appendix H 601.9).
419 What is the maximum size of aggregate that is used when backfilling a seepage trench/filter in a septic system drain field?
Incorrect. Please choose another answer.
Seepage trenches require a maximum size of aggregate that ranges in size from .5 to 2.5 inches in diameter. (IPSCD 605.5; UPC Appendix H 601.2). This material is to be installed below any distribution piping elevation. There is also a requirement that a minimum of 2 ½" of aggregate be installed over the top of distribution piping.
420 You are working on a seepage trench. Your supervising plumber tells you to scratch up the bottom of the trench and loosen the dirt up. It wouldn't be the first time that this plumber has made apprentice plumbers do unnecessary work. So is it true that the bottom of a seepage trench or bed is required to be scarified.
Incorrect. Please choose another answer.
True - It is true that the bottom of a seepage trench or bed is required to be scarified. (IPSDC 605.4; UPC Appendix H 601.2). This means, in simple terms, scratching up the ground to loosen it for absorption. Once this is done all loose material in the bottom of the trench or bed is to be removed. The end result is an earth surface that is receptive to absorbing liquids.
421 The preferred minimum amount of soil cover over the top of a pipe in a seepage trench in a septic drain field is 12 inches.
Incorrect. Please choose another answer.
False - The minimum amount of soil cover over the top of a pipe in a seepage trench in a septic drain field is eighteen inches. (IPSDC 605.5; UPC Appendix Table H 601.9). Do not confuse this with the minimum cover requirement of general plumbing pipes that are buried, which is 12 inches.
422 What is the minimum pipe diameter allowed for distribution piping in a seepage trench or bed in a septic system drain field?
Incorrect. Please choose another answer.
The minimum diameter allowed for distribution piping in a seepage trench or bed in a septic system drain field is four inches. (IPSDC 605.6; UPC Appendix H 501.6).

Special Piping and Storage Systems 

423 Which of the following are covered by the plumbing code requirements?
Incorrect. Please choose another answer.
The plumbing code governs both medical gas systems and non-medical oxygen systems. The coverage of these elements is dealt with as special piping and storage systems or under a category of healthcare facilities and medical gas and vacuum systems. Do not confuse medical uses for non-medical uses.
424 You are plumbing a room that will be accessible to psychiatric patients. What rule are you required to follow for piping and traps in these rooms?
Incorrect. Please choose another answer.
Plumbing pipes and traps installed in rooms that will be used by psychiatric patient must be concealed. (UPC 1303.2).
425 Indirect waste receptors for sterilizers must be trapped and vented.
Incorrect. Please choose another answer.
True - All receptors must be trapped and vented. (IPC 802.3; UPC 801.6).
426 Your job is to install a drinking fountain in a hallway of a healthcare facility. The hall will be used for patient transportation. Some patients will be in wheelchairs. Others will be in either hospital beds or gurneys. Which of the following requirements must you take into account when you install a drinking fountain in the hallway.
Incorrect. Please choose another answer.
Drinking fountains installed in corridors of healthcare facilities where patients are transported by wheelchair, gurney or hospital bed must be either fully recessed or flush mounted. (UPC 1303.1). Normally a drinking fountain can protrude into a hallway. This is not the case in this scenario. Not only are drinking fountains required to be fully recessed or flush mounted, so are valves associated with them. In very simple terms, you cannot install drinking fountains or their valves in any way that could come into contact with equipment used to transport patients.
427 All fixtures and fittings installed in psychiatric patient rooms must be ________.
Incorrect. Please choose another answer.
Fixtures and fittings used in psychiatric patient rooms are required to be vandal proof. (UPC 1303.2). This requirement is meant to protect patients and the plumbing system.
428 You are working with hospital plumbing and it involves connections for medical gases that are both flammable and nonflammable. The local plumbing code pertains only to medical gases that are nonflammable.
Incorrect. Please choose another answer.
True - The plumbing code pertains to medical gases that are nonflammable. This includes such gases as those used in exhalation anesthetic systems and vacuum piping systems. These systems can be found in hospitals, dental offices and other medical facilities.
429 Ice makers and ice storage chests installed in healthcare facilities are required to be installed _______.
Incorrect. Please choose another answer.
Ice makers and ice storage chests installed in healthcare facilities are to be installed in nurse stations or other areas with similar supervision. (UPC 1303.3). The location of ice producing and storage equipment must be protected from contamination. All ice facilities must be safe and hygienic.
430 Aspirators used for removing body fluids are required to be equipped with either collection bottles or ________.
Incorrect. Please choose another answer.
Aspirators used for removing body fluids must be equipped with collection bottles or similar fluid traps. (UPC 1303.5).
431 As you look through your code book you are seeking information on the storage of medical gases used in conjunction with plumbing connections between the gas containers and the equipment they serve. The special piping and storage system section of the plumbing code applies to any portable system and cylinder storage.
Incorrect. Please choose another answer.
False - The plumbing code does not apply to portable systems or cylinder storage in the section based on special piping and storage systems. (IPC 1202.1; UPC 1301.2).
432 Assume that you are installing a sterilizer in a healthcare facility. The fixture must discharge to a drainage system through an indirect waste. Which of the following lengths of piping could be used for the indirect waste?
Incorrect. Please choose another answer.
Indirect-waste drains that serve sterilizers are not allowed to have a developed length in excess of 15 feet. (UPC 801.6). Of the answer options, only 8 feet is an acceptable length. The piping must not have a smaller diameter than the size of the drain connection on the sterilizer being served. And, receptors must be located in the same room as the sterilizer that it is receiving waste from.
433 Vapor vents provided for sterilizers are allowed to __________.
Incorrect. Please choose another answer.
Not all sterilizers require vapor vents. Sterilizers that are required to have vapor vents are identified based on the manufacturer's requirements for sterilizer installation. (UPC 1303.4.2). When a vapor vent is required, it must extend independently to outside air, generally through a roof. These vents are not allowed to tie into any other venting system.
434 Water-supplied suction devices must comply with the same plumbing code regulations that apply to aspirators.
Incorrect. Please choose another answer.
True - Water-supplied suction devices are required to comply with the same plumbing code requirements that pertain to aspirators. (UPC 1303.5).
435 What is the minimum depth of a trap seal that serves a bedpan steamer when installing an indirect waste?
Incorrect. Please choose another answer.
Indirect waste piping that collects the waste from bedpan steamers must be trapped and the traps must maintain a trap seal of three inches in depth. (UPC 1303.4.1).
436 Aspirators are required to discharge their waste through which of the following?
Incorrect. Please choose another answer.
The plumbing code requires aspirators to discharge their waste through an air gap. A potable water supply for an aspirator is required to be equipped with a vacuum breaker or some other equivalent backflow protection. (UPC 1303.5).
437 You are about to begin installing plumbing for a medical vacuum system. Before you begin work you must be sure that plans and specifications for an installation of a medical gas or medical vacuum system has been provided to the local code officer and approved prior to the installation.
Incorrect. Please choose another answer.
True - The installation of medical gas or medical vacuum systems requires that plans and specifications be submitted to the local code enforcement officer. (IFGC 106.1; UPC 1304.3). Further, the code officer must approve the plans and specs and issue a permit before such systems can be installed.
438 Which NFPA standard do the codes reference for healthcare facilities and medical gas and vacuum systems?
Incorrect. Please choose another answer.
The IPC and UPC reference NFPA 99 for standards on medical gas and medical vacuum systems. (IPC 1202.1; UPC 1301.3).
439 The piping used in Med Gas OXY, MED and OXY/MED systems in connected by ______________.
Incorrect. Please choose another answer.
Brazing is the method used to connect pipes and fittings in Med Gas and vacuum systems. (NFPA 99 5.1.10.11.11; UPC 1323.11).
440 Of the following, who may install "Med Gas piping"?
Incorrect. Please choose another answer.
Only a master or journeyman plumber may install Med Gas if they have completed requirements set forth by NFPA 99 section 5.1.11.11. (UPC 1323.11.1).
441 In Med Gas systems, the exhaust from vacuum pumps shall be discharged into the following:
Incorrect. Please choose another answer.
Exhaust shall be discharged outdoors in a way which will minimize the hazard of noise and contamination to the environment. (NFPA 99 5.1.3.77.2; UPC 1313.2)
442 Tubing used in field installation for positive pressure Med Gas systems shall be made from the following:
Incorrect. Please choose another answer.
Type L copper may be used for pressures under 185 psi and Type K shall be used for pressures exceeding 185 psi. Type M is not rated with sufficient psi for positive pressure use. (NFPA 99 5.1.10.1.4; UPC 1318.4).
443 If the psi rating exceeds 185 psi in a positive pressure Med Gas system, what tubing is sufficient in rating to be installed?
Incorrect. Please choose another answer.
K copper is the only grade of copper suitable for pressures above 185 psi. (NFPA 99 5.1.10.1.4; UPC 1318.4)
444 Copper used in Med Gas systems is identified by the manufacturer. If the stamp is blue, it denotes which grade of copper?
Incorrect. Please choose another answer.
A blue stamp denotes Type L copper. (NFPA 99 5.1.10.1.7; UPC 1318.5).
445 Copper with a green stamp is used in a Med Gas system. What grade of copper does the color denote?
Incorrect. Please choose another answer.
A green stamp denotes the heavier grade of K copper. (NFPA 99 5.1.10.1.7; UPC 1318.5).
446 Vacuum tubing systems may be made of which of the following?
Incorrect. Please choose another answer.
All grades of copper (M, L, K and Stainless Steel) may be used for vacuum systems. (NFPA 99 1.10.2.1; UPC 1319.1).
447 The brazing alloy used to bond pipe joints with fittings must exhibit a melting temperature in excess of ______________.
Incorrect. Please choose another answer.
The melting temperature of the brazing alloy used to bond pipe joints must be in excess of 1,000° F or 538° C. (NFPA 99 5.1.10.4.1.1 - 5.1.10.4.1.3; UPC 1321.1).
448 Vacuum main lines cannot be less than which of the following?
Incorrect. Please choose another answer.
The minimum diameter pipe size permitted in vacuum main lines is 7/8" O.D. (NFPA 99 5.1.10.11.1.3; UPC 1323.1.1).
449 While brazing copper-to-copper joints in a Med Gas system, you must constantly purge the system with __________________.
Incorrect. Please choose another answer.
A constant flow of Nitrogen NF is needed to purge the system. (NFPA 99 5.1.10.4.5.1; UPC 1321.10).
450 You are about to braze copper tubing in a Med Gas system. To clean the exterior surface of the copper tubing in your preparations, you must use which of the following?
Incorrect. Please choose another answer.
Non-shedding abrasive pads must be used to clean copper tubing. All other materials are abrasive but leave residue. Surfaces must be wiped with a clean, lint-free white cloth. (NFPA 99 5.1.10.4.3.5; UPC 1321.8.3).
451 You have just finished cleaning the surfaces of copper tubing in a Med Gas system in preparation for brazing. The connections must be brazed within how many hours of cleaning?
Incorrect. Please choose another answer.
Joints must be brazed within 8 hours after cleaning. (NFPA 99 5.1.10.4.3.13; UPC 1321.8.9).
452 Flux can only be used in the brazing process when:
Incorrect. Please choose another answer.
Flux may only be to braze dissimilar metals. (NFPA 99 5.1.10.4.4.1; UPC 1321.9).
453 When purging the Med Gas system of ambient air prior to brazing, the percent of oxygen concentration should be below:
Incorrect. Please choose another answer.
Prior to brazing, the oxygen concentrator should read below 1.0%. (NFPA 99 5.1.10.4.5.5; UPC 1321.10.3).
454 You are inspecting brazed joints and find one that is defective. Assuming that it is the type of joint that is permitted to be repaired, how many times can it be reheated before being replaced?
Incorrect. Please choose another answer.
A defective brazed joint can be reheated only once for repair before it must be replaced. (NFPA 99 5.1.10.4.7.6; UPC 1321.12.4).
455 The ambient temperature around a buried service trench or tunnel used to contain Med Gas piping is limited to what degree maximum?
Incorrect. Please choose another answer.
130° is the maximum temperature permitted around the Med Gas piping system, indoors or out. (NFPA 99 5.1.10.11.3.3; UPC 1323.3.2).
456 Where there is no potential from surface loads or conditions, the minimum cover over buried Med Gas piping is _________________.
Incorrect. Please choose another answer.
If there is no potential for surface loads, 18" is the minimum cover permissible for buried Med Gas piping. (NFPA 99 5.1.10.11.5.5; UPC 1323.5.4).
457 You are working on a project that includes installing backfill cover over buried Med Gas piping. The area where the work is being performed is expected to incur freezing and surface loads. The frost line is at 32". What is the minimum backfill cover that must be used over buried Med Gas piping in this situation?
Incorrect. Please choose another answer.
Due to the conditions and surface loads, 36" is the minimum backfill cover in ditches containing Med Gas piping. (NFPA 99 5.1.10.11.5.5; UPC 1323.5.4).
458 The method used to provide a source of drainage, aspiration and suction to remove body fluids is called:
Incorrect. Please choose another answer.
The drainage, aspiration and suction of bodily fluids is removed into the vacuum system.
459 The purge gas flow rate is controlled by using a _______________________.
Incorrect. Please choose another answer.
The purge gas flow is controlled (be by) a pressure regulator, a flow meter or a combination of both. (NFPA 99 5.1.10.4.5.3-.4; UPC 1321.10.2).
460 Area alarm panels for Medical-surgical vacuum systems must indicate if the vacuum in the area drops below ______________________ mm gauge HgV.
Incorrect. Please choose another answer.
If vacuum in the area drops below 300mm (or 12 inches) gauge HgV, the alarm will sound. (NFPA 99 5.1.12.4.10.4; UPC 1324.5.10.1).
461 A qualified brazer is changing employers. The new employer is permitted to accept that brazer's qualification records if:
Incorrect. Please choose another answer.
Both a and b are the conditions which permit the new employer to accept the brazer's qualification records. (NFPA 99 5.1.10.11.11.6; UPC 1323.11.5).
462 The performance qualification of a brazer will remain in effect indefinitely, unless which of the following occurs?
Incorrect. Please choose another answer.
Unless there is a specific reason to question a qualified Brazer's ability or the Brazer does not braze for over six months with a qualified procedure, the Brazer is considered qualified. (NFPA 99 5.1.10.11.11.7; UPC 1323.11.6).
463 Which of the following does not apply to pipe labels marking Med Gas and vacuum systems?
Incorrect. Please choose another answer.
Pipes may be labeled less than 10', but never more than 20' apart. (NFPA 99 5.1.11.1.4; UPC 1323.13.3).
464 The chemical symbol for carbon dioxide is:
Incorrect. Please choose another answer.
CO2 is the correct symbol, or label, for carbon dioxide. (NFPA 99 Table 5.1.11; UPC Table 1305.1).
465 You are applying pipe labels to various pipes transporting Med Gas and vacuum lines within a system. Each gas or vacuum line has a specific color scheme for background/text which identifies itself. The proper label for the gas Helium will contain the following color scheme:
Incorrect. Please choose another answer.
Brown/white is the correct label for Helium. (NFPA 99 Table 5.1.11; UPC Table 1305.1).
466 The correct label for Nitrogen gas is _________________________.
Incorrect. Please choose another answer.
Black/white is the correct label for Nitrogen. (NFPA 99 Table 5.1.11; UPC Table 1305.1).
467 The correct label for instrument air is _________________________________.
Incorrect. Please choose another answer.
The correct label for instrument air is Red/White. (NFPA 99 Table 5.1.11; UPC Table 1305.1).
468 Which of the following statements is not consistent with the code on labeling Med Gas pipe?
Incorrect. Please choose another answer.
Med Gas piping may not be painted under the codes. (NFPA 99 5.1.11.1.5; UPC 1323.13.4).

Water Heaters 

469 The installation of a water heater requires a plumbing permit and a code inspection. It is necessary for a permit and a code inspection even when a water heater is being replaced in the exact location of an existing water heater. When you are installing a water heater which of the following must you allow for when you consider a suitable location for the installation of the fixture?
Incorrect. Please choose another answer.
Water heaters must be installed in such a way that they are accessible. It is not required for the fixture to be readily accessible. Other code requirements for the installation of a water heater include that each of the following is possible with minimum effort to gain access to the fixture:

• Accessible for observation
• Accessible for maintenance
• Accessible for servicing
• Accessible for replacement

(IPC 501.4; UPC 507.25).
470 You are installing a water heater for a two-family dwelling. The storage tank, if you install one and the water heater are required to have which of the following?
Incorrect. Please choose another answer.
Water heaters and storage tanks for domestic hot water must have the fixture's maximum working pressure clearly and indelibly attached in a permanent manner to the fixture. This can be in the form of a metal plate that is attached to the metal tank. Any form of marking must be clear, indelible and installed for permanent placement. (IPC 501.7; UPC Table 501.1(1); UL 174 43.5).
471 All water heaters are required to be certified by a third party and the fixtures must be installed in accordance with the requirements set forth by the manufacturer.
Incorrect. Please choose another answer.
True - The plumbing code relies on certification by third parties in the approval of water heaters suitable for use in plumbing systems. (UPC 501.5; UPC Table 501.1(1); UL 174, 45.1, 46.1). All water heaters must be installed in compliance with the plumbing code requirements. Additionally, the code demands that all installations be made in compliance with requirements set forth by the manufacturers of water heaters. (UPC 502.1; IPC 501.1).
472 Let's assume that you are responsible for the installation of a water-heating supply system. What type of equipment are you going to install on it?
Incorrect. Please choose another answer.
Automatic temperature controls are required on all water heaters and water heating systems for domestic hot water. (IPC 501.8; UPC 504.6). This control must be adjustable and allow for the temperature setting to be set to a minimum and a maximum level. Check local code requirements to determine the maximum allowable temperature for hot water being supplied for through domestic water distribution systems.
473 You have been asked to install a water heater in an attic. By code, water heaters cannot be installed in an attic.
Incorrect. Please choose another answer.
False - Water heaters are permitted by code to be installed in an attic. (IPC 502.3; UPC 508.4).
474 The installation of an electric water heater requires which of the following to be in close proximity to the fixture?
Incorrect. Please choose another answer.
All electric water heaters are required to be equipped with their own electrical disconnect switch. (IPC 504.3). The switch is required to be in close proximity to the water heater. When a gas-fired or oil-fired water heater is installed, there must be approved cutoff valves installed on the fuel piping in close proximity to the water heater.
475 When you are installing a water heater you will be required to install a cut-off valve on the inlet piping. The type of valve used should be a positive-sealing valve, such as a ball valve or gate valve. Using valves that rely on washers to operate can be a problem if the washer or the seat of the valve becomes defective. Where will you install the main cut-off valve on the inlet water supply?
Incorrect. Please choose another answer.
Valves installed on inlet piping for a water heater must be installed to serve only the water heater. Code requires that the valve be installed close to the water heater and on the same floor level that contains the water heater. (IPC 503.1). It is common practice to install the supply valve within 12 to 18 inches of the water heater. The valve is not allowed to interfere with the cold water supply to the remainder of the cold water distribution system.
476 Water heaters must be protected from back siphonage with the use of a "dip tube".
Incorrect. Please choose another answer.
True - A dip tube extends into the top of the water heater on the cold inlet. (IPC 504.1; UPC Table 501.1(1); UL 174, 15.2). It extends down to within 6"- 12" of the bottom. It has a small hole (about an 1/8") a few inches down from the top. If the piping is opened or broken and starts to siphon, the hole will allow the tank to draw air breaking the siphon. The dip tube also prevents the cold water from mixing with the outgoing hot water and tempering. If a water heater quits providing hot water quickly, it probably has a broken dip tube.
477 You are aware that the code permits the installation of water heaters in attics. However, there are access requirements that plumbers must be aware of. Just because you can get a water heater into an attic does not mean that the area of access meets code regulations. What is the minimum height measurement for the installation of a water heater in an attic?
Incorrect. Please choose another answer.
The minimum height requirement for a water heater being installed in an attic is 30 inches. (IPC 502.3; UPC 508.4).  A minimum of 24 inches in width is also required for the passageway floor. The service area surrounding the water heater is required to be level and solid. Such an installation requires open space in front of the water heater with dimensions of 30 inches deep and 30 inches wide. Additionally, an overflow pan with a drain pipe that is piped to a suitable location is routinely required when water heaters are installed above living space.
478 Water heaters require temperature and relief valves be installed. This is usually one valve that serves as protection against both excessive temperature and pressure. Water heaters are normally provided with a threaded location where the valve can be screwed into either the side or the top of the water heater shell. Knowing this, what is the maximum depth below the top of a water heater that a temperature and pressure relief valve can be installed?
Incorrect. Please choose another answer.
Temperature and relief valves installed on water heaters must be installed in such a way that the valve is actuated by water in the top six inches of the tank being served by the valve. (IPC 504.4.1; UPC Table 501.1; UL 174, 23.3). It is very important to confirm that the ratings for the valve being installed are within the working limits of the water heater being protected by a valve. For example, you would not install a valve with a rating of 150 psi if a water heater was rated for a maximum pressure of 125 psi. The maximum allowable temperature setting is usually 210 degrees F.
479 There is a risk of personal injury if a relief valve discharges into the open area of installation. To avoid this, a discharge tube must be installed on the valve and piped downwards. Under no circumstances are the discharge tubes allowed to connect directly to a drainage system. Normally, the pipe terminates somewhere along the side of the water heater it is serving. Measuring from the end of the discharge pipe to the top of the finished floor what is the maximum allowable distance?
Incorrect. Please choose another answer.
Discharge pipes that terminate above a floor must be extended to a point of not more than six inches above the floor. (IPC 504.6; UPC Table 501.1.(1); UL 174, 46.1). The piping must be maintained so that it can flow freely on a gravity basis. It is a code violation to install a cutoff valve on a discharge tube for a relief valve. If a discharge tube is intended to discharge into a drainage system, the connection between the discharge tube and the drainage system must be made with the use of an air break. The normal size of a discharge tube for a relief valve is 0.75 inch in diameter. The discharge piping for a drainage pan that a water heater sits is in one-inch in diameter.
480 A co-worker of yours told you that relief valves on water heaters are installed to control thermal expansion. Then you checked your plumbing code book during your lunch break. Was the information your co-worker gave you true or false?
Incorrect. Please choose another answer.
False - It is a code violation to use a relief valve in an effort to control thermal expansion. (IPC 504.4). The relief valve is a safety device only and it is required to be of a self-closing type.
481 Which if the following types of traps are required for installation on the discharge tubing of a relief valve for a water heater?
Incorrect. Please choose another answer.
Discharge tubing from a relief valve on a water heater is not allowed to be trapped at all. (IPC 504.6).
482 The end of a discharge pipe connected to a relief valve is required to be threaded on the termination end.
Incorrect. Please choose another answer.
False - It is against code requirements to use threaded pipe at the terminal end of a discharge pipe for a relief valve. (IPC 504.6). The reason for this is simple. If threads are present, a cap could be installed. If this were to happen the pipe would be unable to discharge. Therefore, the ends of discharge tubing and piping must not be threaded.
483 It is your job to install an electric water heater in an attic over a bedroom. The location of the water heater requires it to be provided with a safety pan. When you go to a supply house to acquire a safety pan for this installation what is the required minimum depth for a safety pan that you will install?
Incorrect. Please choose another answer.
Safety pans for water heaters are required to have a minimum depth of 1.5 inches. (IPC 504.7.1; UPC 507.5). The pan must be of a size that will hold the water heater being served and collect all condensate, leakage or discharge from the water heater. The pan can be made of 24-gauge metal or plastic. Drains for safety pans must extend to their point of termination with no reduction in pipe sizing. The waste from a safety pan can terminate over a suitably located indirect waste receptor or floor drain. Another option is for the piping to be extended to the outside of a building where the piping will terminate not less than six inches from ground level and not more than twenty-four inches above ground level. Discharge tubing from a relief valve is not allowed to discharge into a safety pan.
484 Discharge tubing attached to a relief valve for a water heater must be installed in such a way that occupants of the building being served by the water heater can observe the discharge of the tubing.
Incorrect. Please choose another answer.
True - All discharge tubing installed from the relief valves of water heaters are required to be installed in a way that occupants of the building housing the water heater can observe the piping. (IPC 501.4; UPC 608.5). This allows leaks from relief valves to be noticed so that proper service can be performed. When a relief valve is leaking it should be replaced.
485 All water heaters are to be certified by _______________________________.
Incorrect. Please choose another answer.
A third-party testing agency has no conflict of interest in certifying a heater as in the case of A, B and D. (UPC 501.5; UPC Table 501.1(1); UL 174, 45.1, 46.1). Plumbers have no authority or training to "certify" the construction of a water heater. Manufacturers have the knowledge of the product and quality control but cannot certify their product and say it's safe because of a conflict of interest. Same with wholesalers who buy from certain manufacturers based on cost. As with all plumbing products, certifications of quality and safety are determined by third-party testing agencies such as A.S.T.M. or A.N.S.I. or other "third-party" testing agencies that are independent from manufacturers, wholesalers, or buyers.
486 You are installing a water heater which is also being used as a space heater. In order to comply with Code, and limit the water temperature of the potable hot water distribution system, you must install which of the following?
Incorrect. Please choose another answer.
The thermostatic mixing valve must be installed to prevent the temperature of potable hot water distribution from exceeding 140°. (IPC 501.2).
487 Which temperature listed would be considered hot water for potable domestic use?
Incorrect. Please choose another answer.
The definition sections of the codes set forth at what temperatures water is considered "hot water": 110° IPC and 120° UPC.
488 Tankless water heaters are permitted to heat potable water to a maximum of __________ for domestic use.
Incorrect. Please choose another answer.
Tankless heaters have the same hot water limit requirements of tank-type water heaters for domestic use. (IPC 501.6).
489 Where is the maximum allowable working pressure of a storage tank and water heater required to be shown?
Incorrect. Please choose another answer.
Such markings shall be in an accessible position outside of the tank, permanently affixed. (IPC 501.7; UPC Table 501.1(1); UL 174 43.5).
490 A chimney has a factory-built flue. Can a gas water heater be connected to the chimney flue as an exhaust for combustion gases?
Incorrect. Please choose another answer.
A gas water heater may be connected to a chimney with a factory-built flue only if the flue is listed for such an installation. (IFGC 503.5.1; UPC 509.5.1).
491 Electric water heaters must conform to the requirements of which of the following?
Incorrect. Please choose another answer.
Electric water heaters must conform to the requirements of the applicable plumbing code (IPC or UPC) and NFPA 70. (IPC 502.1; UPC 508.2.2)
492 When piping a relief valve to the floor, a full port shut off valve should be installed in case the relief valve begins to drip.
Incorrect. Please choose another answer.
False - A valve must never be installed on a relief line. (IPC 504.4.1; 504.6).
 
You are installing a gas water heater in a new residential home. The heater is to be installed in a closet.
493 Which of the following is required to make your installation Code compliant?
Incorrect. Please choose another answer.
The installation of a vent for exhaust fumes, T&P valve, and provisions for combustion air are all required. (IPC 504.4; IFGC 501.2; UPC 504.1; 506.1).
494 You are installing the pipe which will provide combustion air to the closet where the heater is located. According to the one permanent opening method for combustion air, you should install the opening _____________________________.
Incorrect. Please choose another answer.
The required volume of combustion air for a gas-fired appliance in an enclosed closet or room must be within 12" from the top of the enclosure. (IFGC 304.6.2; UPC 506.4.2).
495 With respect to the free area of the opening needed to supply combustion air to a water heater, the required volume of combustion air must not be less than:
Incorrect. Please choose another answer.
50 cubic feet per 1,000 Btus is the minimum volume of combustion air needed. (IFGC 304.5.1; UPC 506.2.1).
496 You are figuring the free area of the opening needed to supply the combustion air to a water heater in an enclosure. The opening you have installed communicates freely with the outdoors. What is the minimum size in square inches of the opening needed to supply each 3000 btus of the heater?
Incorrect. Please choose another answer.
One square inch of free area per 3,000 Btu/h input rating is the minimum needed. (IFGC 304.6.2; UPC 506.4.2).
497 The minimum free area allowed for combustion air in an enclosure containing a gas water heater is:
Incorrect. Please choose another answer.
100 square inches is the minimum free area required and may require more, depending on Btu rating. (IFGC 304.5.3.1; UPC 506.3).
498 You are installing a pipe sleeve to provide combustion air using the one permanent opening method to an enclosure containing a water heater with a 36,000 Btu rating. This opening will directly communicate to a space that freely communicates with the outdoors. Using the formula of one square inch per 3,000 Btu/h required, what is the minimum size pipe needed?
Incorrect. Please choose another answer.
36K Btu requires 12 square inches of free area. To convert 12 square inches to area of round pipe, you must use formula πr2 to determine the area of a circle.

A 4" diameter pipe has radius = 2"2.

4" x 3.14 = 12.56 square inches.
499 You are installing a pipe sleeve to provide combustion air using the one permanent opening method to an enclosure containing a water heater with a 60,000 Btu rating. This opening will directly communicate to a space that freely communicates with the outdoors. Using the formula of one square inch per 3,000 Btu/h required, what is the minimum size pipe needed?
Incorrect. Please choose another answer.
A 60K Btu heater requires a minimum free area of 20 square inches. A 5" pipe sleeve gives 19.62 square inches and a 6" pipe sleeve gives 28.26 square inches. A 6" inch pipe has a radius of 3".

3" 2  = 9"
9" x 3.14 = 28.26 inches.
500 Relief valves shall not be discharged to which of the following:
Incorrect. Please choose another answer.
Relief valves shall not be discharged into a drip pan. (IPC 504.6; UPC 507.5).
501 Where gas water heaters are installed in residential garages, they shall be elevated a minimum of _________________ AFF.
Incorrect. Please choose another answer.
The codes direct the plumber to install water heaters no less than 18" above the floor. (IFGC 305.3; UPC 507.13).
502 In multi-story vent installations, vertical common vents for category 1 appliances must be what type of gas vent material?
Incorrect. Please choose another answer.
Only Type B gas vent material is permitted to be used for vertical common vents in multi-story vent installations. (IFGC 501.13, Table 503.4; UPC Table 509.4).
503 At minimum, how many feet above a draft hood or flue collar should a Type B vent terminate?
Incorrect. Please choose another answer.
Type B vent should terminate 5' above a draft hood or flue collar. (IFGC 503.6.6; UPC 509.6.1)
504 Gas tankless water heaters typically require _________ Btu/h input than tank-type domestic water heaters.
Incorrect. Please choose another answer.
Because tankless heaters heat water on demand and have no heated reserve water, they demand greater Btu input to heat water rapidly.
505 Which of the following is not required to be installed on top fed tank type and tank less water heaters?
Incorrect. Please choose another answer.
Bottom fed water heaters and bottom fed storage tanks connected to water heaters require a vacuum relief valve.
506 A vent from a gas water heater passes through an insulated assembly. What is required to be installed as a protective measure?
Incorrect. Please choose another answer.
Where a vent passes through an insulated assembly, an insulation shield must be installed between the vent and the insulation. (IFGC 502.4; UPC 509.6.1.1). The shield must be made of 26-gauge metal. The vent needs to terminate not less than 2 inches above the insulation and be secure in place to prevent displacement.
507 All of the following are requirements for discharge piping serving a relief valve, except:
Incorrect. Please choose another answer.
Relief valve discharge piping should not be trapped. (IPC 504.6).
508 You have been sent to install a tankless water heater in a newly constructed residence. The Code does not cover the installation issue you have on a tankless heater. In this situation, you should ____________________.
Incorrect. Please choose another answer.
Manufacturer's instructions take precedence where Codes or city officials may have limited knowledge or information on a particular manufacturer's equipment. (IPC 502.1; UPC 501.1).
509 Which of the following is required to install a gas water heater in a bedroom closet?
Incorrect. Please choose another answer.
Gas water heaters are not permitted to be installed in bedroom closets unless the closet door is gasketed or equipped with a solid-weather-stripping and has an approved or listed self-closing device. (IFGC 303.3; UPC 504.1).
510 Which of the following is not required to be installed by a plumber on an instantaneous tankless gas water heater that is to sanitize dishes?
Incorrect. Please choose another answer.
Some gas tankless water heaters are installed on exterior walls in recessed cans which vent directly to the atmosphere. (IFGC 501.8).
511 You plan on installing an exterior tankless water heater (100,000 btu/hr) beside a window which opens. What is the minimum lateral distance required between the window and the heater, upon installation?
Incorrect. Please choose another answer.
A minimum lateral distance of 12" would be required between a window and an exterior tankless water heater. (IFGC Table 503.8; UPC Table 503.8).
512 The minimum distance allowed from the top of an exterior tankless water heater and the soffit above it is_________.
Incorrect. Please choose another answer.
The minimum distance allowed from the top of an exterior tankless water heater and the soffit above it is to be installed as specified by the appliance manufacturer. (IFGC Table 503.8; UPC Table 503.8).
513 Your job requires that you remove an existing tank-type water heater with a 40,000 Btu rating and replace it with a tankless heater with a 199,000 Btu rating - which will exceed the maximum Btu load. How might you compensate for the increase in Btus in the most efficient, cost-effective, manner?
Incorrect. Please choose another answer.
Increasing the diameter brand line does not lower the demand of the new heater. Tapping into the gas line before the regulation will not affect the present Btu gas level but another regulator will be required downstream at the new heater. Increasing the p.s.i. will require regulators at all existing and new appliances but may be as cost-effective as tapping into an existing line before the regulator.

Recycling Gray Water 

514 Site locations for residential subsurface landscape irrigation systems are ___________.
Incorrect. Please choose another answer.
Site locations for residential subsurface landscape irrigation systems are regulated by state plumbing codes. While the federal Clean Water Act may apply in some circumstances where there is a reuse of waste water that threatens the nation's waters, it is generally will not factor into residential subsurface irrigation systems.
515 Which of the following is an acceptable use for the recycling of gray water?
Incorrect. Please choose another answer.
Water is a commodity. It is in limited supply. With this in mind there is more effort being extended to allow gray water to be used for some purposes. What is gray water? It is drainage water that does not contain waste particles of a sewage nature. In an effort to conserve water, gray water may be used to flush toilet and urinals. (IPC 1302.6.1; UPC 1505.1). It is also allowed to be used for subsurface landscape irrigation systems. (IPC 1302.11; UPC 1505.1).
516 Do you know which types of fixtures are allowed to provide gray water to gray-water drainage systems? Consider this scenario. You are plumbing a single-family residence. The home contains a dishwasher, a toilet, a bathtub and a kitchen sink. Which of these fixtures are allowed to be drained into a gray-water drainage system?
Incorrect. Please choose another answer.
Dishwashers, kitchen sinks and toilets are not allowed to contribute to a gray-water drainage system. (IPC 1302.2.1; UPC 209). In this scenario, only the bathtub can be allowed to discharge its waste into a gray-water drainage system.
517 Which of the following fixtures are allowed to discharge into a gray-water drainage system?
Incorrect. Please choose another answer.
All of the listed fixtures can be discharged into a gray-water holding system or drainage system. (IPC 202; UPC 209). Other fixtures that are allowed to discharge into a gray-water drainage system include bathtubs and showers. The key is not to discharge a fixture that is expected to expel any solids or sewage waste into a gray-water distribution system. This removes the option for urinals, water closets, kitchen sinks and dishwashers from being used to recover gray water from in common systems.
518 Collection reservoirs for gray-water must be made of approved materials. To comply with this, a gray-water collection reservoir is required to be ___________.
Incorrect. Please choose another answer.
Collection reservoirs are required to be durable, nonabsorbent and corrosion resistant--not corrosion proof. (IPC 1301.9.2; UPC 1503.9). The reservoir must be closed with a gas-tight seal. An access opening is required that will allow for routine inspections to be performed.
519 Gray water that enters a collection reservoir must be ________.
Incorrect. Please choose another answer.
Any gray water going into a gray-water collection reservoir is required to be filtered. (IPC 1302.5; UPC 1506.10.5). This is required as a means of blocking solids from entering the collection reservoir. While the fixtures allowed for the recycling of gray water should not be transporting solids, there is always a possibility that some type of solid could find its way into the drainage water. The filters stop these impurities from reaching the collection of gray water that will be recycled.
520 Which of the following is required to use with gray water collected in a reservoir?
Incorrect. Please choose another answer.
Filter media suitable for filtering gray water prior to it entering a gray-water collection reservoir is required. These filters are needed to ensure that only gray water is entering the collection point for later distribution to approved uses. After the filter, disinfection is required. (IPC 1302.6; UPC 1506.10).
521 Under what circumstances can nonpotable water piping be in the same trench as potable water piping?
Incorrect. Please choose another answer.
Non-potable water piping may be in the same trench as potable water piping as long as the potable water piping is not less than 12 inches above the non-potable water piping. (IPC 1301.11; UPC 1502.4). The piping must be made of material permitted by the code.
522 In subsurface irrigation systems, what is the minimum depth of the aggregate placed above the drain piping?
Incorrect. Please choose another answer.
A minimum of two inches of aggregate must be placed on top of the piping in subsurface irrigation systems. (IPC 1403.1.5; UPC Table 1504.7.3).
523 Which of the following is not permitted to be installed with a gray water storage tank overflow pipe?
Incorrect. Please choose another answer.
The codes prohibit the installation of a shutoff valve on overflow piping from a gray water storage tank. (IPC 1301.9.5; UPC 1503.9.1, 1603.9). Overflow piping may connect to sewer drains and have cleanouts.
524 When water pressure in a reclaimed water system is in excess of ______ psi a pressure reducing valve is required to be installed to reduce the pressure to a level below the maximum allowable pressure.
Incorrect. Please choose another answer.
When the water pressure of graywater being supplied to a residence for toilets exceeds 80 psi a pressure reducing valve is required to reduce the pressure to a point at or below 80 psi. (IPC 1304.2; UPC 1505.5).
525 Overflow pipes are required to be installed on every gray-water collection reservoir. As a working plumber you must demonstrate the ability to size this overflow pipe. For this example, assume that the discharge pipe conveying gray water to a collection reservoir has a 3-inch diameter and the maximum capacity of the water supply line to the tank is 150-200 gallons per minute. What is the minimum diameter of an overflow pipe that you must install?
Incorrect. Please choose another answer.
Under the UPC, the overflow pipe must have a minimum diameter that is equal to the discharge pipe that is emptying into a gray water collection reservoir. (UPC 1503.9.1(6)). Under the IPC, the size of the overflow pipe depends on the maximum capacity of the water supply line to the tank. (IPC Table 606.5.4, 1301.9.5). An overflow pipe can be larger than the discharge pipe, but this is not a requirement.
526 On which of the following will the estimation of gray water discharge be based?
Incorrect. Please choose another answer.
The estimation of gray water discharge is based on the gallons of use per day per occupant number based on the type of fixtures connected to a system. This is derived by use of an equation. The equation is as follows:

C = A x B
A = the number of occupants
B = estimated flow demands per occupant
C = estimated gray water discharge based on the total number of occupants
(IPC 1402.1; UPC 1503.8).
527 What minimum size filter must be used with on-site treated nonpotable water utilized for water closet and urinal flushing?
Incorrect. Please choose another answer.
The filter cannot allow the passage of particles larger than 100 microns. (IPC 1301.2.2; UPC 1506.10.5).
528 What is the maximum amount of time that untreated gray water is allowed to be retained for use to flush a toilet or urinal?
Incorrect. Please choose another answer.
The maximum allowable time for the retention of untreated gray water that will be used to flush toilets or urinals is 24 hours. (IPC 1302.6). Holding water for long periods of time can result in the growth of bacteria. This bacteria is not wanted in the plumbing system. For example, green water in a toilet tank is not appealing and could present health hazards. When a gray water recycling system is sized properly the water retained in a collection reservoir would be balanced to the fixtures served and the normal daily use of the fixtures will draw down from the reservoir often enough to avoid prolonged water storage.
529 Which of the following is a design consideration for the installation of a subsurface irrigation system?
Incorrect. Please choose another answer.
An initial design consideration for the construction of a subsurface irrigation system is the effective irrigation area or absorption area needed to handle the gray water discharge. (IPC 1403.1.1; UPC 1504.2). Under the IPC, the total absorption area required is calculated from the estimated daily graywater discharge and the design-loading rate based on the percolation rate of the site. The required absorption area will equal the estimated graywater discharge divided by the design-loading rate. Under the UPC, the effective irrigation area is based on the type of soil at the site and the estimated graywater discharge. The UPC provides a chart of six soils with their maximum absorption capacities.
530 You are spacing out the subsurface irrigation piping into lines of pipe and initially place the piping two feet apart. What distance from center to center of the piping complies with the code?
Incorrect. Please choose another answer.
When constructing a subsurface irrigation system, the piping should be evenly spaced and be no closer than 3 feet (IPC) or 4 feet (UPC) apart. (IPC 1403.1.3; UPC Table 1504.73.). The piping should not be spaced more than five feet apart. (IPC 1403.1.3.).
531 You are constructing a subsurface irrigation system in a back yard that has a slope. Which of the following slopes are within the maximum limits for the grade of distribution piping in a nonpotable water subsurface irrigation system?
Incorrect. Please choose another answer.
The slope of distribution piping in gray water subsurface irrigation systems cannot exceed 3" per 100 feet (UPC) or 4" per 100 feet (IPC). (IPC 1403.2; UPC Table 1504.7.3).
532 Licensed plumbers are required to know what forms of disinfection are allowable for the use with gray water that will be used to flush toilets and urinals. With this said, assuming that you are the plumber who has to decide what to use as a suitable and approved disinfection, which of the following would you choose?
Incorrect. Please choose another answer.
Disinfectants allowed for the use of disinfecting gray water that will be used for the flushing of toilets or urinals may include chlorine or ozone. (IPC 1301.2.1; UPC 1506.10.2). These are the only disinfectants identified and approved by the plumbing code.
533 Gray water is required to be dyed which of the following colors?
Incorrect. Please choose another answer.
Gray water no longer is required to be dyed. (IPC 1401.6). Under previous codes, it was to be dyed blue or green before it could be reintroduced into a plumbing system.
534 What should be done when specifications for a job require a gray-water flushing system for toilets and urinals, but the system could fall short of capacity requirements?
Incorrect. Please choose another answer.
When there is a risk of inadequate gray-water supply you should plan on supplementing the gray-water with potable water. (IPC 1301.9.4; UPC 1505.4). Any water supply that delivers potable water to a gray water system must be protected by a backwater preventer. (IPC 1301.9.4; UPC 1505.4).
535 Is gray water used for subsurface landscape irrigation required to be dyed and, if so, with which color?
Incorrect. Please choose another answer.
Gray water that is used for subsurface irrigation is not required to be dyed. (IPC 1401.6). No artificial color is required. Collection reservoirs used to collect water for subsurface landscape irrigation is not required to be fitted with a potable water source to maintain minimum capacities. Essentially, gray water used for irrigation can be used when it is available but it is not required to be available in any particular quantity.
536 Subsurface irrigation systems that use gray water for irrigation are required to be installed at elevations which are higher than the surface grade of any potable water well.
Incorrect. Please choose another answer.
False - The exact opposite is true. Such systems must be installed lower than the surface grade of any water well or reservoir. (IPC 1301.11; UPC 1502.4). This rule applies to water sources on adjoining land. In short, the gray water cannot be used at an elevation that may allow it to disperse into potable water sources and contaminate them.
537 What is the minimum horizontal distance that must be placed between a gray water storage tank and a water well?
Incorrect. Please choose another answer.
Nonpotable water storage tanks must be located at least 50 feet away from water wells. (IPC Table 1302.71; UPC Table 1503.4).
538 Water piping used to distribute recycled gray water must be ________.
Incorrect. Please choose another answer.
Water piping that is used to distribute gray water as recycled water to a reuse site must be identified as non-potable water in an approved manner. (IPC 1301.3; UPC 1505.10). In all cases piping carrying gray water must be clearly identified as not being potable water.
539 What is the maximum size of aggregate that is used when backfilling a seepage trench/filter in a subsurface irrigation field?
Incorrect. Please choose another answer.
Seepage trenches in subsurface irrigation fields require a maximum size of aggregate that ranges in size from .5 to 2.5 inches in diameter. (IPC 1403.1.5; UPC 1504.7.2).
540 What is the minimum pipe diameter allowed for distribution piping in a subsurface irrigation system?
Incorrect. Please choose another answer.
The minimum diameter allowed for distribution piping in a seepage trench or bed in a subsurface irrigation system is three inches. (IPC 1403.2; UPC 1504.7.1).
541 Recycled gray water may be used to supply the following fixtures, except:
Incorrect. Please choose another answer.
Toilets, urinals and subsurface irrigation systems can be supplied by recycled gray water, thereby conserving the potable water supply. (IPC 1302.6.1; UPC 1505.1). It cannot supply bath water.
542 Which of the following fixtures shall not discharge its waste into a gray water system?
Incorrect. Please choose another answer.
A urinal and toilet must drain waste into a sanitary sewer or septic system. (IPC 1302.2.1; UPC 209).
543 What type test is used to determine the permeability of the soil for a proposed absorption system?
Incorrect. Please choose another answer.
A percolation test is used. A test hole is to be dug or bored 4"-8" in diameter. The bottom of the hole is scratched to loosen the natural soil. 2" of gravel is then added to the bottom. Water is then added to 12" above the bottom. The time for the water to seep away is the general idea of the test.
544 Storage tanks for rainwater that are in direct sunlight must be made of which of the following material?
Incorrect. Please choose another answer.
The codes require that rainwater storage tanks located above ground, and in direct sunlight, be made of an opaque, UV resistant material. (IPC 1301.9.1; UPC 1603.7). This is to prevent algae growth. Storage tanks may be made of fiberglass, concrete or galvanized steel. If the tank will be behind a sun barrier or inside a building, the requirement for an opaque material may not apply.
545 When an overflow drain discharges to a storm drainage system, what must be installed on the overflow drain piping?
Incorrect. Please choose another answer.
Overflow drains must be protected by backwater valves to protect the drain piping from backflow. (IPC 1303.11.1; UPC 1603.9). Shutoff valves are not permitted.
546 Rainwater catchment systems use _______________ to gather the water.
Incorrect. Please choose another answer.
Rainwater catchment systems use roof surfaces or other manmade above ground collection surfaces. (IPC 1305.5; UPC 1603.3).
547 What is the minimum size distribution piping in a subsurface irrigation system?
Incorrect. Please choose another answer.
Distribution piping shall not be less than 3". (IPC 1403.2; UPC 1504.7.2).
548 Which of the following statements is NOT true concerning the use of gray water to supply systems for flushing toilets and urinals?
Incorrect. Please choose another answer.
Gray water supplying systems for flushing toilets and urinals must be disinfected. (IPC 1301.6.1; UPC 1506.10.2).
549 To calculate the daily discharge amount of gray water for residential use to size a subsurface absorption system, you must know the number of ___________________:
Incorrect. Please choose another answer.
Estimated gray water discharge is calculated by number of occupants and flow demands for each. (IPC 1402.1; UPC 1503.8).
550 In residential applications for determining gray water flow demands for each occupant, the rate for each occupant using showers, bath tubs, and lavatories is _______ gallons per day.
Incorrect. Please choose another answer.
25 gallons per day, per occupant, is estimated for gray water flow demands in residential applications for showers, bath tubs and lavatories. (IPC 1402.1; UPC 1503.8.1).
551 What is the estimated flow demand, in gallons per day, for each occupant of a residential home for the use of clothes washer or laundry trays?
Incorrect. Please choose another answer.
15 gallons per day for the use of clothes washers or laundry trays, per occupant, is estimated. (IPC 1402.1; UPC 1503.8.1).
552 You are determining the minimum number of occupants in a residential home to assess the daily gray water discharge amount to size a subsurface absorption system. The home has four bedrooms. What is the total number of occupants for your formula?
Incorrect. Please choose another answer.
To calculate the number of occupants, the codes look to the number of bedrooms. (IPC 1402.1; UPC 1503.8.1). The first bedroom is attributed with two occupants. Additional bedrooms are given one additional occupant. So, a four-bedroom house will have five occupants for the formula for system sizing.
553 You are calculating the daily discharge amount of gray water for residential use to size a subsurface gray water absorption system. Assume that a single-family residence has 4 occupants. The home has 1 shower, 2 bathtubs, 3 lavatories and 1 clothes washer. What is the total amount of gray water, per day, draining into the receptor?
Incorrect. Please choose another answer.
To calculate the answer, you must add the gallons per day per occupant attributed to each fixture. A shower, bathtub and lavatory get 25 gallons per day per occupant and a clothes washer gets 15 gallons per day per occupant.

4 occupants x 25 gallons per day for showers, bathtub and lavatory = 100 gallons per day
4 occupants x 15 gallons per day for the clothes washing machine = 60 gallons per day
Total: 160 gallons per day

(IPC 1402.1; UPC 1503.8.1).
554 You are sizing a subsurface absorption system and calculating the gray water discharge amount that can be expected at the single-family residence. Assume that the residence has 5 occupants. Only the clothes washer is connected to the gray water system. What is the total amount of gray water, per day, draining into the system?
Incorrect. Please choose another answer.
To calculate the gray discharge, a clothes washer gets 15 gallons per day per occupant.

5 occupants x 15 gallons per day = 75 gallons per day

(IPC 1402.1; UPC 1503.8.1).
555 In commercial applications, the gray water discharge estimated flow demand can be based on:
Incorrect. Please choose another answer.
Water use records can be used to calculate the estimated flow demand for gray water discharge in commercial applications. (IPC 1402.1; UPC 1503.8.2). Under the IPC, discharge of fixtures not discharging gray water are subtracted from the water use records to get the gray water discharge estimated flow demand. An estimated flow demand can also be calculated based on the type of fixtures discharging to the system.
556 You are installing an irrigation disposal field from a gray water reservoir. What is the minimum horizontal distance that must be between the absorption area and building?
Incorrect. Please choose another answer.
Two feet from the building is the minimum horizontal distance required of the disposal field of an absorption system. (IPC Table 1402.3; UPC Table 1503.4).
557 Gray water irrigation disposal fields should be a minimum horizontal distance of at least how many feet from a septic tank?
Incorrect. Please choose another answer.
Five feet is the minimum horizontal distance from a disposal field to a septic tank. (IPC Table 1402.3; UPC Table 1503.4).
558 Water treatment is not required for gray water used for irrigation. Why is this the case?
Incorrect. Please choose another answer.
The chemicals used in disinfection would be detrimental to the vegetation.
559 You are installing a gray water adsorption field. Nearby is a water well. At a minimum, how far away from the water well does the gray water absorption disposal field need to be to be code compliant?
Incorrect. Please choose another answer.
The minimum horizontal distance between a gray water absorption disposal field to a water well is 100'. (IPC Table 1402.3; UPC Table 1503.4).
560 Potable water may be connected to a non-potable water source under what condition?
Incorrect. Please choose another answer.
When there is a risk of inadequate gray-water supply, potable water can be used makeup water. (IPC 1301.9.4; UPC 1505.4). Any water supply that delivers potable water to a gray water system must be protected by a backwater preventer. (IPC 1301.9.4; UPC 1505.4).
561 What color shall non-potable water pipes be marked?
Incorrect. Please choose another answer.
Non-potable water lines shall be clearly marked in purple. (IPC 608.9.2; UPC 601.3.3).
562 You are installing a gray water irrigation disposal field. A stream runs into a lake near the owner's home. At a minimum, how far from the stream and lake must the disposal field be placed?
Incorrect. Please choose another answer.
Fifty feet is the minimum horizontal distance from streams or lakes to a gray water irrigation disposal field. (IPC Table 1402.3; UPC Table 1503.4).
563 Which of the following must be provided to the building owner of a graywater reuse system by the system designer?
Incorrect. Please choose another answer.
The codes require the system designer to provide the owner of the building an operation and maintenance manual. (IPC 1302.13; UPC 1501.6).
564 On what basis does a reclaimed water system need to have its backflow prevention assemblies inspected?
Incorrect. Please choose another answer.
A reclaimed water system is required to have its backflow prevention assemblies inspected annually. (IPC 312.11.1, 1304.4.2; UPC 1502.3).

Fuel Gas 

565 What type of gas piping fittings and connections may be concealed?
Incorrect. Please choose another answer.
When fittings and connections installed on gas piping is to be concealed, they must be of an approved type. The codes permit threaded couplings, brazed fittings, welded fittings and listed compression fittings. (IFGC 404.5; UPC 1210.4.1).
566 Gas piping installed in a laundry chute ____________.
Incorrect. Please choose another answer.
Gas piping in not allowed to be installed in laundry chutes, dumbwaiters, air-circulating ducts or elevators. (IFGC 404.3; UPC 1210.3.4.). The chutes, shafts and ducts can transport gas to various locations in a building if a leak should occur. Therefore, it is inappropriate to install gas piping in a location that could distribute gas beyond the location of the leak.
567 When gas piping is installed outdoors and underground, the minimum amount of cover is:
Incorrect. Please choose another answer.
Outdoor pipping must be covered for protection from traffic. (IFCG 404.12; UPC 1210.1.1).
568 Non-metallic gas piping installed underground must ____________.
Incorrect. Please choose another answer.
Non-metallic gas piping installed underground must be provided with a tracer. (IFCG 404.17.3; UPC 1210.1.72). The tracer is usually a metal wire with a minimum conductor size of 18 AWG. Since the piping is plastic, it cannot be found with metal-detecting equipment. When a wire is installed alongside the piping, the metal in the conductor can be detected to determine the piping location. The tracer should rise from each end of the piping trench to a point above ground.
569 Which of the following mediums is not allowed for use in testing gas pipe installations?
Incorrect. Please choose another answer.
Oxygen is not allowed to be used when testing a gas piping system. (IFCG 404.6.2; UPC 1213.16).
570 When a wet-gas system is installed, it is required to _____________.
Incorrect. Please choose another answer.
Gas piping that carries wet gas is required to have drip legs installed at low points. (IFGC 408.2; UPC 1210.7). The length of the drip leg is usually six to eight inches. All drip legs are required to be readily accessible. The purpose of the drip leg is to collect condensation that accumulates so that it is not held in the gas delivery system.
571 What is the smallest pipe size that can be used with Schedule 40 metallic piping in fuel gas systems?
Incorrect. Please choose another answer.
The minimum size for Schedule 40 metallic piping in fuel gas systems is ½". (IFGC Table 402.4(1); UPC Table 1215.2(1)).
572 When flow controls are installed on gas piping, they _____________.
Incorrect. Please choose another answer.
Flow controls on gas systems are installed to keep the operating pressure of the system lower than the supply pressure for the system. (IFGC 410.1; UPC 1208.3.3). These devices prevent excessive pressure from the distribution system. They must be approved and suitable for both the inlet and outlet gas pressure for the application. The flow controls must be readily accessible.
573 You are installing a cooking range that uses fuel gas and must install a shutoff valve. Which of the following designs comply with the code for installation of shutoff valves with an appliance?
Incorrect. Please choose another answer.
Only the answer on accessibility complies with the code. Shutoffs must be accessible and it is acceptable to place it behind a removable panel. A shutoff valve must be within 6 feet of the appliance and be located upstream of a connector or union. (IFGC 409.5.1; UPC 1212.6).
574 What type plastic can be used for fuel gas piping?
Incorrect. Please choose another answer.
High density polyethylene (HDPE) is approved for underground gas piping. (IFGC 403.5; UPC 1208.5.4). It is desirable because it is very resilient, resists breaking and does not rust.
575 How should approved polyethylene plastic fuel gas piping be marked?
Incorrect. Please choose another answer.
When polyethylene plastic piping is used for fuel gas piping, the piping must be marked "Gas" and "ASTM D2513". (IFGC 403.5; UPC 1208.5.4). Polyamide pipe is required to be marked "Gas ASTM D2945".
576 You have completed a minor repair on a cooking range fuel gas line that has already been in service. Which of the following is the next step?
Incorrect. Please choose another answer.
No pressure test is necessary on minor repairs, but a leak test must be performed with a non-corrosive leak-detecting fluid or other leak detecting method. (IFGC 406.1.2; UPC 1213.1.2).
577 Natural gas systems must be able to be tested, inspected and approved by the plumbing authority. A natural gas line in a single-family home is being tested. Which of the following time periods meet the duration requirement for the tests under the code?
Incorrect. Please choose another answer.
A 15 minute test would meet the code requirements for testing gas lines. (IFGS 406.4.2 - not less than 10 minutes; UPC 1213.3 - not less than 15 minutes).

Math 

578 Which of the following is an improper faction?
Incorrect. Please choose another answer.
The fraction is improper because it has a top number larger than (or equal to) the bottom number. The top number (the numerator) is the number of parts we have. The bottom number (the denominator) is the number of parts the whole is divided into.
579 Which of the following fractions is matched with an incorrect decimal?
Incorrect. Please choose another answer.
1/8 equals 0.125. Divide 1 by 8 and you get 0.125.
580 What is the volume of a cylinder that is 8 inches in diameter and 12 inches high?
Incorrect. Please choose another answer.
Volume = π x Radius² x Height
v = 3.14 x 4 x 4 x 12
v = 3.14 x 16 x 12
v = 602.88 cubic inches
581 How many gallons will a tank hold if the tank contains 8,850 cubic inches?
Incorrect. Please choose another answer.
Gallons = cubic inches ÷ 231
Gallons = 8,850 ÷ 231
Gallons = 38.312
582 How much fall would you need at 1/8 of an inch per foot fall in a 90 foot run?
Incorrect. Please choose another answer.
Drop = Pitch x Run
Drop = 1/8 x 90
Drop = .125 x 90
Drop = 11.25 inches per foot fall
583 The centerline of a pipe and fittings by which the pipeline is measured is known as the ________.
Incorrect. Please choose another answer.
The measured distance is the required length of pipe that is needed less the fitting take off.
584 What is the pitch of a pipe with a run of 86 feet and a 1 foot drop?
Incorrect. Please choose another answer.
Pitch = Drop ÷ Run
Pitch = 1 ÷ 86
Pitch = 0.012
Pitch = 1/8 inch per foot
Any decimal between 0.094 - 0.156 is the equivalent of a 1/8 of an inch per foot in plumbing terms.
585 A sewer is installed with a 2 percent fall per foot and has a run of 200 feet. How much drop will be required?
Incorrect. Please choose another answer.
Drop = Percent of Fall x Run
Drop = 2 percent x 200
Drop = .02 x 200
Drop = 4 feet
586 A sewer line has an offset of 6 feet and 1/8 bends are used for the offset. What is the length of pipe that you will need?
Incorrect. Please choose another answer.
Diagonal = 1.414 x Offset
Diagonal = 1.414 x 6
Diagonal = 8.484 feet
587 You are trying to locate the restroom wall that will receive the plumbing waste pipes. You refer to the plumbing drawing and note the scale is ... of an inch per foot. Your ruler measures a length of 14 ¼ inches and your scale indicates ... per foot fall. What is the length of the wall?
Incorrect. Please choose another answer.
Actual Length = Plan Measurement ÷ Scale
Actual Length = 14.25 inches ÷ .125
Actual Length = 114 feet
588 How many 4 inch pipes will it take to replace an 8 inch pipe?
Incorrect. Please choose another answer.
Ratio = Large Diameter Squared ÷ Small Diameter Squared
Ratio = 64 ÷ 16
Ratio = 4 pipes
The formula used has been devised from the inside surface area between the 4 and 8 inch pipe as well as friction loss due to the smaller pipe. The ratio between larger diameter squared and small diameter squared has been considered in this conversion.
589 What is the amount of lead needed to caulk 240 3 inch joints if each joint requires ¾ pounds of lead for each inch in diameter?
Incorrect. Please choose another answer.
Amount of Lead = Diameter x Weight in Pounds Per Joint x Number of Joints
Amount of Lead = 3 x ¾ x 240
Amount of Lead = 3 x .75 x 240
Amount of Lead = 540 Pounds
590 What is the angle made when you offset a sewer with a 1/8 bend?
Incorrect. Please choose another answer.
Degree of Angle = Fitting x 360 Degrees
Degree of Angle = 0.125 x 360 Degrees
Degree of Angle = 45 degrees
591 What is the total pressure in pounds per square inch (psi) on a 6 inch diameter test plug with a water head of 15 feet?
Incorrect. Please choose another answer.
Pressure = Height x Amount of pressure exerted at base of a one foot stack
P = 15 x .434
P = 6.51 psi
592 Find the area of a plug with the diameter of 10 inches.
Incorrect. Please choose another answer.
Area = π x Radius²
Area = 3.14 x 5 x 5
Area = 78.5 square Inches
593 What is the pressure in pounds per square inch at the base of a 4 inch soil stack that is 45 feet in height?
Incorrect. Please choose another answer.
Pressure = Height x Amount of pressure exerted at base of a one foot stack
P = 45 x .434
P = 19.53 psi
594 What head of water will produce 35 psi?
Incorrect. Please choose another answer.
Head of water = psi ÷ Amount of pressure exerted at base of a one foot stack
Head of water = 35 ÷ .434
Head of water = 80.645
595 Determine the pounds of pressure on a 4 inch test plug in a stack with a head of 17 feet of water.
Incorrect. Please choose another answer.
Pressure = Height x Amount of pressure exerted at base of a one foot stack
P = 17 x .434 = 7.378
P = 3.14 x 2 x 2 = 12.56 (The diameter of the test plug)
P = 12.56 x 7.387
P = 92.78 psi
596 A job requires 200 pounds of lead and you figure that there will be 6 percent waste. What is the total amount of lead you need to order?
Incorrect. Please choose another answer.
200 pounds x .06 percent = 12 pounds waste
200 pounds + 12 pounds = 212 pounds
597 Convert the faction 3/8 to a percentage.
Incorrect. Please choose another answer.
3 ÷ 8 = .375
.375 x 100% = 37.5%
598 Convert the faction 3/5 to a percentage.
Incorrect. Please choose another answer.
3 ÷ 5 = 0.6
0.6 x 100% = 60%
 
599 You got a deal on lead that is 20% less than the going rate which is $150.00 for the quantity. How much will you pay for the lead?
Incorrect. Please choose another answer.
Reduction in price = $150 x 20% = $30
$150 - $30 = $120.00
600 Add the following fractions: 1 7/8 + 5 ¾ =
Incorrect. Please choose another answer.
1 7/8 + 5 ¾ =
1 7/8 + 5 6/8 = 6 13/8 = 7 5/8
601 Subtract the following factions: 13 ½ - 9 ¼ =
Incorrect. Please choose another answer.
13 ½ - 9 ¼ =
13 2/4 - 9 ¼ = 4 ¼
602 Convert 0.625 to a fraction of an inch.
Incorrect. Please choose another answer.
.625 x 16 = 10
   1      16    16     8
603 You have an offset of 24 inches and you are making a 45° offset. What is the travel length?
Incorrect. Please choose another answer.
Travel Length = constant x offset
t = 1.414 x 24 inches
t = 33.93 inches
1.414 is a constant that is multiplied by the offset to get a 45 degree diagonal in pipe length. The 45 degrees offset is the most common offset used in the plumbing industry.
 
604 What angle is made when you offset a sewer with a 1/16 bend?
Incorrect. Please choose another answer.
Degree of Angle = 1/16 x 360 degrees
Degree of Angle = .063 x 360 degrees
Degree of Angle = 22.68°
605 What is the circumference of a tank that is 32" in diameter?
Incorrect. Please choose another answer.
To solve for the circumference of a circle, you use the following formula with pi:
 
3.14 x diameter = circumference
 
3.14 x 32” = 100.48”
606 How much does a full 50-gallon water heater weigh? (assume the heater weighs 210 lbs. empty)
Incorrect. Please choose another answer.
Water weighs 8.34 lbs. per gallon.
 
50 lbs. x 8.34 lbs/per gallon = 417 lbs. with 50 gallons
417 lbs + 210 lbs. = 627 lbs.